HomeMy WebLinkAbout22016 Staff Report Staff Report
Cherry Creek Mixed Use Site Plan
Application No. 22016
August 31, 2022
Page 1 of 16
Application No. 22016 Type Site Plan
Project Name Cherry Creek Mixed Use SP
Summary Seven new buildings in Gallatin Park Subdivision with accessory residential apartments. 24
2-bedroom second level residential units, above 24 commercial units with associated parking,
open space, landscaping, and site improvements.
Zoning M-1 Growth Policy Maker Space Mixed Use Parcel Size 2.01 Acres
Overlay District(s) None
Street Address Addresses TBD
Legal Description Gallatin Park Sub, S36, T01 S, R05 E, Block 2, Lot 12, Acres 2.01, Plat J-300 Plus Open Space
Owner Long Shot Equity, LLC, PO Box 10025, Bozeman, MT 59719
Applicant Same as Owner
Representative Headwaters Engineering, Inc., 190 Northstar Lane, Bozeman, MT 59718
Staff Planner Danielle Garber Engineer Mikaela Schultz
Noticing Public Comment Period Site Posted Adjacent Owners
Mailed
Newspaper Legal Ad
8/2/22 – 8/17/22
8/2/22 8/2/22 N/A
Advisory Boards Board Date Recommendation
Development Review
Committee
7/28/22 The application is adequate, conforms to
standards, and is sufficient for approval with
conditions and code provisions
Design Review Board NA NA
Recommendation The application is adequate, conforms to standards, and is sufficient for approval with conditions and
code provisions as noted below.
Decision Authority Director of Community Development Date 8/31/22
Full application and file of record: Community Development Department, 20 E. Olive St., Bozeman, MT 59715
Staff Report
Cherry Creek Mixed Use Site Plan
Application No. 22016
August 31, 2022
Page 2 of 16
FINDINGS OF FACT AND APPEAL PROVISIONS CERTIFICATE
A) PURSUANT to Chapter 38, Article 2, Bozeman Municipal Code (BMC), and other applicable sections of Ch.38, BMC, public
notice was given, opportunity to submit comment was provided to affected parties, and a review of the Site Plan described in
this report was conducted. The applicant proposed to the City a Site Plan (SP) to permit seven new office and warehouse
buildings in Gallatin Park Subdivision with accessory residential apartments. The purposes of the Site Plan review were to
consider all relevant evidence relating to public health, safety, welfare, and the other purposes of Ch. 38, BMC; to evaluate the
proposal against the criteria of Sec. 38.230.100 BMC, and the standards of Ch. 38, BMC; and to determine whether the
application should be approved, conditionally approved, or denied.
B) It appeared to the Director that all parties and the public wishing to examine the proposed Site Plan and offer comment were
provided the opportunity to do so. After receiving the recommendation of the relevant advisory bodies established by Ch. 38,
Art. 210, BMC, and considering all matters of record presented with the application and during the public comment period
defined by Ch. 38, BMC, the Director has found that the proposed Site Plan would comply with the requirements of the BMC if
certain conditions were imposed. Therefore, being fully advised of all matters having come before them regarding this
application, the Director makes the following decision.
C) The Site Plan has been found to meet the criteria of Ch. 38, BMC, and is therefore approved, subject to the conditions listed
in this report and the correction of any elements not in conformance with the standards of the Title. The evidence contained in
the submittal materials, advisory body review, public testimony, and this report, justifies the conditions imposed on this
development to ensure that the Site Plan complies with all applicable regulations, and all applicable criteria of Ch. 38, BMC.
On this ______ day of ________________, 2022, Anna Bentley, Interim Director of Community Development, approved with
conditions this Site Plan for and on behalf of the City of Bozeman as authorized by Sec. 38.200.010, BMC.
D) This Director of Community Development’s project decision may be appealed by filing a documented appeal with and paying
an appeal fee to the Clerk of the Commission for the City of Bozeman within 10 working days after the date of the final decision
as evidenced by the Director’s signature, following the procedures of Sec. 38.250.030, BMC.
DIRECTOR OF COMMUNITY DEVELOPMENT
Staff Report
Cherry Creek Mixed Use Site Plan
Application No. 22016
August 31, 2022
Page 3 of 16
CONDITIONS OF APPROVAL
1. The applicant is advised that unmet code provisions, or code provisions that are not specifically listed as conditions
of approval, does not, in any way, create a waiver or other relaxation of the lawful requirements of the Bozeman
Municipal Code or state law.
2. Phasing as noted on drawing sheet PH-1 represents the order of construction for the buildings. All shared site
improvements including access, stormwater drainage, open space (in phase 1) and utilities must be completed prior
to occupancy of the first building. Phased improvements such as parking space striping, parking signage, walkways,
and landscaping must be installed with each phase prior to occupancy of any structures in that phase. Landscaping
may be financially guaranteed to accommodate construction and seasonality.
3. City of Bozeman Resolution 5076, Policy 1- the draft SID waiver is adequate. Please execute and provide a copy of
the recorded SID Waiver to the review engineer prior to final site plan approval.
4. Provide an executed copy of the sewer pipeline and access easement meeting the city approved easement
language to the review engineer prior to final site plan approval.
5. Provide executed copies of the two required public utility easements meeting the city approved easement language
to the review engineer prior to final site plan approval.
CODE PROVISIONS
1. BMC 38.560.080 - Comprehensive sign plan. A comprehensive sign plan must be submitted for all commercial,
office, industrial and civil uses consisting of two or more tenant or occupant spaces on a lot, or two or more lots
subject to a common development permit or plan. A comprehensive sign plan is required prior to the installation of
any signs on the property.
2. BMC 38.420.030 - Cash donation in-lieu of land dedication. Provide proof of payment and approval for CILP from
the Parks Department prior to final site plan approval. Contact Matthew Lee, mjlee@bozeman.net with any
questions.
3. BMC 38.410.030 - Water adequacy. Provide proof of payment for cash-in-lieu of water rights prior to final site plan
approval. Contact Griffin Nielsen, gnielsen@bozeman.net with any questions or your reviewing engineer for the final
total based on estimated annual municipal water demand.
4. BMC 38.270.030.D - Exception for concurrent construction. In certain circumstances, the issuance of a building
permit may be allowed prior to completion of the public infrastructure, if the criteria listed in this section are met.
Provide concurrent construction approval prior to building permit approval.
Staff Report
Cherry Creek Mixed Use Site Plan
Application No. 22016
August 31, 2022
Page 4 of 16
Figure 1: Current Zoning Map
Staff Report
Cherry Creek Mixed Use Site Plan
Application No. 22016
August 31, 2022
Page 5 of 16
Figure 2: Site Plan
Staff Report
Cherry Creek Mixed Use Site Plan
Application No. 22016
August 31, 2022
Page 6 of 16
Figure 3: Landscape Plan
Staff Report
Cherry Creek Mixed Use Site Plan
Application No. 22016
August 31, 2022
Page 7 of 16
Figure 4: Phasing Plan
Staff Report
Cherry Creek Mixed Use Site Plan
Application No. 22016
August 31, 2022
Page 8 of 16
Figure 5: Perspective Views, Interior Elevations
Figure 6: Building 2 North Elevation Facing the Trail
Staff Report
Cherry Creek Mixed Use Site Plan
Application No. 22016
August 31, 2022
Page 9 of 16
Figure 7: Building 6 East Elevation Facing Gallatin Drive
Staff Report
Cherry Creek Mixed Use Site Plan
Application No. 22016
August 31, 2022
Page 10 of 16
ANALYSIS AND FINDINGS
Analysis and resulting recommendations based on the entirety of the application materials, municipal codes, standards,
plans, public comment, and all other materials available during the review period. Collectively this information is the record
of the review. The analysis in this report is a summary of the completed review.
Plan Review, Section 38.230.100, BMC
In considering applications for plan approval under this title, the Director of Community Development shall consider the
following:
1. Conformance with Article 1 - Consistency with the City’s adopted Growth
Policy 38.100.040.D
Meets Code?
Growth Policy
Land Use
Maker Space Mixed Use Yes
Zoning M-1, Light Manufacturing District Yes
Comments: The project conforms to the requirements of the M-1 zoning district. The 2020 Community Plan
designation of Maker Space Mixed use correlates with the M-1 zoning district. The proposed project
conforms to this designation by providing employment and services to the community with the opportunity for
live/work and housing on upper floors of the four mixed-use buildings.
2. Conformance with Article 1 - All other applicable laws, ordinances, and
regulations (38.100.080)
Condominium ownership No
Comments: Additional steps will be required including but not limited to review of building permits and
infrastructure plans. The Building Division of the Department of Community Development will review the
requirements of the International Building Code for compliance at the time of building permit application.
3. Conformance with Article 2, including the cessation of any current violations
(38.200.160)
Meets Code?
Current Violations None Yes
Comments: There are no current violations on the property.
4. Conformance with Article 2 - Submittal material (38.220) requirements and
plan review for applicable permit types (38.230)
Meets Code?
Site Plan Yes
Submittal requirements 38.220.100 Yes
Phasing of development
38.230.020.B
No. of phases: 4 Yes
Comments: The overall site plan details improvements in four phases.
Phase 1 includes:
All underground utilities, stormwater treatment, and water and sewer services.
Asphalt for the parking lot, striping for phase 1, and approaches onto Gallatin Park Drive
Buildings 2 and 6.
Landscaping in phase 1, the eastern open space, and trail connection.
Walkways adjacent to phase 1 and the covered solid waste enclosure.
Phase 1A includes building 4, striping for the phase 1A parking spaces, and adjacent landscaping and
walkways.
Phase 2 includes buildings 3 and 5, striping for the phase 2 parking spaces, and adjacent landscaping
and walkways, as well as the central open space.
Staff Report
Cherry Creek Mixed Use Site Plan
Application No. 22016
August 31, 2022
Page 11 of 16
Phase 3 includes buildings 1A and 1B, striping for the phase 3 parking spaces, and adjacent landscaping
and walkways.
Any additional use permit (Conditional Use Permit) 38.230.120 or (Special use
Permit) 38.230.120
NA
Comments: No conditional or special uses are proposed.
5. Conformance with Article 3 - Zoning Provisions (38.300) Meets Code?
Permitted uses 38.310 Shell manufacturing or warehousing with
accessory office and accessory apartments
Yes
Form and intensity standards 38.320
Zoning: REMU Setbacks
(feet)
Structures Parking /
Loading
Yes
Front Block Frontage, Other NA
Rear 3 NA
Side 3 NA
Alley NA NA
Comments: Three kinds of manufacturing are primary uses within the M-1 district, as well as
warehousing. This application proposes shell spaces to accommodate future businesses, with the option
for accessory office spaces. The second floor contains accessory apartments (48.6% of the gross floor
area). All uses are compliant with the M-1 zoning district. The proposed project fronts onto Gallatin Park
Drive with an Other block frontage designation and a 10-foot front setback. The application provides a 20-
foot front setback meeting this standard. The rear and side setbacks of 3-feet are met.
Lot
coverage
24.3% Allowed 100% Yes
Building
height
28’ 10” Allowed 50-feet Yes
Comments: Lot coverage and building height form and intensity standards are met with the proposed design.
Applicable zone specific or overlay standards 38.330-40 NA
Comments: The project is not within an overlay district, or zoning district with specific standards
General land use standards and requirements 38.350 Yes
Comments: Allowable 1-foot encroachment by building roofline meets standards. Upper level balconies
do not encroach into setbacks. Screening fences for the ground mounted AC condensing units encroach
about 6-inches into the side and rear setbacks, but the AC units do not.
Applicable supplemental use criteria 38.360 Yes
Supplemental
uses/type
None NA
Comments: NA
Wireless facilities 38.370 NA
Affordable Housing 38.380.010 NA
Affordable housing plan NA
Comments: No wireless facilities are proposed. No affordable housing requirements are triggered with
the proposed uses.
6a. Conformance with Article 4 - Community Design Provisions: Transportation
Facilities and Access (38.400)
Meets Code?
Streets 38.400.010 Yes
Street and road dedication 38.400.020 NA
Access easements NA
Staff Report
Cherry Creek Mixed Use Site Plan
Application No. 22016
August 31, 2022
Page 12 of 16
Level of Service
38.400.060
Yes Transportation grid adequate to serve site Yes
Comments: Adjacent streets exist to serve the site, no additional dedication is needed. No new traffic
impact study was required by the Engineering Division however, a peak-hour trip generation letter was
provided by the Applicant to ensure that the proposed project would not exceed the original assumed trip
estimates reviewed with the subdivision. Level of service standards for arterial and collector streets
serving the site was evaluated by engineering. A Waiver of Right to Protest Creation of Special
Improvement Districts (SID’s) for future transportation improvements was provided by the applicant
ensuring participation in funding of future infrastructure improvements that may be required to offset
impacts created by development of the property.
Sidewalks 38.400.080 Yes
Comments: A sidewalk exists and will be repaired where removed for the drive access.
Drive access 38.400.090 Access to site: 1 Yes
Fire lanes, curbs, signage and striping Yes
Comments: One new access is proposed along Gallatin Park Drive; engineering evaluated the access for
spacing and design standards.
Street vision triangle 38.400.100 Yes
Transportation pathways 38.400.110 NA
Pedestrian access easements for shared use pathways and similar transportation
facilities
NA
Public transportation 38.400.120 NA
Comments: No transportation pathways or public transportation facilities are proposed with this
application.
6b. Conformance with Article 4 – Community Design Provisions: Community
Design and Elements (38.410)
Meets Code?
Neighborhood centers 38.410.020 NA
Comments: This project does not trigger neighborhood center requirements.
Lot and block standards 38.410.030-040 Yes
Midblock crossing: rights of way for pedestrians alternative block delineation NA
Comments: This project does not trigger lot and block standards.
If the development is adjacent to an existing or approved public park or public open
space area, have provisions been made in the plan to avoid interfering with public
access to and use of that area
Yes
Provisions for utilities including efficient public services and utilities 38.410.050-060 Yes
Easements (City and public utility rights-of-way etc.) Yes
Water, sewer, and stormwater Yes
Other utilities (electric, natural gas, communications) Yes
CIL of water Yes
Comments: Requirements were reviewed by engineering. Payment of CIL of water rights is a required
condition of approval.
Municipal infrastructure requirements 38.410.070 Yes
Comments: Municipal water, sanitary sewer, and storm sewer systems proposed with this project have
been reviewed by engineering.
Grading & drainage 38.410.080 Yes
Location, design and capacity of stormwater facilities Yes
Stormwater maintenance plan Yes
Landscaping: native species, curvilinear, 75% live vegetation 38.410.080.H Yes
Staff Report
Cherry Creek Mixed Use Site Plan
Application No. 22016
August 31, 2022
Page 13 of 16
Comments: Location, design and capacity of stormwater facilities was reviewed by engineering. A detention
area is proposed at the northwest corner of the site next to building 1A. Stormwater will also flow into the
existing regional pond on the other side of Gallatin Drive. Grading and drainage was reviewed by
engineering.
Watercourse setback 38.410.100 NA
Watercourse setback planting plan 38.410.100.2.f NA
6c. Conformance with Article 4 – Community Design Provisions: Park and
Recreation Requirements (38.420)
Meets Code?
Parkland requirements 38.420.020.A 0.69 ac. CIL required Yes
Cash donation in lieu (CIL) 38.420.030 Yes
Improvements in-lieu NA
Comments: 0.69 acres = 30,056.4 sf x $2.07/sf = $62,216.75 required cash in lieu. This amount must be
verified by parks and paid by the applicant prior to final site plan approval.
Park Frontage 38.420.060 NA
Park development 38.420.080 NA
Recreation pathways 38.420.110 NA
Park/Recreational area design NA
Comments: No parks are proposed with this application. A public park exists approximately a quarter mile
to the east and can be accessed via a public trail and sidewalks.
7a. Conformance with Article 5 – Project Design: Block Frontage Standards
(38.510)
Meets Code?
Block frontage classification Other, Park/Trail Frontage Yes
Departure criteria None requested Yes
Comments: Gallatin Park Drive is an Other block frontage. The project meets the building placement, façade
transparency, parking location, and sidewalk width requirements. A front facing building entrance with
weather protection to building 6 is provided and this building architecturally addresses the street frontage.
The north side of building 2 faces an existing trail connecting the Cherry Creek recreation area to the City’s
trail network. BMC 38.510.030 – “Where a property fronts onto a park or a public trail, such frontages must
comply with the mixed block frontage standards set forth in subsection D of this section. For non-residential
developments/uses where the review authority determines that an orientation to the trail would not be
appropriate based on the context of the site, the development must be subject to the standards for "other
block frontages" set forth in subsection G above, with a minimum building setback of 20 feet from the
applicable park/trail right-of-way, easement, or property line.” Due to the uses and context of the site staff
supports a frontage along the other block frontage standards, with a 10-foot setback from the trail consistent
with Ordinance 2070 that reduced the required M-1 20-foot setback to 10-feet. Additionally, there is an
approximately 35 feet of open space area between the subject property and the other developable parcel to
the northeast which will help preserve light and air access to the trail. The applicant requested a
determination from the Director on this point by letter on December 7, 2021. On February 8, 2022, the
Director provided an email supporting the analysis and determined that the applicant can provide a 10-foot
setback from the trail for Building 2 provided that additional transparency treatments and landscaping. The
building 2 design was revised to provide ground level windows and additional shrub plantings were provided,
meeting this requirement.
7b. Conformance with Article 5 – Project Design: Site Planning and Design
Elements (38.520)
Meets Code?
Staff Report
Cherry Creek Mixed Use Site Plan
Application No. 22016
August 31, 2022
Page 14 of 16
7d. Conformance with Article 5 – Parking (38.540) Meets Code?
Parking requirements 38.540.050 Yes Yes
Parking requirements residential 38.540.050.A.1 48 spaces
Reductions residential 38.540.050.A.1.b 50% Mixed Uses
Parking requirements nonresidential
38.540.050.A.2
36 spaces
Reductions nonresidential 38.540.050.A.2.c NA
Provided off-street 60 spaces
Design and arrangement of the elements of the plan (e.g., buildings, circulation, open
space and landscaping, etc.) so that activities are integrated with the organizational
scheme of the community, neighborhood, and other approved development and produce
an efficient, functionally organized and cohesive development
Yes
Relationship to adjacent properties 38.520.030 NA
Non-motorized circulation and design systems to enhance convenience and safety
across parking lots and streets, including, but not limited to paving patterns, pathway
design, landscaping and lighting 38.420.040
Yes
Comments: Pedestrian paths through the site and to the open space and service areas meet the
standards in this section for location, connections, and widths. A departure from the landscaping
standards between walkways and buildings in 38.520.040.D was requested where the ground level
building facades are dominated by drive accesses and roll up doors. Instead of a continuous landscaping
strip, the applicant has proposed individual planting beds between doors; this approach is supported by
staff.
Design of vehicular circulation systems to assure that vehicles can move safely and
easily both within the site and between properties and activities within the general
community 38.420.050
Yes
Internal roadway design 38.520.050.D NA
Comments: NA
On-site open space 38.520.060
Total required 3,600 square feet Yes
Total provided 3,832 square feet Yes
Comments: 3,832 square feet provided in the two common open space areas in the northeast and
southwest sides of the site. These areas will have seating, a lawn, a trail connection (NE) and bicycle
maintenance facilities. It is proposed to be screened from the adjacent walkways, mechanical equipment,
and parking areas with fencing and landscaping.
Location and design of service areas and mechanical equipment 38.520.070 Yes
Comments: AC units and utility meters are to be screened by landscaping and fencing. Solid waste will
be collected via one enclosure on the south side of the lot near building 4. The enclosure meets the
screening standards in this section and adequate adjacent landscaping is provided.
7c. Conformance with Article 5 – Project Design: Building Design (38.530) Meets Code?
Compatibility with, and sensitivity to, the immediate environment of the site and the
adjacent neighborhoods and other approved development 38.530.030
Yes
Building massing and articulation 38.530.040 Yes
Building details, materials, and blank wall treatments 38.530.050-070 Yes
Comments: The seven buildings are meeting the building design standards of this section. Entries,
building materials, and vertical articulation serve to break up the elevations. 22 gauge vertical structural
box rib steel, 24 gauge snap seam metal roofing, stained horizontal running cedar siding, white hardy
plank siding, black round metal railing, and dark bronze aluminum louvered mechanical screening.
Staff Report
Cherry Creek Mixed Use Site Plan
Application No. 22016
August 31, 2022
Page 15 of 16
Provided on-street 0
Bicycle parking 38.540.050.A.4 6
Comments: Parking is proposed to be provided for the 24 2 two-bedroom units in the off-street parking
lot, with a 24 space reduction for residential uses in mixed use projects. In order to ensure long term
availability of the non-residential parking spaces and allow commercial parking directly in front of
manufacturing unit roll up doors, the applicant is providing signs on the roll up doors that state “Unit XX
parking only between 8-5 AM.” This management structure will allow unlimited residential parking after
hours while ensuring commercial parking is met. Commercial parking requirements are based off the
manufacturing and office calculations for 85% net floor area requiring 36 stalls. A total of 60 stalls is
required. Each stall provided off-street meets the stall, aisle, and driveway design requirements of
Section 38.540.020. Bike parking will be provided central to the site, adjacent to the open space area and
building 5 with compliant U-style bike racks and within units.
Loading and uploading area requirements 38.540.080 NA
First berth – minimum 70 feet length, 12 feet in width, 14 feet in height NA
Additional berth – minimum 45 feet length NA
Comments: NA
7e. Conformance with Article 5 – Landscaping (38.550) Meets Code?
Mandatory landscaping requirements 38.550.050 Yes
Drought tolerant species 75% required Yes
Parking lot landscaping Yes
Additional screening NA
Street frontage Yes
Street median island NA
Acceptable landscape materials Yes
Protection of landscape areas NA
Irrigation: plan, water source, system type Yes
Residential adjacency NA
Comments: The provided landscaping plan conforms to standards.
Landscaping of public lands 38.550.070 Yes
Comments: Street trees will be provided along Gallatin Park Drive.
7f. Conformance with Article 5 – Signs (38.560) Meets Code?
Allowed SF/building 38.560.060 NA NA
Proposed SF/building NA NA
Comments: No signage is proposed with this application. A comprehensive sign plan will be required prior to
the installation of any signs.
7g. Conformance with Article 5 – Lighting (38.560) Meets Code?
Site lighting (supports, cutoff, footcandles, temperature) 38.570.040 NA
Building-mounted lighting (supports, cutoff, footcandles, temperature) 38.570.040.B Yes
Comments: The proposed building mounted wall sconces and under awning recessed lighting meet the
required cutoff and intensity requirements.
8. Conformance with Article 6 – Natural Resource Protection Meets Code?
Floodplain regulations 38.600 NA
Wetland regulations 38.610 NA
Comments: NA
9. Relevant Comment from Affected Parties (38.220) Meets Code?
Staff Report
Cherry Creek Mixed Use Site Plan
Application No. 22016
August 31, 2022
Page 16 of 16
Public Comment Yes
Comments: A public notice period was conducted meeting the requirements of this section and detailed on
page 1 of this report. No public comment was provided.
10. Division of Land Pertaining to Subdivisions (38.240-Part 4) Meets Code?
Subdivision exemptions NA
Required easements Yes
Comments: No subdivision exemptions were required with this application. Utility easements are required