Chris Budeski
From:Chris Budeski <chris@mad-eng.com>
Sent:Tuesday, March 22, 2022 4:14 PM
To:'Mikaela Schultz'
Subject:21358 - Tidal Wave Auto Spa
Mikaela:
Below is the response, shown in blue, from the applicant’s representative, John LaPointe, regarding anticipated
peak wastewater discharge from the proposed Tidal Wave Car Wash development.
The City’s hydraulic model has shown a downstream section of sewer that is near capacity, which may
need to be upgraded given this particular developments type of use. The applicant is encouraged to
submit certified peak-flow estimates to the engineering department (Mikaela Schultz) prior to submitting
a site plan application to verify the sewer requirements. Peak sanitary flow rate is 50 gpm.
Please review the information submitted at your earliets convenience. If you have any questions or need
additional information please feel free to contact me.
Sincerely:
Chris G. Budeski, PE
Madison Engineering, LLC
895 Technology Boulevard, Suite 203
Bozeman, MT 59718
406.586.0262 office
chris@mad-eng.com