HomeMy WebLinkAbout2022.04.13_SID EmailAlex Edwards - RE: Easement Correction
From:"Karl A. Johnson" <kajohnson@BOZEMAN.NET>
To:Alex Edwards <alex.edwards@tdhengineering.com>
Date:4/13/2022 2:41 PM
Subject:RE: Easement Correction
Attachments:Part.002
Alex,
Sorry for the late response. I got the new easement cover page included with the old package and on its
way to get signed and that SID waiver will suffice SID waiver requirements.
For the rest of your questions
1. The concurrent construction requirements (conditions established in the latest PP submittal) must
be satisfied prior to issuing a building permit.
2. We ask for the site drainage self cert with all building permits to clarify the responsibility of
providing proper site drainage. However the grading and drainage plans suffice this requirement in
commercial development. You do not have to provide the site drainage form with this building
permit.
3. The sump pump policy form is required for all developments
4. Understood. I just didn’t want there to be an issue connecting to the stub. Sounds like there is no
concern.
Thanks,
Karl Johnson, E.I. | Engineering Department
City of Bozeman | 20 E. Olive St. | Bozeman, MT 59715
C: 406.451.1693
O: 406.582.2281
kajohnson@bozeman.net
From: Alex Edwards <Alex.Edwards@tdhengineering.com>
Sent: Friday, April 8, 2022 9:13 AM
To: Karl A. Johnson <kajohnson@BOZEMAN.NET>
Subject: Re: Easement Correction
CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you
recognize the sender and know the content is safe.
Thanks for the clarification. The revised sheet is attached. I have also attached the existing SID that is
currently active for the Subdivision.
There were also a couple of comments posted to the PDOX portal that we received from the architect
yesterday. The items that apply to Civil scope are summarized below with some of my comments in red.
Please see my comments below and let us know with what we need to do to get these taken care of.
Page 1 of 3
5/11/2022file:///C:/Users/aje/AppData/Local/Temp/XPgrpwise/6256E115tdhinctdhincpo1001693764...
1. Completion of Improvements requirements (BMC 38.270.030.B) have not been satisfied. See Preliminary
Plat comments related to completion of improvements standards. These must be satisfied prior to building
permit approval.
This item is completely out of our control. Can you please verify that the walk-thru that took place in
January is sufficient for us to move forward?
2. Provide a completed Site Drainage Self Certification form.
I have not seen the requirement for commercial development before. We had our full design report and
plans reviewed and approved through infrastructure review. Is the self certification form necessary? We have
typically been required to provide these only for residential development.
3. Provide a completed Sump Pump Policy form.
This item is more applicable to the Mechanical designer, but again this is typically only required for
residential development. Is this required for the Medical Eye Building?
4. C7.0: Confirm sewer stub elevation. Sewer stub may have been installed per deep sewer service detail
which will have a higher elevation than shown and may require insulation near the building.
Our records indicate this was installed per plan. If the stub had been installed any higher it would not gravity
flow from the building. Since it was installed per plan, no changes will be necessary to the existing plan set.
Thanks,
Alex Edwards, P.E.
TD&H Engineering
234 E. Babcock, Suite 3 l Bozeman, MT 59715
p: 406.586.0277
www.tdhengineering.com
>>> "Karl A. Johnson" <kajohnson@BOZEMAN.NET> 4/8/2022 8:08 AM >>>
Alex,
Following up on your voice mail. This is the error that was marked up on the package you gave me. If you
could get me a clean first page without the error I will get it included with the rest of the release and get it
signed.
Thanks,
Karl Johnson, E.I. | Engineering Department
City of Bozeman | 20 E. Olive St. | Bozeman, MT 59715
C: 406.451.1693
O: 406.582.2281
kajohnson@bozeman.net
Page 2 of 3
5/11/2022file:///C:/Users/aje/AppData/Local/Temp/XPgrpwise/6256E115tdhinctdhincpo1001693764...
City of Bozeman emails are subject to the Right to Know provisions of Montana’s Constitution (Art. II, Sect.
9) and may be considered a “public record” pursuant to Title 2, Chpt. 6, Montana Code Annotated. As such,
this email, its sender and receiver, and the contents may be available for public disclosure and will be
retained pursuant to the City’s record retention policies. Emails that contain confidential information such
as information related to individual privacy may be protected from disclosure under law.
Page 3 of 3
5/11/2022file:///C:/Users/aje/AppData/Local/Temp/XPgrpwise/6256E115tdhinctdhincpo1001693764...