HomeMy WebLinkAbout005a_Improvements Agreement Calculations and EstimatesBlackwood Groves Subdivision ‐ Phases 1 and 9
Improvements Agreement Summary
Item Total Remaining Notes
Civil Infrastructure Improvements 1,581,212.40$ Sime Construction Contract
Park Improvements (Baseline) 415,395.19$ Design 5 Estimate (Includes Irrigation Wells)
Park Improvements (Add‐In‐Lieu) 153,702.50$ Design 5 Estimate
Open Space Improvements 72,869.40$ Cashman's Nursery Estimate
Sidewalks ‐ Private Lots 264,646.84$ Sime Construction Unit Cost
Total 2,487,826.33$
150% of Total 3,731,739.49$ Phases 1 and 9 Improvements Agreement Total
Blackwood Groves
Landscape Improvements Estimate
10/19/2021
DESCRIPTION QTY UNITS
UNIT COST COST UNIT COST COST
PHASE 1 - PARK IMPROVEMENTS
Park 4 Improvements
Prep & Material 6" Topsoil - Sod Area 44 CY $5.00 $219.91 --
Prep & Material 6" Topsoil - Planting Bed Area 13 CY $5.00 $63.43 --
Sidewalk Prep 427 SY $1.50 $640.83 --
Sidewalk Aggregate 47 CY $30.00 $1,422.65 --
Hardscape 4" Concrete Sidewalk 3845 SF $5.50 $21,147.50 --
Crusher Fines Path 300 LF --$6.00 $1,800.00
Signage - Primary Future EA ----
Signage - Posts/Totems Future EA ----
Bridge - Freespan 20 LF --$1,200.00 $24,000.00
Bridge Abutments 2 EA --$4,000.00 $8,000.00
Landscape Park Trees 3 EA --$300.00 $900.00
Mulched Planting Beds 685 SF --$2.50 $1,712.50
Native Seed 32275 SF $0.18 $5,809.50 --
Sod 5200 SF $0.60 $3,120.00 --
Boulevard Sod 2375 SF $0.60 $1,425.00 --
Watercourse Setback Planting 344 LF -$5,160.00 --
Stormwater Pond Planting 340 LF -$5,100.00 --
Irrigation Plant Material 13711 SF $1.25 $17,138.44 --
Well 1 Install + Power 1 EA $50,000.00 $50,000.00 --
Play Areas Boulder Rock Dock 6 EA --$450.00 $2,700.00
Furnishings Pet Waste 1 EA --$500.00 $500.00
Benches (6' Wood)2 EA --$1,350.00 $2,700.00
SubTotal $111,247.25 $42,312.50
Park 12 Improvements
Prep & Material 6" Topsoil - Planting Bed Area 9 CY $5.00 $43.98 --
6" Topsoil - Sod Area 353 CY $5.00 $1,762.69 --
Sidewalk Prep 289 SY $1.50 $433.33 --
Sidewalk Aggregate 32 CY $30.00 $962.00 --
Hardscape 4" Concrete Sidewalk 2600 SF $5.50 $14,300.00 --
Crusher Fines Path 225 LF --$6.00 $1,350.00
8' Asphalt Trail 3375 SF $4.00 $13,500.00 --
Signage - Primary Future EA ----
Signage - Posts/Totems Future EA ----
Seating Surfacing - DG 200 SF --$3.50 $700.00
Fitness Station Surfacing 540 SF --$8.00 $4,320.00
Boulders for Seatwalls 14 EA --$450.00 $6,300.00
Landscape Frontage Trees 13 EA $300.00 $3,900.00 --
Park Trees 6 EA --$300.00 $1,800.00
Mulched Planting Beds 475 SF --$2.50 $1,187.50
Sod 14200 SF $0.60 $8,520.00 --
Boulevard Sod 4837 SF $0.60 $2,902.20 --
Irrigation Plant Material 19512 SF $1.25 $24,390.00 --
Play Areas Play Berms X2 180 CY --$5.00 $900.00
Furnishings Pet Waste 1 EA --$500.00 $500.00
Picnic Table 2 EA --$1,500.00 $3,000.00
Bike Racks 2 EA --$500.00 $1,000.00
Trash 1 EA --$500.00 $500.00
Fitness Station 1 EA --$1,500.00 $1,500.00
SubTotal $70,714.20 $23,057.50
REQUIRED BASELINE COSTS IMPROVEMENTS IN LIEU
1
Blackwood Groves
Landscape Improvements Estimate
10/19/2021
DESCRIPTION QTY UNITS
UNIT COST COST UNIT COST COST
REQUIRED BASELINE COSTS IMPROVEMENTS IN LIEU
Park 13 Improvements
Prep & Material 6" Topsoil - Sod Area 216 CY $5.00 $1,082.41 --
Sidewalk Prep 333 SY $1.50 $500.00 --
Sidewalk Aggregate 37 CY $30.00 $1,110.00 --
Hardscape 4" Concrete Sidewalk 3000 SF $5.50 $16,500.00 --
Signage - Posts/Totems Future EA ----
Fitness Station Surfacing 300 SF --$8.00 $2,400.00
8' Asphalt Trail 3180 SF $4.00 $12,720.00 --
Boulders for Seatwalls 16 EA --$450.00 $7,200.00
Landscape Frontage Trees 9 EA $300.00 $2,700.00 --
Park Trees 3 EA --$300.00 $900.00
Sod 8682 SF $0.60 $5,209.20 --
Boulevard Sod 3008 SF $0.60 $1,804.80 --
Irrigation Plant Material 11690 SF $1.25 $14,612.50 --
Play Areas Play Berms X2 150 CY --$5.00 $750.00
Log Steppers 2 EA --$4,000.00 $8,000.00
Furnishings Pet Waste 1 EA --$500.00 $500.00
Bike Racks 2 EA --$500.00 $1,000.00
Fitness Station 1 EA --$1,500.00 $1,500.00
Trash 1 EA --$500.00 $500.00
SubTotal $56,238.91 $22,750.00
Park 14 Improvements
Prep & Material 6" Topsoil - Planting Bed Area 6 CY $5.00 $27.78 --
6" Topsoil - Sod Area 512 CY $5.00 $2,559.72 --
Sidewalk Prep 411 SY $1.50 $616.67 --
Sidewalk Aggregate 46 CY $30.00 $1,369.00 --
Hardscape 4" Concrete Sidewalk 3700 SF $5.50 $20,350.00 --
8' Asphalt Trail 4600 SF $4.00 $18,400.00 --
Fitness Station Surfacing 800 SF --$8.00 $6,400.00
Signage - Posts/Totems Future EA ----
Boulders for Seatwalls 10 EA --$450.00 $4,500.00
Boulders at Berms 6 EA --$450.00 $2,700.00
Seating Surfacing - DG 225 SF --$3.50 $787.50
Landscape Frontage Trees 4 EA $300.00 $1,200.00 --
Mid Block Crossing Trees 11 EA --$300.00 $3,300.00
Mulched Planting Beds 300 SF --$2.50 $750.00
Sod 26645 SF $0.60 $15,987.00 --
Boulevard Sod 1000 SF $0.60 $600.00 --
Irrigation Plant Material 27945 SF $1.25 $34,931.25 --
Well 4 Install + Power 1 EA $50,000.00 $50,000.00 --
Play Areas Play Berms X3 450 CY --$5.00 $2,250.00
Log Fort Stacked Boulders 20 EA --$450.00 $9,000.00
Log Fort Timber Materials 1 EA --$3,000.00 $3,000.00
Small Tot Playground 1 EA --$10,000.00 $10,000.00
Furnishings Pet Waste 1 EA --$500.00 $500.00
Benches (6' Wood)2 EA --$1,350.00 $2,700.00
Bike Racks 2 EA --$500.00 $1,000.00
Trash 1 EA --$500.00 $500.00
Fitness Station 1 EA --$1,500.00 $1,500.00
Picnic Table 2 EA --$1,500.00 $3,000.00
SubTotal $146,041.42 $51,887.50
2
Blackwood Groves
Landscape Improvements Estimate
10/19/2021
DESCRIPTION QTY UNITS
UNIT COST COST UNIT COST COST
REQUIRED BASELINE COSTS IMPROVEMENTS IN LIEU
Park 15 Improvements
Prep & Material 6" Topsoil - Planting Bed Area 0 CY $5.00 $0.46 --
6" Topsoil - Sod Area 102 CY $5.00 $509.72 --
Sidewalk Prep 178 SY $1.50 $266.67 --
Sidewalk Aggregate 20 CY $30.00 $592.00 --
Hardscape 4" Concrete Sidewalk 1600 SF $5.50 $8,800.00 --
Crusher Fines Path 165 LF --$6.00 $990.00
Signage - Posts/Totems Future EA ----
Seating Surfacing 60 SF --$5.50 $330.00
Landscape Frontage Trees 5 EA $300.00 $1,500.00 --
Mulched Planting Beds 50 SF --$2.50 $125.00
Park Trees 3 EA --$300.00 $900.00
Sod 4050 SF $0.60 $2,430.00 --
Boulevard Sod 1455 SF $0.60 $873.00 --
Irrigation Plant Material 5555 SF $1.25 $6,943.75 --
Play Areas Play Berms X2 230 CY --$5.00 $1,150.00
Boulder Balance Course 14 EA --$450.00 $6,300.00
Furnishings Benches (6' Wood)2 EA --$1,550.00 $3,100.00
SubTotal $21,915.60 $12,895.00
Park 16 Improvements
Prep & Material 6" Topsoil - Sod Area 47 CY $5.00 $236.11 --
Sidewalk Prep 73 SY $1.50 $110.00 --
Sidewalk Aggregate 8 CY $30.00 $244.20 --
Hardscape 4" Concrete Sidewalk 660 SF $5.50 $3,630.00 --
Signage - Primary Future EA ----
Signage - Posts/Totems Future EA ----
Landscape Frontage Trees 1 EA $300.00 $300.00 --
Park Trees 1 EA --$300.00 $300.00
Sod 2350 SF $0.60 $1,410.00 --
Boulevard Sod 200 SF $0.60 $120.00 --
Irrigation Plant Material 2550 SF $1.25 $3,187.50 --
Furnishings Pet Waste 1 EA --$500.00 $500.00
SubTotal $9,237.81 $800.00
PHASE 1 TOTALS
$415,395.19 Improvements IL $153,702.50
Park Improvements Total $569,097.69
City Required Parkland IIL $115,189.64
$38,512.86
Baseline Improvements
IIL In Excess of Requirement
3
Blackwood Groves Subdivision ‐ Phases 1 and 9
Open Space Landscaping Improvements Estimate
Item Qty Unit Unit Price* Total
Trees
Norway Maple 3 EA 175.00$ 525.00$
Honeylocust 3 EA 250.00$ 750.00$
Spring Snow Crabapple 3 EA 215.00$ 645.00$
Accolade Elm 5 EA 250.00$ 1,250.00$
American Linden 2 EA 215.00$ 430.00$
Tree Guards, Stakes, and Wire 16 EA 7.65$ 122.40$
Perennials and Grasses
White Swan Coneflower 31 EA 13.00$ 403.00$
Blue Oat Grass 31 EA 13.00$ 403.00$
May Night Salvia 25 EA 13.00$ 325.00$
Watercourse and Storm
Black Hawthorn 6 EA 125.00$ 750.00$
Songarica Poplar 2 EA 105.00$ 210.00$
Lanceleaf Poplar 8 EA 105.00$ 840.00$
Sod, Seed, Site Material
Native/Upland Seed Blend 9,475 SF 0.20$ 1,895.00$
Detention Pond/Watercourse Seed Mix 46,700 SF 0.35$ 16,345.00$
Lawn/Boulevard Seed Mix 27,200 SF 0.50$ 13,600.00$
Rock Bark Mulch 22 SY 250.00$ 5,500.00$
Landscape Boulders 125 EA 60.00$ 7,500.00$
Irrigation
Irrigation Systems 1 LS 17,376.00$ 17,376.00$
Irrigation Vaults 2 EA 2,000.00$ 4,000.00$
Phases 1 and 9 Open Space Landscaping Improvements Total: 72,869.40$
*Cashman Nursery estimate for all landscape items, Sime Construction estimate for irrigation vaults
Blackwood Groves Subdivision ‐ Phases 1 and 9
Sidewalks (Private Lots) Estimate
Qty Unit* Unit Price Total Notes
Phase 1
Block 2 (Lots 1‐ 6) 2,325.00 SF 5.95$ 13,833.75$
Block 3 (Lots 1 ‐ 6) 1,650.00 SF 5.95$ 9,817.50$
Block 4 (Lots 1 ‐ 6) 2,850.00 SF 5.95$ 16,957.50$
Block 5 (Lots 1 ‐ 6) 1,992.55 SF 5.95$ 11,855.67$
Block 6 (Lots 1 ‐ 12) 4,400.00 SF 5.95$ 26,180.00$
Block 7 (Lots 1 ‐ 12) 4,835.00 SF 5.95$ 28,768.25$
Block 8 (Lots 1 ‐ 20) 4,621.75 SF 5.95$ 27,499.41$
Block 10 (Lots 1 ‐ 2) 3,015.00 SF 5.95$ 17,939.25$
Block 11 (Lots 1 ‐ 2) 4,220.00 SF 5.95$ 25,109.00$
Phase 9
Block 1 (Lot 1) Locals 4,652.10 SF 5.95$ 27,680.00$
Block 1 (Lot 1) 19th Ave 3,243.54 SF 5.95$ 19,299.06$ 6‐ft wide (Arterial)
Block 13 (Lot 1) 3,677.10 SF 5.95$ 21,878.75$
Open Space G** 2,996.42 SF 5.95$ 17,828.70$ 6‐ft wide along 19th
Phases 1 and 9 Sidewalks (Private Lots) Total: 264,646.84$
*All sidewalks are 5‐ft wide, 4" thick unless otherwise indicated
**Civil Improvements Estimate includes all Open Space sidewalks except OS G