HomeMy WebLinkAboutMDT - Bozeman TCC Area Projects Report_10-24-22Bozeman Area Transportation Coordinating
Committee
Wednesday, October 26, 2022
Bozeman Area- Construction Phase
Gallatin Canyon VMS:
➢ Adds permanent electronic message boards in the Gallatin Canyon.
➢ Awarded to Stillwater Electric.
➢ Construction expected to be completed in fall 2022.
Bozeman Rest Area Relocation, aka Headwaters Rest Area:
➢ Public/Private Partnership project to relocate the RA currently located on
N. 19th in Bozeman north of I-90 Exit 274 near Three Forks.
➢ Awarded by Transportation Commission in April 2021.
➢ Construction began in August 2021
➢ RA completion, and property transfer expected in spring of 2023.
Bozeman Hill Ditch Cleaning: (Maintenance)
➢ I-90 EB and WB, RP 313- 323
➢ Remove and recycle excess sanding materials in roadway ditches.
➢ 75,000 cubic yards of material recycled to date.
Dry Creek Road and Manhattan to Belgrade: (Maintenance)
➢ Tied Chip seal projects
➢ Dry Creek Road- RP 0.7- 9.0
➢ Manhattan-Belgrade frontage Road- RP 0.0 – 8.0
➢ Complete
Logan Dump Rd. and Madison Frontage Rd (Maintenance)
➢ Tied chip seal projects
➢ Combined total of approx. 3.0 miles
➢ Complete
Bozeman- NE and Bridger Canyon Rd. (Maintenance)
➢ MT 86
➢ RP 2.3- 9.6 overlay
➢ RP 2.3- 15.8 chip seal
➢ Chip seal will be applied in 2023 season
East Valley Center Rd. (Maintenance)
➢ RP 0.1 – 4.4 from Jackrabbit to Spur Road signal
➢ Completed
Luminaire Upgrades- MDT Maint. Statewide Total- (Maintenance)
➢ Replacing current high pressure sodium luminaire heads w/LED Type.
➢ Individual projects in each MDT division.
➢ Statewide effort, to be completed by the end of 2023.
Bozeman Area- 2023 Design Phase Projects
2023 I-90 Incident Management- Phase 1
➢ Mitigate operational and maintenance impacts for I-90 closures and
weather events between Three Forks and Billings.
➢ The project area encompasses approximately 170 miles of I-90 between the
US 287 Interchange west of Three Forks to the I-90/I-94 junction at Billings.
➢ Installation of advance warning such as road closure signs and gates with
flashers and electronic message boards throughout the corridor.
2023 SF-189 D2 HT Median Cable Rail
➢ Includes locations on Interstates 15 and 90
➢ I-90 Bozeman Area- between Three Forks and the mouth of Rocky Canyon.
2023 Turnbay North of Gallatin Gateway
US 191, RP 77
➢ Adds a two way left turn lane between Gooch Hill Rd. and Zachariah Lane.
➢ Connects to existing turn lanes at either end.
2023 CRSII NH 50-2(87)61 S. of Spanish Creek-S
➢ US 191, RP 61- 65
➢ M/F, seal and cover
➢ Begins at bridge near Lava Lake trailhead, extends north 3.8 miles
2023 4-Corners East
➢ 19th to Fowler- Mill/fill
➢ Seal and Cover – 4-corners to 19th Avenue
2023 North 7th & Griffin Drive, Bozeman
➢ Intersection reconstruction, traffic signals, lighting, ADA upgrades to
current standards, and turn lanes.
➢ MDT is coordinating this project with the city of Bozeman’s reconstruction
of West Griffin Drive.
2023 N 19th Ave Bozeman
➢ Mill Fill – I-90 interchange to Main Street.
2023 SF-169 S-288 Curves (Safety Project South of Manhattan)
➢ Site 1- RP 4.5- 5.0
o Replace bridge w/culvert.
o Reconstruct curve.
o Widened shoulders, rumble strips, delineation, int. improvements,
slope flattening.
➢ Site 2- RP 2.4- 2.9
o Widened shoulders, rumble strips, and signs.
o Replace stock pass and correct adverse super-elevation.