Bozeman Bucks Hitting Facility – Construction Management Plan
The applicant plans to construct the project in one phase. The work will include necessary site grading, storm pond
construction, sidewalks, and construction of the building. During each step of the construction, the garbage and
materials will be managed. Below is a description of the Construction Management Plan.
PHASE 1
1. Site grading
During site grading, the excess materials (topsoil & fill) will be hauled offsite and disposed of. Garbage will be
minimal in this portion of the construction and will be hauled offsite daily by the contractor. Minimal topsoil
will be stockpiled onsite and placed immediately sidewalk and building completion.
2. Infrastructure Installation
During the installation of the underground power and gas, the minimal garbage will be hauled offsite daily. The
pipe and wire will be stored at an offsite yard until the time of installation when it will be hauled to the site
and stored until it is installed. Staging areas are shown on the attached construction management exhibit.
3. Parking Lot Grading, Sidewalks & Building Pad Construction
The excess fill materials will be hauled offsite during the site grading phase of construction so minimal material
is anticipated to leave the site during the parking lot construction. The gravels will be trucked in on an as‐
needed basis. Concrete will be brought in with concrete trucks and the slab will be poured using a pump truck.
Excess concrete will be hauled away and disposed of off site.
4. Building Construction
During the construction of the building, a 20‐30 cubic yard dumpster will be onsite as shown on the attached
exhibit to manage the waste generated by the building. A portable toilet will be onsite during all phases of
construction. The building materials will be stored in the staging area during construction.
5. General Management
During this phase of construction, the access will be construction access with cobble runout pads until the
parking lot is paved. The construction access shall remain open to allow access for the EMS services.