SEVENTH AMENDMENT TO PROFESSIONAL SERVICES AGREEMENT
THIS SEVENTH AMENDMENT TO THE PROFESSIONAL SERVICES AGREEMENT
FOR Oak Street Improvements dated March 16, 2015 (the “Agreement”) is made and entered
into this _____ day of ____________, 2022, by and between the CITY OF BOZEMAN,
MONTANA, a self governing municipal corporation organized and existing under its Charter and
the laws of the State of Montana, 121 North Rouse Street, Bozeman, Montana, with a mailing
address of PO Box 1230, Bozeman, MT 59771, hereinafter referred to as “City,” Sanderson
Stewart, hereinafter referred to as “Contractor.”
In consideration of the mutual covenants and agreements herein contained, the receipt and
sufficiency whereof being hereby acknowledged, the parties hereto agree to amend the Agreement
as follows:
1. Scope of services, rate schedules, and budget for design services are outlined in
Attachment “Exhibit A - Scope of Work.”
2. Agreement still valid. All remaining terms and provisions of the Agreement remain valid.
**** END OF AGREEMENT EXCEPT FOR SIGNATURES ****
DocuSign Envelope ID: 5E688A1D-E11C-4405-B621-3C24AD0436E8
July26
Seventh Amendment to Professional Services Agreement for Oak Street Improvements Project
Page 2 of 2
IN WITNESS WHEREOF, the parties hereto have executed this instrument the day and
year first above written.
CITY OF BOZEMAN, MONTANA SANDERSON STEWART
By________________________________ By_____________________________
Jeff Mihelich, City Manager Print Name: Danielle Scharf, P.E.
Title: Principal
APPROVED AS TO FORM
By_______________________________
Greg Sullivan, Bozeman City Attorney
DocuSign Envelope ID: 5E688A1D-E11C-4405-B621-3C24AD0436E8
Exhibit A – Scope of Work
Front Street Connector Trail
Construction Contract Administration and Staking Amendment 1
Seventh Amendment to Professional Services Agreement
07/06/22
This scope of work includes additional time spent and future time anticipated to address unforeseen
construction issues. Additionally, the original contract in September of 2016 did not include
construction staking and has been included in this contract amendment.
Phase 1 – Construction/Contract Administration
This phase includes the additional time needed for construction inspection and administration not
anticipated during the original scoping in September of 2016. Subtasks under Phase 1 include the
following:
· Coordination and design to address construction issues
o Failed bridge abutments. Coordination to discuss and resolve failure, including emails,
phone calls, and meetings with structural engineers, IMEG, Morrison Maierle, and
City of Bozeman.
o Drainage Issues. Research into drainage issues, site visits, and meetings with City staff.
Revise plans to address drainage issues along east side of Kenyon Noble property.
o Site access coordination. Montana Rail Link Temporary Occupancy Permit and
Northwestern Energy guy wire relocation coordination.
o Coordination on excessive trash within project area and landscaping around path.
· Increased inspection time associated with the construction issues noted above
Phase 2 – Construction Staking
This phase of the project consists of the construction layout. Subtasks under Phase 2 include the
following:
· Stake path alignment and offsets
· Stake bridge footings and abutments
· Stake curb, gutter, and new ramps on Wallace
· Stake bollard & sign locations
· Stake new fence
DocuSign Envelope ID: 5E688A1D-E11C-4405-B621-3C24AD0436E8
Front Street Connector Trail
Construction Administration & Staking
15022.02
Labor Category Total Plan Hours Total Plan Bill Amt
Phase: Construction/Contract Admin
Task: Project Mgmt & Coordination
Principal 2.00 440.00
Senior Engineer I 17.00 2,805.00
Staff Engineer I 4.00 400.00
Task: Construction Inspection & Documentation
Senior Engineer I 7.00 1,155.00
Staff Engineer I 27.50 2,750.00
Task: Change orders/contract mods
Senior Engineer I 35.00 5,775.00
Staff Engineer I 4.00 400.00
Subtotal 96.50 13,725.00
Expenses
Total for Construction/Contract Admin 96.50 13,725.00
Phase: Construction/PropertyStaking
Task: Project Mgmt & Coordination
Designer I 1.00 95.00
Senior Engineer I 2.00 330.00
Senior Professional Land Surveyor 2.00 320.00
Task: Bollards & Fence
Designer I .50 47.50
Staff Surveyor II 1.00 110.00
Task: Path Alignment
Designer I 2.00 190.00
Staff Surveyor II 8.00 880.00
Task: Curb & Gutter, ADA Ramps
Designer I 1.00 95.00
Staff Surveyor II 2.00 220.00
Task: Fence
Designer I 1.00 95.00
Staff Surveyor II 3.00 330.00
Task: Bridge Footings/Abutment
Designer I 2.00 190.00
Staff Surveyor II 12.00 1,320.00
Subtotal 37.50 4,222.50
Expenses
Total for Construction/PropertyStaking 37.50 4,222.50
Total for Front Street Connector Trail - CA & Staking Services 134.00 17,947.50