Hello Gary,
Based on the reported # of peak hour trips below, you do not need to submit a Traffic Impact Study (TIS) for the
abovementioned project.
Please include this correspondence with site plan resubmittal.
Thank you,
City of Bozeman MT
Alicia Paz-Solis, EI | Engineering Department
O: 406.582.2976
apazsolis@bozeman.net
From: Gary Fox <gfox@wgmgroup.com>
Sent: Wednesday, October 27, 2021 2:41 PM
To: Lynn Hyde <lhyde@BOZEMAN.NET>; Alicia Paz-Solis <apazsolis@BOZEMAN.NET>
Subject: [SENDER UNVERIFIED]Traffic Study for Beall Townhomes #21230
CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you recognize the
sender and know the content is safe.
Hello,
This email is in regards to a comment received on the Conceptual review of the Beall Townhomes
(#21230). The comment asked to provide peak hour trip generation to determine whether a traffic study is
required.
The traffic generation numbers are provided in the table below. An excerpt of the conceptual plan is attached.
Thank you for your help. Please let us know if a traffic study is required.
Land Use Size
ITE Land
Use Code
Average Daily
Traffic (ADT)
AM Peak-Hour Trips PM Peak-Hour Trips
Entering Exiting Entering Exiting
Duplex 4 units 210 38 1 2 2 2
Triplex 6 units 220 44 1 2 2 1