HomeMy WebLinkAbout035 Construction management plan      190 NORTHSTAR LANE  BOZEMAN, MT  59718   406‐581‐5730  www.headwatersmt.net                                                                Page 1 of 3  January 13, 2022    Cherry Creek Mixed Use – Construction Management Plan     The applicant plans to construct the buildings in four phases as shown on the PH‐1 sheet. Phase 1 will contain the  majority of the site work; site grading, parking lot construction, storm pond construction, construction of Buildings #2  and #6, and the majority of the project’s landscaping. Phases 1A, 2 and 3 will mostly include the construction of  buildings and adjacent sidewalks. During each step of the construction, the garbage and materials will be managed.  Below is a description of the Construction Management Plan broken down into the four phases.    PHASE 1  1. Site grading  During site grading, the excess materials (topsoil & fill) will be hauled offsite and disposed of. Garbage will be  minimal in this portion of the construction and will be hauled offsite daily by the contractor. Minimal topsoil  will be stockpiled onsite in the future building sites and placed immediately following parking lot and building  completion.    2. Infrastructure Installation  During the installation of the underground water and sewer services, as well as during the installation of the  underground power and phone, the minimal garbage will be hauled offsite daily. The pipe and wire will be  stored at an offsite yard until the time of installation when it will be hauled to the site and stored until it is  installed. Staging areas are shown on the attached construction management exhibit.    3. Parking Lot & Building Pad Construction  The excess fill materials will be hauled offsite during the site grading phase of construction so minimal material  is anticipated to leave the site during the parking lot construction. The gravels and asphalt will be trucked in on  an as‐needed basis. Any waste asphalt will be trucked back to the pit after paving has been completed by the  paving contractor.     4. Building Construction  During the construction of buildings 2 and 6, a 20‐30 cubic yard dumpster will be onsite as shown on the  attached exhibit to manage the waste generated by the buildings. A portable toilet will be onsite during all  phases of construction. The building materials will be stored in the staging area during construction.    5. General Management  During this phase of construction, the access will be construction access with cobble runout pads until the  parking lot is paved.  As shown on the phasing plan, all parking lots will be paved in Phase 1 to allow for an  all‐weather staging/construction area.    The existing hydrant east of the property along Gallatin Park Drive will be utilized for any firefighting needs.   The construction access shall remain open to allow access for the EMS services.      PHASE 1A  1. Site grading  During site grading, the excess materials (topsoil & fill) will be hauled offsite and disposed of. Garbage will be  minimal in this portion of the construction and will be hauled offsite daily by the contractor. Minimal topsoil  will be stockpiled onsite in the future building sites and placed following parking lot and building completion.    2. Infrastructure Installation  No infrastructure installation will occur in Phase 1A.  190 Northstar Lane, Bozeman, MT 59718                  (406) 581‐5730                 www.headwatersmt.net                         Page 2 of 3    3. Building Pad Construction  The excess fill materials will be hauled offsite during the site grading phase of construction, so minimal  material is anticipated to leave the site during the building pad construction. The gravel will be trucked in on  an as‐needed basis.     4. Building Construction  During the construction of building 1A, a 20‐30 cubic yard dumpster will be onsite as shown on the attached  exhibit to manage the waste generated by the buildings. A portable toilet will be onsite during all phases of  construction. The building materials will be stored in the staging area during construction.    5. General Management  The construction dumpster and the sanitary facilities will be located away from any occupied buildings in an  attempt to minimize disturbance. Access to the mailbox and phase 1 trash enclosure must be maintained at all  times for the existing residents.      The existing hydrant east of the property along Gallatin Park Drive will be utilized for any firefighting needs.   The construction access shall remain open to allow access for the EMS services.      PHASE 2    1. Site grading  During site grading, the excess materials (topsoil & fill) will be hauled offsite and disposed of.  Garbage will be  minimal in this portion of the construction and will be hauled offsite daily by the contractor. Minimal topsoil  will be stockpiled onsite in the future building sites and placed following curb installation and building  completion.    2. Infrastructure Installation  No infrastructure installation will occur in Phase 2.    3. Building Pad Construction  The excess fill materials will be hauled offsite during the site grading phase of construction, so minimal  material is anticipated to leave the site during the building pad construction. The gravel will be trucked in on  an as‐needed basis.     4. Building Construction  During the construction of buildings 3 and 5, a 20‐30 cubic yard dumpster will be onsite as shown on the  attached exhibit to manage the waste generated by the buildings. A portable toilet will be onsite during all  phases of construction. The building materials will be stored in the staging area during construction.    5. General Management  The construction dumpster and the sanitary facilities will be located away from any occupied buildings in an  attempt to minimize disturbance. Access to the mailbox and phase 1 trash enclosure must be maintained at all  times for the existing residents.      The existing hydrant east of the property along Gallatin Park Drive will be utilized for any firefighting needs.   The construction access shall remain open to allow access for the EMS services.      PHASE 3  1. Site grading  During site grading, the excess materials (topsoil & fill) will be hauled offsite and disposed of. Garbage will be  minimal in this portion of the construction and will be hauled offsite daily by the contractor. Minimal topsoil  190 Northstar Lane, Bozeman, MT 59718                  (406) 581‐5730                 www.headwatersmt.net                         Page 3 of 3  will be stockpiled onsite in the future building sites and placed following curb installation and building  completion.    2. Infrastructure Installation  During the installation of the sewer service to Building 1A, the minimal garbage will be hauled offsite daily. The  pipe will be stored at an offsite yard until the time of installation when it will be hauled to the site and stored  until it is installed. Staging areas are shown on the attached construction management exhibit.  No other infrastructure installation will occur in Phase 3.    3. Building Pad Construction  The excess fill materials will be hauled offsite during the site grading phase of construction, so minimal  material is anticipated to leave the site during the building pad construction. The gravel will be trucked in on  an as‐needed basis.     4. Building Construction  During the construction of buildings 1A and 1B, a 20‐30 cubic yard dumpster will be onsite as shown on the  attached exhibit to manage the waste generated by the buildings. A portable toilet will be onsite during all  phases of construction. The building materials will be stored in the staging area during construction.    5. General Management  The construction dumpster and the sanitary facilities will be located away from any occupied buildings in an  attempt to minimize disturbance. Access to the mailbox and phase 1 trash enclosure must be maintained at all  times for the existing residents.      Sidewalks adjacent to buildings 1A and 1B will be installed during phase 3. The existing hydrant east of the  property along Gallatin Park Drive will be utilized for any firefighting needs. The construction access shall  remain open to allow access for the EMS services.            H:\1086\017\DOCS\SITEPLAN\construction management plan.doc