HomeMy WebLinkAbout005_Civil Stormwater Design Report
DESIGN REPORT
STORMWATER MANAGEMENT
COTTAGES AT BLACKWOOD GROVES SITE PLAN
LOTS 1 & 2, BLOCK 10 AND LOTS 1 & 2, BLOCK 11
BLACKWOOD GROVES SUBDIVISION, PHASE 1
Prepared for:
Blackwood Land Fund, LLC
140 Village Crossing Way, Unit 3B
Bozeman, MT 59715
Prepared by:
Project Number: 211217
November 2021
INTRODUCTION
The Cottages at Blackwood Groves consists of 58 one-, two-, and three-bedroom dwelling units,
located on Lots 1&2, Block 10 and Lots 1&2, Block 11 of Blackwood Groves Subdivision, Phase
1. As part of the Blackwood Groves Subdivision, Phase 1 Infrastructure design stormwater ponds
were sized to detain portions of the runoff from the multi-family lots located on Blocks 10 and 11.
Runoff generated beyond the allocated limit will be stored on each block in retention ponds.
Supporting stormwater calculations are attached to this report. A Drainage Area Map is included
in Appendix A. Calculations for each individual drainage area are included in Appendix B. Pond
sizing calculations are included in Appendix C. Groundwater depth information is included in
Appendix D. The Blackwood Groves, Phase 1 Stormwater Design Report is included in Appendix
E.
DRAINAGE AREAS
Drainage Area 1
Drainage Area 1 consists of the western portion of Lot 1, Block 10. Drainage Area discharges into
the subdivision R.O.W. and will be treated in the subdivision Detention Pond 9. Roof downspouts
and swales between the buildings will convey the runoff to the R.O.W. Drainage Area 1 of the
Cottages Site Plan corresponds to Drainage Area 9G of the Phase 1 Design Report (see Appendix
E). Based on the Phase 1 design report, Lot 1, Block 10 was assigned a C value of C=0.6, which
equates to a C*Area (Rational “C” factor multiplied by the drainage basin area) of 23,911 sf. The
C*Area of Drainage Area 1 is 16,777, which is well below the allocated value for the lot. As such,
the existing subdivision infrastructure has capacity to handle Drainage Area 1.
Drainage Area 2
Drainage Area 2 consists of the largest portion of Block 10. Runoff from this drainage area will
be retained in Retention Pond 1, located in the north portion of the site. This pond was sized to
retain the 10-year, 2-hour storm. In addition to the 10-year, 2-hour storm the proposed retention
ponds were sized to retain the runoff generated from the first 0.5” of rainfall, otherwise known as
the Runoff Reduction Volume (RRV.). It was determined that the 10-year, 2-hour storm and RRV
required 833 cubic feet of storage and 424 cubic feet of storage, respectively. Retention Pond 1
provided 993 cubic feet of storage.
Drainage Area 3
Drainage Area 3 consists of the southern portion of Lots 1&2, Block 10. Drainage Area 3
discharges into the subdivision R.O.W. and will be treated in the subdivision Detention Pond 9.
Drainage Area 3 of the Cottages Site Plan corresponds to Drainage Area 9D of the Phase 1 Design
Report. Based on the Phase 1 design report, Lot 2, Block 10 was assigned a C value of C=0.4,
which equates to a C*Area (Rational “C” factor multiplied by the drainage basin area) of 5,138 sf.
The C*Area of Drainage Area 3 is 4,910, which is below the allocated value for the lot. As such,
the existing subdivision infrastructure has capacity to handle Drainage Area 3.
Drainage Area 4
Drainage Area 4 consists of the northern and eastern portions of Lot 2, Block 10. Drainage Area 4
discharges into the subdivision R.O.W. and will be treated in the subdivision Detention Pond 8C.
Drainage Area 4 of the Cottages Site Plan corresponds to Drainage Area 8J of the Phase 1 Design
Report. Based on the Phase 1 design report, Lot 2, Block 10 was assigned a C value of C=0.4,
which equates to a C*Area (Rational “C” factor multiplied by the drainage basin area) of 9,561 sf.
The C*Area of Drainage Area 3 is 9,455 sf, which is below the allocated value for the lot. As such,
the existing subdivision infrastructure has capacity to handle Drainage Area 4.
Drainage Area 5
Drainage Area 5 consists of a small portion of Lot 2, Block 10. Runoff from this drainage area will
be retained in Retention Pond 4, located in the south portion of the site. This pond was sized to
retain the 10-year, 2-hour storm and the RRV. It was determined that the 10-year, 2-hour storm
and RRV required 211 cubic feet of storage and 110 cubic feet of storage, respectively. Retention
Pond 4 provided 215 cubic feet of storage.
Drainage Area 6
Drainage Area 6 consists of a small portion of Lot 2, Block 10. Runoff from this drainage area will
be retained in Retention Pond 3, located in the eastern half of the site. This pond was sized to retain
the 10-year, 2-hour storm and the RRV. It was determined that the 10-year, 2-hour storm and RRV
required 220 cubic feet of storage and 127 cubic feet of storage, respectively. Retention Pond 3
provided 225 cubic feet of storage.
Drainage Area 7
Drainage Area 7 consists of a small portion of Lot 2, Block 10. Runoff from this drainage area will
be retained in Retention Pond 2, located in the central portion of the site. This pond was sized to
retain the 10-year, 2-hour storm and the RRV. It was determined that the 10-year, 2-hour storm
and RRV required 120 cubic feet of storage and 68 cubic feet of storage, respectively. Retention
Pond 2 provided 125 cubic feet of storage.
Drainage Area 8
Drainage Area 8 consists of the western portion of Lot 1, Block 11. Drainage Area discharges into
the subdivision R.O.W. and will be treated in the subdivisions’ Detention Pond 8C. Drainage Area
8 of the Cottages Site Plan corresponds to Drainage Area 8L of the Phase 1 Design Report. Based
on the Phase 1 design report, Lot 1, Block 11 was assigned a C value of C=0.4, which equates to
a C*Area (Rational “C” factor multiplied by the drainage basin area) of 14,869 sf. The C*Area of
Drainage Area 3 is 13,918 sf, which is below the allocated value for the lot. As such, the existing
subdivision infrastructure has capacity to handle Drainage Area 8.
Drainage Area 9
Drainage Area 9 consists of the largest portion of Block 11. Runoff from this drainage area will
be retained in Retention Pond 6, located in the north portion of the block. This pond was sized to
retain the 10-year, 2-hour storm and RRV. It was determined that the 10-year, 2-hour storm and
RRV required 958 cubic feet of storage and 493 cubic feet of storage, respectively. Retention Pond
6 provided 1,404 cubic feet of storage.
Drainage Area 10
Drainage Area 10 consists of the eastern portion of Lot 2, Block 11. Drainage Area discharges into
the subdivision R.O.W. and will be treated in the subdivisions’ Detention Pond 8A. Drainage Area
10 of the Cottages Site Plan corresponds to Drainage Area 8A of the Phase 1 Design Report. Based
on the Phase 1 design report, Lot 2, Block 11 was assigned a C value of C=0.4, which equates to
a C*Area (Rational “C” factor multiplied by the drainage basin area) of 14,162 sf. The C*Area of
Drainage Area 3 is 13,602 sf, which is below the allocated value for the lot. As such, the existing
subdivision infrastructure has capacity to handle Drainage Area 10.
Drainage Area 11
Drainage Area 11 consists of the southwest portion of Lot 1, Block 11. Runoff from this drainage
area will be retained in Retention Pond 5, located in the southwest portion of the lot. This pond
was sized to retain the 10-year, 2-hour storm and the RRV. It was determined that the 10-year, 2-
hour storm and RRV required 268 cubic feet of storage and 137 cubic feet of storage, respectively.
Retention Pond 5 provided 275 cubic feet of storage.
Drainage Area 12
Drainage Area 12 consists of the southeast portion of Lot 2, Block 11. Runoff from this drainage
area will be retained in Retention Pond 7, located in the southeast portion of the lot. This pond was
sized to retain the 10-year, 2-hour storm and the RRV. It was determined that the 10-year, 2-hour
storm and RRV required 392 cubic feet of storage and 204 cubic feet of storage, respectively.
Retention Pond 7 provided 395 cubic feet of storage.
Table 1: Pond Sizing Summary
Pond Contributing Area (sf) Weighted C-Value Runoff Reduction Volume (cf)
Required Retention Storage Volume (cf)
Proposed Storage Volume (cf)
1 24,135 0.51 424 833 993
2 2,588 0.68 68 120 125
3 4,540 0.72 127 220 225
4 5,719 0.54 110 211 215
5 7,699 0.51 137 268 275
6 27,073 0.52 493 958 1,404
7 10,770 0.54 204 392 395
GROUNDWATER CONSIDERATIONS
Groundwater monitoring wells were installed across the subject property in 2019 and were
monitored throughout the spring/summer of 2019 and spring of 2020 during the subdivision
preliminary plat process. The results generally showed that seasonal high groundwater (SHGW)
peaked in early April, and ranged from 7” to 3.5’ below existing grade. This information was used
to generate a SHGW elevation surface in AutoCAD to reference during the stormwater design for
the subdivision. All proposed ponds in the development are set with the bottom of pond elevation
above the SHGW elevation in the pond footprint. The proposed retention pond elevations and
approximate SHGW elevations are listed in Table 3 below. The groundwater monitoring results
can be found in Appendix D.
Table 2: SHGW and Proposed Pond Elevations
Pond Approximate Existing Surface Elevation (ft)
Estimated Peak Groundwater Elevation (ft. bgs)
Estimated Peak Groundwater Elevation (ft.)
Proposed Pond Top Elevation (ft)
Proposed Pond Bottom Elevation (ft.)
1 5006.5 1.0 5005.5 5007.03 5008.53
2 5006.5 1.2 5005.3 5008.74 5007.24
3 5007.7 1.5 5006.2 5008.90 5007.40
4 5008.5 1.6 5006.9 5010.00 5008.50
5 5008.5 2.8 5005.7 5009.90 5008.40
6 5004.8 0.9 5004.9 5005.86 5004.36
7 5006.3 1.5 5004.8 5000.65 4999.15
G:\C&H\21\211217\Design Reports\Storm\211217 Stormwater Design Report.Docx
APPENDIX A
DRAINAGE AREA MAP
APPENDIX B
DRAINAGE AREA CALCULATIONS
DRAINAGE AREA #1
DRAINAGE AREA #1
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft2 )C * Area
Hardscape 0.95 4424 4202
Roof 0.95 11072 10518
Landscape 0.20 10280 2056
Total 25776 16777
A = Area (acres)0.5917
C = Weighted C Factor 0.65
C* Area (ft 2 ) =16,777
Allocated C* Area (ft2 ) =23,911
(Drainage Area 9G)*
*Blackwood Groves, Phase 1 Stormwater Design Report
DRAINAGE AREA #2
DRAINAGE AREA #2
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2)C * Area
Hardscape 0.95 2713 2577
Roof 0.95 7243 6881
Landscape 0.20 14180 2836
Total 24135 12294
A = Area (acres)0.5541
C = Weighted C Factor 0.51
DRAINAGE AREA #3
DRAINAGE AREA #3
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2)C * Area
Hardscape 0.95 1458 1385
Roof 0.95 2521 2395
Landscape 0.20 5653 1131
Total 9631 4910
A = Area (acres)0.2211
C = Weighted C Factor 0.51
C* Area (ft 2 ) =4,910
Allocated C* Area (ft2 ) =5,138
(Drainage Area 9D)*
*Blackwood Groves, Phase 1 Stormwater Design Report
DRAINAGE AREA #4
DRAINAGE AREA #4
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2)C * Area
Hardscape 0.95 2986 2837
Roof 0.95 5597 5317
Landscape 0.20 6508 1302
Total 15091 9455
A = Area (acres)0.3464
C = Weighted C Factor 0.63
C* Area (ft 2 ) =9,455
Allocated C* Area (ft2 ) =9,561
(Drainage Area 8J)*
*Blackwood Groves, Phase 1 Stormwater Design Report
DRAINAGE AREA #5
DRAINAGE AREA #5
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2)C * Area
Hardscape 0.95 651 618
Roof 0.95 1974 1875
Landscape 0.20 3094 619
Total 5719 3112
A = Area (acres)0.1313
C = Weighted C Factor 0.54
DRAINAGE AREA #6
DRAINAGE AREA #6
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2)C * Area
Hardscape 0.95 401 381
Roof 0.95 2726 2590
Landscape 0.20 1413 283
Total 4540 3253
A = Area (acres)0.1042
C = Weighted C Factor 0.72
DRAINAGE AREA #7
DRAINAGE AREA #7
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2)C * Area
Hardscape 0.95 243 230
Roof 0.95 1422 1351
Landscape 0.20 923 185
Total 2588 1766
A = Area (acres)0.0594
C = Weighted C Factor 0.68
DRAINAGE AREA #8
DRAINAGE AREA #8
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2)C * Area
Hardscape 0.95 3801 3611
Roof 0.95 9150 8692
Landscape 0.20 8077 1615
Total 21027 13918
A = Area (acres)0.4827
C = Weighted C Factor 0.66
C* Area (ft 2 ) =13,918
Allocated C* Area (ft2 ) =14,869
(Drainage Area 8L)*
*Blackwood Groves, Phase 1 Stormwater Design Report
DRAINAGE AREA #9
DRAINAGE AREA #9
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2)C * Area
Hardscape 0.95 3086 2932
Roof 0.95 8551 8123
Landscape 0.20 15436 3087
Total 27073 14142
A = Area (acres)0.6215
C = Weighted C Factor 0.52
DRAINAGE AREA # 10
DRAINAGE AREA #10
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2)C * Area
Hardscape 0.95 3697 3512
Roof 0.95 8992 8542
Landscape 0.20 7737 1547
Total 20425 13602
A = Area (acres)0.4689
C = Weighted C Factor 0.67
C* Area (ft 2 ) =13,602
Allocated C* Area (ft2 ) =14,162
(Drainage Area 8A)*
*Blackwood Groves, Phase 1 Stormwater Design Report
DRAINAGE AREA # 11
DRAINAGE AREA #11
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2)C * Area
Hardscape 0.95 1188 1128
Roof 0.95 2035 1933
Landscape 0.20 4476 895
Total 7699 3957
A = Area (acres)0.1767
C = Weighted C Factor 0.51
DRAINAGE AREA # 12
DRAINAGE AREA #12
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2)C * Area
Hardscape 0.95 1493 1418
Roof 0.95 3351 3183
Landscape 0.20 5926 1185
Total 10770 5787
A = Area (acres)0.2472
C = Weighted C Factor 0.54
APPENDIX C
POND SIZING CALCULATIONS
RETENTION POND 1
REQUIRED VOLUME
1. Calculate Area and Weighted C Factor (Post-Development)
Contributing Area C Area (ft 2 )C * Area
Hardscape 0.95 2713 2577
Roof 0.95 7243 6881
Landscape 0.2 14180 2836
Total 24135 12294
A = Area (acres)0.5541
C = Weighted C Factor 0.51
2. Calculate Required Volume
Q = CIA
V=7200Q
C = Weighted C Factor 0.51
I = intensity (in/hr) 0.41 (10 yr, 2hr storm)
A = Area (acres)0.55
Q = runoff (cfs)0.12
V = REQUIRED VOL (ft3)833
PROVIDED VOL (ft3)993
Check the half inch requirement (per DSSP II.A.4)
3. Determine Area of Hardscape within Drainage Area #2
Contributing Area Area (ft 2 )
Hardscape 9,956
4. Calculate 1/2" runoff volume over hardscape
(aka Runoff Reduction Volume [RRV] as calculated in Montana Post-
Construction Storwater BMP Manual - Equation 3-1)
RRV = [P*Rv*A]/12
P = Water quality rainfall depth 0.50 inches
Rv = Dimensionless runoff coefficient 0.42 0.05 + 0.9*I
I = Percent impervious cover (decimal)0.41 decimal
A = Entire drainage area 0.55 acres
RRV = Runoff Reduction Volume 0.010 acre-ft
RRV = Runoff Reduction Volume 424 cubic feet
Because the runoff volume from the 10-yr, 2-hr storm (for flood control) is
greater than the runoff volume produced by the half inch rainfall (for water quality)
the retention facility is sized to handle the larger volume (740 cf).
RETENTION POND 2
REQUIRED VOLUME
1. Calculate Area and Weighted C Factor (Post-Development)
Contributing Area C Area (ft 2)C * Area
Hardscape 0.95 243 230
Roof 0.95 1422 1351
Landscape 0.2 923 185
Total 2588 1766
A = Area (acres)0.0594
C = Weighted C Factor 0.68
2. Calculate Required Volume
Q = CIA
V=7200Q
C = Weighted C Factor 0.68
I = intensity (in/hr) 0.41 (10 yr, 2hr storm)
A = Area (acres)0.06
Q = runoff (cfs)0.02
V = REQUIRED VOL (ft3)120
PROVIDED VOL (ft3)125
Check the half inch requirement (per DSSP II.A.4)
3. Determine Area of Hardscape within Drainage Area #7
Contributing Area Area (ft 2 )
Hardscape 1,665
4. Calculate 1/2" runoff volume over hardscape
(aka Runoff Reduction Volume [RRV] as calculated in Montana Post-
Construction Storwater BMP Manual - Equation 3-1)
RRV = [P*Rv*A]/12
P = Water quality rainfall depth 0.50 inches
Rv = Dimensionless runoff coefficient 0.63 0.05 + 0.9*I
I = Percent impervious cover (decimal)0.64 decimal
A = Entire drainage area 0.06 acres
RRV = Runoff Reduction Volume 0.002 acre-ft
RRV = Runoff Reduction Volume 68 cubic feet
Because the runoff volume from the 10-yr, 2-hr storm (for flood control) is
greater than the runoff volume produced by the half inch rainfall (for water quality)
the retention facility is sized to handle the larger volume (120 cf).
RETENTION POND 3
REQUIRED VOLUME
1. Calculate Area and Weighted C Factor (Post-Development)
Contributing Area C Area (ft 2)C * Area
Hardscape 0.95 401 381
Roof 0.95 2726 2590
Landscape 0.2 1413 283
Total 4540 3253
A = Area (acres)0.1042
C = Weighted C Factor 0.72
2. Calculate Required Volume
Q = CIA
V=7200Q
C = Weighted C Factor 0.72
I = intensity (in/hr) 0.41 (10 yr, 2hr storm)
A = Area (acres)0.10
Q = runoff (cfs)0.03
V = REQUIRED VOL (ft3)220
PROVIDED VOL (ft3)225
Check the half inch requirement (per DSSP II.A.4)
3. Determine Area of Hardscape within Drainage Area #6
Contributing Area Area (ft 2 )
Hardscape 3,127
4. Calculate 1/2" runoff volume over hardscape
(aka Runoff Reduction Volume [RRV] as calculated in Montana Post-
Construction Storwater BMP Manual - Equation 3-1)
RRV = [P*Rv*A]/12
P = Water quality rainfall depth 0.50 inches
Rv = Dimensionless runoff coefficient 0.67 0.05 + 0.9*I
I = Percent impervious cover (decimal)0.69 decimal
A = Entire drainage area 0.10 acres
RRV = Runoff Reduction Volume 0.003 acre-ft
RRV = Runoff Reduction Volume 127 cubic feet
Because the runoff volume from the 10-yr, 2-hr storm (for flood control) is
greater than the runoff volume produced by the half inch rainfall (for water quality)
the retention facility is sized to handle the larger volume (220 cf).
RETENTION POND 4
REQUIRED VOLUME
1. Calculate Area and Weighted C Factor (Post-Development)
Contributing Area C Area (ft2 )C * Area
Hardscape 0.95 651 618
Roof 0.95 1974 1875
Landscape 0.2 3094 619
Total 5719 3112
A = Area (acres)0.1313
C = Weighted C Factor 0.54
2. Calculate Required Volume
Q = CIA
V=7200Q
C = Weighted C Factor 0.54
I = intensity (in/hr) 0.41 (10 yr, 2hr storm)
A = Area (acres)0.13
Q = runoff (cfs)0.03
V = REQUIRED VOL (ft3)211
PROVIDED VOL (ft3)215
Check the half inch requirement (per DSSP II.A.4)
3. Determine Area of Hardscape within Drainage Area #5
Contributing Area Area (ft 2)
Hardscape 2,624
4. Calculate 1/2" runoff volume over hardscape
(aka Runoff Reduction Volume [RRV] as calculated in Montana Post-
Construction Storwater BMP Manual - Equation 3-1)
RRV = [P*Rv*A]/12
P = Water quality rainfall depth 0.50 inches
Rv = Dimensionless runoff coefficient 0.46 0.05 + 0.9*I
I = Percent impervious cover (decimal)0.46 decimal
A = Entire drainage area 0.13 acres
RRV = Runoff Reduction Volume 0.003 acre-ft
RRV = Runoff Reduction Volume 110 cubic feet
Because the runoff volume from the 10-yr, 2-hr storm (for flood control) is
greater than the runoff volume produced by the half inch rainfall (for water quality)
the retention facility is sized to handle the larger volume (211 cf).
RETENTION POND 5
REQUIRED VOLUME
1. Calculate Area and Weighted C Factor (Post-Development)
Contributing Area C Area (ft2 )C * Area
Hardscape 0.95 1188 1128
Roof 0.95 2035 1933
Landscape 0.2 4476 895
Total 7699 3957
A = Area (acres)0.1767
C = Weighted C Factor 0.51
2. Calculate Required Volume
Q = CIA
V=7200Q
C = Weighted C Factor 0.51
I = intensity (in/hr) 0.41 (10 yr, 2hr storm)
A = Area (acres)0.18
Q = runoff (cfs)0.04
V = REQUIRED VOL (ft3)268
PROVIDED VOL (ft3)275
Check the half inch requirement (per DSSP II.A.4)
3. Determine Area of Hardscape within Drainage Area #11
Contributing Area Area (ft 2 )
Hardscape 3,223
4. Calculate 1/2" runoff volume over hardscape
(aka Runoff Reduction Volume [RRV] as calculated in Montana Post-
Construction Storwater BMP Manual - Equation 3-1)
RRV = [P*Rv*A]/12
P = Water quality rainfall depth 0.50 inches
Rv = Dimensionless runoff coefficient 0.43 0.05 + 0.9*I
I = Percent impervious cover (decimal)0.42 decimal
A = Entire drainage area 0.18 acres
RRV = Runoff Reduction Volume 0.003 acre-ft
RRV = Runoff Reduction Volume 137 cubic feet
Because the runoff volume from the 10-yr, 2-hr storm (for flood control) is
greater than the runoff volume produced by the half inch rainfall (for water quality)
the retention facility is sized to handle the larger volume (256 cf).
RETENTION POND 6
REQUIRED VOLUME
1. Calculate Area and Weighted C Factor (Post-Development)
Contributing Area C Area (ft 2 )C * Area
Hardscape 0.95 3086 2932
Roof 0.95 8551 8123
Landscape 0.2 15436 3087
Total 27073 14142
A = Area (acres)0.6215
C = Weighted C Factor 0.52
2. Calculate Required Volume
Q = CIA
V=7200Q
C = Weighted C Factor 0.52
I = intensity (in/hr) 0.41 (10 yr, 2hr storm)
A = Area (acres)0.62
Q = runoff (cfs)0.13
V = REQUIRED VOL (ft3)958
PROVIDED VOL (ft3)1404
Check the half inch requirement (per DSSP II.A.4)
3. Determine Area of Hardscape within Drainage Area #9
Contributing Area Area (ft2 )
Hardscape 11,637
4. Calculate 1/2" runoff volume over hardscape
(aka Runoff Reduction Volume [RRV] as calculated in Montana Post-
Construction Storwater BMP Manual - Equation 3-1)
RRV = [P*Rv*A]/12
P = Water quality rainfall depth 0.50 inches
Rv = Dimensionless runoff coefficient 0.44 0.05 + 0.9*I
I = Percent impervious cover (decimal)0.43 decimal
A = Entire drainage area 0.62 acres
RRV = Runoff Reduction Volume 0.011 acre-ft
RRV = Runoff Reduction Volume 493 cubic feet
Because the runoff volume from the 10-yr, 2-hr storm (for flood control) is
greater than the runoff volume produced by the half inch rainfall (for water quality)
the retention facility is sized to handle the larger volume (967 cf).
RETENTION POND 7
REQUIRED VOLUME
1. Calculate Area and Weighted C Factor (Post-Development)
Contributing Area C Area (ft 2 )C * Area
Hardscape 0.95 1493 1418
Roof 0.95 3351 3183
Landscape 0.2 5926 1185
Total 10770 5787
A = Area (acres)0.2472
C = Weighted C Factor 0.54
2. Calculate Required Volume
Q = CIA
V=7200Q
C = Weighted C Factor 0.54
I = intensity (in/hr) 0.41 (10 yr, 2hr storm)
A = Area (acres)0.25
Q = runoff (cfs)0.05
V = REQUIRED VOL (ft3)392
PROVIDED VOL (ft3)395
Check the half inch requirement (per DSSP II.A.4)
3. Determine Area of Hardscape within Drainage Area #12
Contributing Area Area (ft2 )
Hardscape 4,844
4. Calculate 1/2" runoff volume over hardscape
(aka Runoff Reduction Volume [RRV] as calculated in Montana Post-
Construction Storwater BMP Manual - Equation 3-1)
RRV = [P*Rv*A]/12
P = Water quality rainfall depth 0.50 inches
Rv = Dimensionless runoff coefficient 0.45 0.05 + 0.9*I
I = Percent impervious cover (decimal)0.45 decimal
A = Entire drainage area 0.25 acres
RRV = Runoff Reduction Volume 0.005 acre-ft
RRV = Runoff Reduction Volume 204 cubic feet
Because the runoff volume from the 10-yr, 2-hr storm (for flood control) is
greater than the runoff volume produced by the half inch rainfall (for water quality)
the retention facility is sized to handle the larger volume (384 cf).
APPENDIX D
GROUNDWATER DEPTH INFORMATION
Project Engineer:
Project:
South Bozeman, Gallatin County, MT
Well Information:bgs = below ground surface ags = above ground surface
MW-1 MW-2 MW-3 MW-4 MW-5 MW-6 MW-7 MW-8 MW-9 MW-10 MW-11 MW-12 MW-13 MW-14 MW-15 MW-16 MW-17 MW-18 MW-19 MW-20
3.83 3.00 3.08 3.67 1.50 2.42 2.08 3.58 2.92 2.92 3.83 2.92 3.92 3.58 4.08 3.00 3.92 3.50 3.58 2.92
Groundwater Information:
MW-1 MW-2 MW-3 MW-4 MW-5 MW-6 MW-7 MW-8 MW-9 MW-10 MW-11 MW-12 MW-13 MW-14 MW-15 MW-16 MW-17 MW-18 MW-19 MW-20
3.34 3.05 3.02 2.78 3.45 1.58 4.24 4.27 2.55 4.13 3.99 4.36 2.25 2.27 2.26 5.50 2.71 2.20 2.97 2.38
3.47 3.18 3.11 2.85 3.49 1.50 4.42 4.42 2.64 4.34 4.31 4.78 2.50 2.32 2.60 6.10 2.85 2.42 3.40 2.77
3.57 3.23 3.13 2.94 4.10 1.64 4.53 4.53 2.67 4.45 4.36 4.90 2.54 2.39 2.65 6.21 2.92 2.74 3.74 2.96
3.75 3.42 3.26 3.18 3.74 1.88 4.72 4.70 2.80 4.59 4.50 5.16 2.84 2.54 2.84 6.32 3.18 3.14 4.07 3.19
3.78 3.63 3.36 3.35 3.81 1.94 4.90 4.98 2.99 4.86 4.56 5.31 3.16 2.83 3.23 DRY 3.79 3.68 4.31 3.49
3.76 3.65 3.41 3.43 3.76 1.91 4.94 5.11 3.09 4.98 4.68 5.48 3.25 2.79 3.30 DRY 4.17 3.91 4.51 3.56
3.94 3.82 3.52 3.45 3.83 2.00 4.90 5.23 3.27 5.08 4.82 5.60 3.42 2.88 3.37 DRY 4.29 4.05 4.67 3.59
3.90 3.68 3.38 3.31 3.75 1.94 4.85 4.93 3.08 5.02 4.86 5.66 3.37 2.88 3.20 DRY 4.22 4.11 4.80 3.48
4.00 3.87 3.55 3.60 4.01 2.24 5.11 5.23 3.44 5.18 4.82 5.65 3.54 3.13 3.46 DRY 4.59 4.31 4.87 3.80
4.09 3.52 3.34 3.33 3.81 2.09 5.06 5.03 3.11 4.99 5.42 5.08 3.34 2.89 3.37 DRY 4.59 4.41 4.47 3.60
4.14 4.09 3.69 3.72 3.92 2.34 5.24 5.42 3.69 5.39 4.95 5.78 3.73 3.34 3.69 DRY 4.87 4.65 5.03 3.89
4.16 4.38 4.13 4.01 4.12 2.49 5.43 5.70 4.06 5.99 5.27 6.24 4.20 3.79 3.99 DRY 5.29 5.19 5.63 4.07
ICE 2.50 2.49 2.03 ICE 0.93 3.43 3.60 2.39 ICE 3.69 3.88 1.38 1.47 1.82 4.04 2.27 0.96 2.07 2.01
1.99 1.95 2.16 1.64 3.00 0.63 3.04 3.29 2.19 3.08 3.07 3.33 0.72 0.72 0.87 3.57 2.10 0.60 1.67 1.28
2.65 2.25 2.37 1.93 3.35 1.03 3.14 3.47 2.29 3.26 3.29 3.60 1.18 1.62 1.57 3.60 2.30 1.20 2.19 1.45
2.94 2.50 2.53 2.17 1.90 1.54 3.32 3.68 2.33 3.53 3.63 3.83 1.56 1.53 1.86 4.13 2.40 1.45 2.47 1.86
3.27 2.97 2.84 2.64 2.35 1.42 3.72 4.30 2.48 3.95 3.92 4.23 2.00 1.67 2.13 4.52 2.68 2.04 3.07 2.38
3.47 3.20 3.00 2.85 2.50 1.52 3.94 4.38 2.59 4.23 4.17 4.61 2.30 2.29 2.42 4.97 2.81 2.55 3.42 2.70
3.57 3.28 3.10 2.98 2.60 1.68 4.13 4.52 2.65 4.39 4.37 4.88 2.53 2.35 2.64 DRY 2.91 2.92 3.85 2.93
3.68 3.38 3.21 3.10 2.70 1.74 4.29 4.68 2.70 4.54 4.57 5.10 2.73 2.43 2.81 DRY 3.12 3.30 4.13 3.17
3.79 3.51 3.32 3.20 2.66 1.89 4.51 4.79 2.81 4.71 4.74 5.32 2.93 2.60 2.97 DRY 3.47 3.56 4.37 3.33
3.92 3.63 3.51 3.38 2.79 1.95 4.79 4.90 2.92 4.89 4.78 5.49 3.08 2.63 3.08 DRY 3.73 4.09 4.57 3.59
5.15.20
4.10.20
4.17.20
4.24.20
5.1.20
5.8.20
Well ID
Well Depth (feet-bgs)
Top of Well (feet-ags)
Ground Elevation
4.6.20
Date
5.10.19
6.10.19
6.17.19
6.20.19
6.28.19
7.12.19
7.26.19
8.9.19
Monitor Well Data
Depth to Ground Water (feet-bgs)
Project Number: 190390
South Bozeman Groundwater Monitoring
Project Location:
8.23.19
3.24.20
5.20.19
5.24.19
5.31.19
5.22.205.29.20
APPENDIX E
BLACKWOOD GROVES SUBDIVISION
PHASE 1 STORMWATER DESIGN REPORT
BLACKWOOD GROVES SUBDIVISION,
PHASE 1
STORMWATER
DESIGN REPORT
Prepared for:
Bridger Builders, Inc.
115 West Kagy Boulevard
Bozeman, MT 59715
Prepared by:
Project Number: 190390
July 29, 2021
BLACKWOOD GROVES SUBDIVISION – STORMWATER DESIGN REPORT
July 29, 2021
#190390 1
TABLE OF CONTENTS
REPORT
Introduction ..........................................................................................................................2
Existing Site Conditions ......................................................................................................2
Pre-Development Drainage Areas .......................................................................................2
Storm Sewer Facilities Design .............................................................................................3
Post-Development Drainage Areas ......................................................................................4
Stormwater Pond Design .....................................................................................................6
Groundwater Considerations ...............................................................................................8
APPENDICES
Appendix A: Drainage Area Maps
Appendix B: Pre-Development Drainage Area Calculations
Appendix C: Post-Development Drainage Area Calculations
Appendix D: Pond Sizing Calculations
Appendix E: Groundwater Monitoring Data
BLACKWOOD GROVES SUBDIVISION – STORMWATER DESIGN REPORT
July 29, 2021
#190390 2
INTRODUCTION
The Blackwood Groves Subdivision is a proposed 120-acre development located at the south
side of the City of Bozeman. The proposed project is zoned as Residential Emphasis Mixed Use
(REMU) and will feature a variety of commercial, residential, and park/open space
developments. As part of the project, public improvements, including water, sanitary sewer,
stormwater, and City road infrastructure are proposed. This report is intended to evaluate the
drainage design for Phase 1 of the development.
EXISTING SITE CONDITIONS
The existing property is currently vacant and is being used for agricultural purposes. The
property is bounded by S. 19th Avenue to the west, vacant agricultural land and Alder Creek
Subdivision to the north, Sacajawea Middle School to the east, and vacant agricultural land to the
south. The property generally slopes from south to north at 1%-2%. Several agricultural
irrigation ditches, and watercourses cross the property. Based on site topography, stormwater
runoff on the existing site currently drains to 4 of these water features that cross the property via
overland sheet flow. A large portion of the approximately 119-acre agricultural property to the
south of the project also sheet flows onto the project site, draining to these same 4 water features.
PRE-DEVELOPMENT DRAINAGE AREAS
Stormwater runoff from the proposed site improvements will primarily be controlled and treated
through the use of several proposed detention ponds that will release runoff into these 4 water
features. These detention ponds will discharge runoff into these water features at the pre-
development runoff rates that currently contribute to these water features from the existing site.
In order to determine the pre-development runoff rates, pre-development drainage areas were
delineated for each water feature on the subject property. These drainage areas are shown on the
“Pre-Development Drainage Area Plan” in Appendix A.
City of Bozeman GIS contours were used in order to determine the portion of the property to the
south of the site that sheet flows onto the subject property. These contours are shown in yellow
on the Pre-Development Drainage Area Plan. As shown by the slight overlap of these GIS
BLACKWOOD GROVES SUBDIVISION – STORMWATER DESIGN REPORT
July 29, 2021
#190390 3
contours with the contours produced from the topographic survey that C&H Engineering
performed of the project site, these GIS contours match extremely well with the contours from
the survey.
EX DA #1 accounts for runoff from the subject property that currently drains to the irrigation
ditch located along the east side of the S. 19th Avenue right-of-way, labeled “Irrigation Ditch –
West” for the purposes of this report. EX DA #2 accounts for runoff draining to the irrigation
ditch running east/west along the north property boundary, labeled “Irrigation Ditch – North” for
the purposes of this report. This drainage area also collects runoff from a large portion of the
property to the south of the project site. EX DA #3 accounts for runoff contributing to the
irrigation ditch located at the eastern side of the property that continues through Alder Creek
Subdivision to the north. This ditch is labeled as “Irrigation Ditch – Center” for the purposes of
this report. The final drainage area, EX DA #4, accounts for runoff from the far eastern portion
of the site that drains to the two watercourses that converge and drain north into the park in Alder
Creek Subdivision. These watercourses are labeled as “Unnamed Watercourse – Center” and
“Unnamed Watercourse – East” for the purposes of this report. This drainage area also collects
runoff from a portion of the property to the south of the project site. Calculations for the time of
concentration, and pre-development runoff rates for these drainage areas can be found in
Appendix B.
STORM SEWER FACILITIES DESIGN
Stormwater runoff from the proposed improvements will be conveyed via curb and gutter
channel flow to a series of curb chases and storm sewer inlets. It will then be routed through
storm drainage pipes to detention and retention ponds for storage. The detention ponds will
release runoff at pre-development runoff rates into 4 of the irrigation ditches and watercourses
that flow through the property. Pre and Post development Drainage Area Maps are included in
Appendix A, and calculations for pond sizing for each of the post development drainage areas
(total area, weighted C factor, required and provided storage volumes, and discharge rates) are
included in Appendix C.
BLACKWOOD GROVES SUBDIVISION – STORMWATER DESIGN REPORT
July 29, 2021
#190390 4
Storm sewer facilities were sized for the 25-yr storm using Manning’s Equation, and for each
inlet, the contributing area, gutter capacity, weighted C factor, and time of concentration were
calculated. These values were input into Manning’s Equation to check capacity and flow
characteristics for inlets, storm drain pipes, and curb gutters. All curb gutters were designed to
maintain 0.15’ freeboard per C.O.B. Design Manual Section IV.C.5.
POST-DEVELOPMENT DRAINAGE AREAS
This phase of the project was divided into 7 drainage areas based on the retention or detention
ponds that these areas will eventually drain to. These drainage areas are further divided based on
the proposed use within each area. This stormwater design conservatively assumes that 100% of
the runoff from the multifamily and commercial lots will drain to these common stormwater
ponds, and that no stormwater storage or treatment will take place on the individual lots. Phase 1
consists of Drainage Areas 6-9, and a small portion of Drainage Area 5.
Each area type was assigned a C-value based on the proposed use. Several of these C-values (i.e.
open land, and low/medium density residential) were taken from Table I-1 in the City of
Bozeman Design Standards and Specifications, while the remainder were calculated based on the
impervious and landscaped cover ratios anticipated in each area. The C-value for each right-of-
way type (local, collector, alley, angled-parking) were calculated based on the ratio of
impervious to landscaped area of the standard cross-section of these right-of-ways.
The dense residential C-value for the lots that are proposed for multi-family developments was
calculated by reviewing the impervious/landscaped ratios for the proposed layouts for several of
these lots, and averaging the C-values. This produced a C-value of 0.75, which is more
conservative than the dense residential value of 0.50 from Table I-1 in the city standards. Several
of the dense residential lots have the space to provide onsite stormwater management. Therefore,
these lots located in Drainage Area 8 and a portion of Drainage Area 9 (DA #9C) have been
assigned a reduced C-value of 0.40. The C-value for the several commercial blocks that are
intended to be the development’s “town center” was conservatively assumed to be 0.95, or
completely impervious. The proposed commercial lots in Block 1 and Block 13 were assigned
BLACKWOOD GROVES SUBDIVISION – STORMWATER DESIGN REPORT
July 29, 2021
#190390 5
the same C-value as the dense residential lots (0.75) since they are not intended to be developed
as densely as the town center lots. This C-value of 0.75 is more conservative than the
commercial neighborhood C-value of 0.60 from Table I-1 in the city standards. The C-values for
each area type are provided in the following table:
Table 1: C-Values
Area Type C-Value
ROW – Local 0.76
ROW – Collector 0.70
ROW – Alley 0.80
ROW – Angled 0.93
Residential – Low/Med 0.35
Residential - Dense 0.75
Residential –Dense
(Reduced C) 0.40
Commercial 0.95
Open Space 0.20
Park 0.20
The extents of the post development drainage areas can be seen on the drainage area map
included in Appendix A. It should be noted that only the Spring Ridge Drive portion of Drainage
Area 5 will be installed with this phase of the project. Similarly, only the South 11th Avenue
portion of Drainage Areas 6 & 7 will be installed with this phase. The proposed drainage area
map further subdivides the drainage areas (9A, 9B, 9C etc.) based on which inlet they are
draining to. In addition, time of concentration flow paths for each sub-area are depicted on the
proposed drainage area map. It should be noted that overland flow from the right-of-way line to
the curb flow line used a composite C value of 0.50 in the time of concentration calculations.
The C value was based on a ratio of the landscape boulevard to hardscape sidewalk. Curb inlets
were spaced to provide adequate gutter flow capacity without encroaching more than 0.15-feet of
freeboard per C.O.B. Design Manual Section IV.C.5. Calculations showing the peak runoff value
BLACKWOOD GROVES SUBDIVISION – STORMWATER DESIGN REPORT
July 29, 2021
#190390 6
as well as the determined gutter capacity for the sub-areas are included in Appendix C.
Additionally, storm sewer pipes were sized to accommodate the 25-year storm flows. Pipe
capacity calculations are included in Appendix C.
Building design guidelines, enforced by the Property Owners Association, will include a
requirement, enforced in the covenants, for each individual lot owner to route their roof drainage
to rain barrels or on-site infiltration facilities, or to surface drain the runoff to the front side of the
lot where it will collect in the street. The site will be graded to make this feasible for each lot.
The proposed detention and retention facilities are sized to accommodate any and all lots that
route their roof runoff to the street; any lots utilizing on-site runoff storage will result in excess
storage capacity, and improved storm water treatment.
STORMWATER POND DESIGN
Detention Ponds 6-9 have been sized according to City of Bozeman Design Standards. In
accordance with the design standards the ponds were sized to retain the runoff generated from
the first 0.5” of rainfall, otherwise known as the Runoff Reduction Volume (RRV.). The
detention ponds are also sized to limit discharge to pre-development rates for the 10-year storm
event, while the retention pond is designed to store the runoff volume of the 10-year storm event.
Each pond has been designed with 4:1 side slopes and a max water storage depth of 1.5’.
The detention ponds have also been designed with outlet structures containing a slotted weir to
control the discharge rate from the ponds. In an effort to accommodate the RRV from each
drainage basin, the inlet into the outlet structures has been raised to allow for stormwater
retention prior to discharge. The portions of Block 12 and Block 17 draining to Detention Pond
8B will have to retain the RRV on their individual lots prior to discharging into the public
system, The RRV for the remainder all commercial and multi-family lots can be handled by the
proposed detention ponds. Calculations used for sizing each pond can be found in Appendix D.
Pond storage capacities were calculated using volume surfaces in AutoCAD Civil 3D.
BLACKWOOD GROVES SUBDIVISION – STORMWATER DESIGN REPORT
July 29, 2021
#190390 7
As stated previously, a small portion of the Drainage Area 5 will be installed with this phase of
the subdivision. There are two inlets that will discharge into Detention Pond 5 being installed
with this Phase 1. In order to manage the runoff from this area, a temporary retention pond will
be installed in the location of future Detention Pond #5. Pond sizing calculations can be found in
Appendix D.
The proposed design has several detention ponds that discharge to the same water feature / pre-
development drainage area. Where this occurs, the pre-development runoff rate was divided
amongst each of the contributing detention ponds, so that their total discharge rate does not
exceed the pre-development runoff rate for that drainage area / water feature. The pre-
development runoff rate from EX DA #2 draining into “Irrigation Ditch - North” was calculated
to be 8.73 cfs. Proposed Detention Pond #9 will discharge into “Irrigation Ditch – West”. It was
assumed that because the northern and western irrigation ditches rejoin north of the project area,
the same shared release rate calculated for EX DA #2 can be applied to detention ponds 8A, 8B,
8C and 9. Therefore, the combined discharge rates from each of these detention ponds totals 8.73
cfs.
Similarly Ponds 6 & 7 share a pre-development runoff rate generated from EX DA #4. There are
ponds to be installed with future phases that will also share this runoff rate. As such, the leftover
difference from Phase 1 can be applied to these future phases. The pre-development conditions
for each detention pond are included in the pond sizing calculations in Appendix C. A summary
of the pond sizing calculations can be found in Table 2 below.
Table 2: Pond Sizing Summary
Pond Storage type
Pre Development Drainage Area
Contributing Area (acre) Weighted C-Value
Runoff Reduction Volume (cf)
Required Detention Storage Volume (cf)
Proposed Storage Volume (cf)
5 Retention - 0.62 0.76 810 1,118 1,992
6 Detention EX 4 3.68 0.72 4,494 4,669 4,777
7 Detention EX 4 8.04 0.71 11,699 12,218 12,484
8A Detention EX 2 7.60 0.55 4,586 5,028 5,130
8B Detention EX 2 9.56 0.58 5,061 5,094 5,098
8C Detention EX 2 5.77 0.47 3,903 2,733 3,925
9 Detention EX 2 22.53 0.67 25,002 55,563 57,340
A Retention - 0.16 0.76 205 351
BLACKWOOD GROVES SUBDIVISION – STORMWATER DESIGN REPORT
July 29, 2021
#190390 8
Due to grading limitations curb inlets could not be set on the northern property boundaries to
capture all drainage from the site. In an effort to retain the maximum practicable amount of
runoff curb chases are proposed to pick up additional runoff. There is approximately 6,000 sf of
local street R.O.W. in Spring Ridge Drive and South 15th Avenue that will drain into the
retention pond located at the NW corner of the Alder Creek Subdivision. The new development
will generate an additional extra 618 cf of runoff into this pond. Based on review of the previous
design report there is approximately 1,644 cf of excess capacity in the 26,000 cf existing
retention pond. A small portion of South 11th will drain into the detention pond located in the
Alder Creek Phase 3 park. It is expected to generate and additional 255 cf of runoff to the
detention pond. There are 322 cf of excess capacity in the 4,175 cf existing detention pond. As
such, it is anticipated that the facilities in the Alder Creek Subdivision have sufficient capacity to
handle the small amount of excess runoff from the proposed development.
GROUNDWATER CONSIDERATIONS
Groundwater monitoring wells were installed across the subject property in 2019 and were
monitored throughout the spring/summer of 2019 and spring of 2020. The results generally
showed that seasonal high groundwater (SHGW) peaked in early April, and ranged from 7” to
3.5’ below existing grade. This information was used to generate a SHGW elevation surface in
AutoCAD to reference during the stormwater design for the subdivision. Additional
measurements along the northern property boundary were taken in the spring of 2021 to refine
the SHGW surface in that area. All proposed ponds in the development are set with the bottom of
pond elevation above the SHGW elevation in the pond footprint. The Phase 1 pond elevations
and approximate SHGW elevations are listed in Table 3 below. The groundwater monitoring
results can be found in Appendix D.
BLACKWOOD GROVES SUBDIVISION – STORMWATER DESIGN REPORT
July 29, 2021
#190390 9
Table 3: SHGW and Proposed Pond Elevations
Pond Storage type
Approximate Existing Surface Elevation (ft)
Estimated Peak Groundwater Elevation (ft. bgs)
Estimated Peak Groundwater Elevation (ft.)
Proposed Pond Top Elevation (ft)
Proposed Pond Bottom Elevation (ft.)
5 Retention 5005.4 2.91 5002.50 5005.00 5003.50
6 Detention 5000.6 4.16 5000.26 5002.05 5000.55
7 Detention 4997.2 1.95 4995.29 4997.00 4995.50
8A Detention 4999.3 1.15 4998.15 4999.75 4998.25
8B Detention 4999.3 1.15 4998.15 4999.75 4998.25
8C Detention 5000.8 1.67 4999.13 5000.65 4999.15
9 Detention 5000.9 1.42 4999.48 5001.21 4999.71
A Retention 5000.5 1.42 4999.08 5001.00 4999.50
APPENDIX A
Drainage Area Maps
APPENDIX B
Pre-Development Drainage Area Calculations
DA - EX 1
REQUIRED VOLUME
1. Calculate Area and Weighted C Factor (Post-Development)
Contributing Area DA C Area (ft2 )C * Area
Open Land EX 1 0.20 339691 67938
Total 339691 67938
A = Area (acres)7.80 Storm
C = Weighted C Factor 0.20 Return (yrs)Cf
2 to 10 1
2. Calculate T c (Pre-Development)11 to 25 1.1
Tc Overland Flow 26 to 50 1.2
Tc = 1.87 (1.1-CCf)D1/2/S1/3 51 to 100 1.25
S = Slope of Basin (%)1.460
C = Rational Method Runoff Coefficient 0.2
Cf = Frequency Adjustment Factor 1
D = Length of Basin (ft)1773
Tc (Pre-Development) (minutes)62
3. Calculate Rainfall Intensity (Duration = Pre-Development Tc)
i = 0.64x-0.65 (10-yr Storm, Fig. I-3, COB Design Standards)
x = storm duration (hrs)1.04 (Tc Pre-Development)
i = rainfall intensity (in./hr.)0.62
4. Calculate Runoff Rate (Pre-Development)
Q = CiA
C = Rational Method Runoff Coefficient 0.2 (open land)
i = rainfall intensity (in./hr.)0.62 (calculated above)
A = Area (acres)7.80 (calculated above)
Q = Runoff Rate (Pre-Development) (cfs)0.97
DA - EX 2
REQUIRED VOLUME
1. Calculate Area and Weighted C Factor (Post-Development)
Contributing Area DA C Area (ft2 )C * Area
Open Land EX 2 0.20 4033738 806748
Total 4033738 806748
A = Area (acres)92.60 Storm
C = Weighted C Factor 0.20 Return (yrs)Cf
2 to 10 1
2. Calculate T c (Pre-Development)11 to 25 1.1
Tc Overland Flow 26 to 50 1.2
Tc = 1.87 (1.1-CCf)D1/2/S1/3 51 to 100 1.25
S = Slope of Basin (%)1.490
C = Rational Method Runoff Coefficient 0.2
Cf = Frequency Adjustment Factor 1
D = Length of Basin (ft)4250
Tc (Pre-Development) (minutes)96
3. Calculate Rainfall Intensity (Duration = Pre-Development Tc)
i = 0.64x-0.65 (10-yr Storm, Fig. I-3, COB Design Standards)
x = storm duration (hrs)1.60 (Tc Pre-Development)
i = rainfall intensity (in./hr.)0.47
4. Calculate Runoff Rate (Pre-Development)
Q = CiA
C = Rational Method Runoff Coefficient 0.2 (open land)
i = rainfall intensity (in./hr.)0.47 (calculated above)
A = Area (acres)92.60 (calculated above)
Q = Runoff Rate (Pre-Development) (cfs)8.73
DA - EX 3
REQUIRED VOLUME
1. Calculate Area and Weighted C Factor (Post-Development)
Contributing Area DA C Area (ft2 )C * Area
Open Land EX 3 0.20 238679 47736
Total 238679 47736
A = Area (acres)5.48 Storm
C = Weighted C Factor 0.20 Return (yrs)Cf
2 to 10 1
2. Calculate T c (Pre-Development)11 to 25 1.1
Tc Overland Flow 26 to 50 1.2
Tc = 1.87 (1.1-CCf)D1/2/S1/3 51 to 100 1.25
S = Slope of Basin (%)1.820
C = Rational Method Runoff Coefficient 0.2
Cf = Frequency Adjustment Factor 1
D = Length of Basin (ft)606
Tc (Pre-Development) (minutes)34
3. Calculate Rainfall Intensity (Duration = Pre-Development Tc)
i = 0.64x-0.65 (10-yr Storm, Fig. I-3, COB Design Standards)
x = storm duration (hrs)0.57 (Tc Pre-Development)
i = rainfall intensity (in./hr.)0.93
4. Calculate Runoff Rate (Pre-Development)
Q = CiA
C = Rational Method Runoff Coefficient 0.2 (open land)
i = rainfall intensity (in./hr.)0.93 (calculated above)
A = Area (acres)5.48 (calculated above)
Q = Runoff Rate (Pre-Development) (cfs)1.02
DA - EX 4
REQUIRED VOLUME
1. Calculate Area and Weighted C Factor (Post-Development)
Contributing Area DA C Area (ft2 )C * Area
Open Land EX 4 0.20 1709509 341902
Total 1709509 341902
A = Area (acres)39.24 Storm
C = Weighted C Factor 0.20 Return (yrs)Cf
2 to 10 1
2. Calculate T c (Pre-Development)11 to 25 1.1
Tc Overland Flow 26 to 50 1.2
Tc = 1.87 (1.1-CCf)D1/2/S1/3 51 to 100 1.25
S = Slope of Basin (%)1.590
C = Rational Method Runoff Coefficient 0.2
Cf = Frequency Adjustment Factor 1
D = Length of Basin (ft)2345
Tc (Pre-Development) (minutes)70
3. Calculate Rainfall Intensity (Duration = Pre-Development Tc)
i = 0.64x-0.65 (10-yr Storm, Fig. I-3, COB Design Standards)
x = storm duration (hrs)1.16 (Tc Pre-Development)
i = rainfall intensity (in./hr.)0.58
4. Calculate Runoff Rate (Pre-Development)
Q = CiA
C = Rational Method Runoff Coefficient 0.2 (open land)
i = rainfall intensity (in./hr.)0.58 (calculated above)
A = Area (acres)39.24 (calculated above)
Q = Runoff Rate (Pre-Development) (cfs)4.55
APPENDIX C
Post Development Drainage Area Calculations
DRAINAGE AREA # 9A
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Local 0.76 14613 11106
Residential - Dense 0.75 88780 66585
Total 103393 77691
A = Area (acres)2.37
C = Weighted C Factor 0.75
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)1.00 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.75 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)380 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)10.02
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0144
L = length of gutter (ft)279
V = mean velocity (ft/s)3.60
Tc Gutter Flow (minutes) =1.29
Tc Total =11.32
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.75 (calculated above)
I = 0.78 Tc-0.64 (in/hr)2.27 (25-yr storm)
A = area (acres)2.37 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)4.05 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 0.15' Below Top of Curb
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0144
Q = PROVIDED GUTTER CAPACITY (cfs)4.46
REQ'D PIPE CAPACITY
DA 9A 3.13 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:Pipe 9A Project:Blackwood Groves Phase 1
INPUT
D= 12 inches
d= 11.26 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.005 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2 Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
0.77 2.64 0.29 5.12 3.91 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 9B
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Local 0.76 31547 23976
Residential - Dense 0.60 114817 68890
Park 0.20 20901 4180
Total 167265 97046
A = Area (acres)3.84
C = Weighted C Factor 0.58
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)0.75 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.60 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)486 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)19.96
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0083
L = length of gutter (ft)245
V = mean velocity (ft/s)2.37
Tc Gutter Flow (minutes) =1.72
Tc Total =21.69
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.58 (calculated above)
I = 0.78 Tc-0.64 (in/hr)1.50 (25-yr storm)
A = area (acres)3.84 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)3.33 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 0.15' Below Top of Curb
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0083
Q = PROVIDED GUTTER CAPACITY (cfs)3.39
REQ'D PIPE CAPACITY
DA 9B+Pipe 9C 7.69 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:Pipe 9B Project:Blackwood Groves Phase 1
INPUT
D= 15 inches
d= 14.07 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.0102 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2
Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
1.20 3.30 0.36 8.48 10.14 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 9B2
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Local 0.76 15281 11614
Residential - Dense 0.60 38754 23252
Total 54035 34866
A = Area (acres)1.24
C = Weighted C Factor 0.65
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)0.75 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.60 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)135 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)10.52
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0155
L = length of gutter (ft)370
V = mean velocity (ft/s)3.24
Tc Gutter Flow (minutes) =1.91
Tc Total =12.43
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.65 (calculated above)
I = 0.78 Tc-0.64 (in/hr)2.14 (25-yr storm)
A = area (acres)1.24 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)1.71 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 0.15' Below Top of Curb
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0083
Q = PROVIDED GUTTER CAPACITY (cfs)3.39
REQ'D PIPE CAPACITY
DA 9B2 1.71 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:Pipe 9B2 Project:Blackwood Groves Phase 1
INPUT
D= 15 inches
d= 14.07 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.0265 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2
Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
1.20 3.30 0.36 13.67 16.34 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 9C
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Local 0.76 22307 16953
Commercial 0.95 26505 25180
Residential - Dense 0.75 45055 33791
Total 93867 75924
A = Area (acres)2.15
C = Weighted C Factor 0.81
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)1.00 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.75 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)304 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)8.97
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0144
L = length of gutter (ft)165
V = mean velocity (ft/s)2.92
Tc Gutter Flow (minutes) =0.94
Tc Total =9.91
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.81 (calculated above)
I = 0.78 Tc-0.64 (in/hr)2.47 (25-yr storm)
A = area (acres)2.15 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)4.31 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 0.15' Below Top of Curb
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0144
Q = PROVIDED GUTTER CAPACITY (cfs)5.80
REQ'D PIPE CAPACITY
DA 9C 4.31 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:Pipe 9C Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 12 inches
d= 11.26 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.006 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2
Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
0.77 2.64 0.29 5.67 4.34 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 9D
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
Residential - Dense 0.40 11619 4647
OS 0.20 3357 671
ROW - Local 0.76 12697 9649
Total 27672 14968
A = Area (acres)0.64
C = Weighted C Factor 0.54
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)1.50 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.40 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)108 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)11.20
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0075
L = length of gutter (ft)157
V = mean velocity (ft/s)2.60
Tc Gutter Flow (minutes) =1.01
Tc Total =12.21
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.54 (calculated above)
I = 0.78 Tc-0.64 (in/hr)2.16 (25-yr storm)
A = area (acres)0.64 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)0.74 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 0.15' Below Top of Curb
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0075
Q = PROVIDED GUTTER CAPACITY (cfs)3.22
REQ'D PIPE CAPACITY
Pipe 9B + DA 9D 9.67 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:Pipe 9D Project:Blackwood Groves Phase 1
INPUT
D= 18 inches
d= 16.88 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.0081 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2
Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
1.72 3.96 0.44 8.53 14.69 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
REQ'D PIPE CAPACITY
Pipe 9D + Pipe 9I + Pipe 9A 16.92 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe: Pipe 9D2 Project: Blackwood Groves Phase 1
INPUT
D=21 inches
d= 19.70 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.0055 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2 Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
2.34 4.62 0.51 7.79 18.26 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 9E
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Local 0.76 21527 16360
Residential - Dense 0.75 102610 76958
Total 124137 93318
A = Area (acres)2.85
C = Weighted C Factor 0.75
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)1.00 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.75 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)480 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)12.17
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0152
L = length of gutter (ft)70
V = mean velocity (ft/s)3.70
Tc Gutter Flow (minutes) =0.32
Tc Total =12.48
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.75 (calculated above)
I = 0.78 Tc-0.64 (in/hr)2.13 (25-yr storm)
A = area (acres)2.85 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)4.56 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 0.15' Below Top of Curb
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0152
Q = PROVIDED GUTTER CAPACITY (cfs)4.58
REQ'D PIPE CAPACITY
Pipe 9D2 + Pipe 9G + DA 9E 25.61 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:Pipe 9E Project:Blackwood Groves Phase 1
INPUT
D= 21 inches
d= 19.70 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.0112 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2
Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
2.34 4.62 0.51 11.12 26.05 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 9F
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Local 0.76 7859 5973
Total 7859 5973
A = Area (acres)0.18
C = Weighted C Factor 0.76
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)2.00 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.50 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)15 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)3.16
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0126
L = length of gutter (ft)207
V = mean velocity (ft/s)3.37
Tc Gutter Flow (minutes) =1.03
Tc Total =4.19
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.76 (calculated above)
I = 0.78 Tc-0.64 (in/hr)4.29 (25-yr storm)
A = area (acres)0.18 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)0.59 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 0.15' Below Top of Curb
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0126
Q = PROVIDED GUTTER CAPACITY (cfs)4.17
REQ'D PIPE CAPACITY
Pipe 9E + DA 9F 26.20 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:Pipe 9F Project:Blackwood Groves Phase 1
INPUT
D= 24 inches
d= 22.51 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.006 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2 Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
3.06 5.28 0.58 8.90 27.23 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 9G
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Local 0.76 9046 6875
Park 0.20 4251 850
OS 0.20 13120 2624
Residential - Dense 0.60 35478 21287
Total 61894 31636
A = Area (acres)1.42
C = Weighted C Factor 0.51
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)1.00 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.60 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)270 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)13.52
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0152
L = length of gutter (ft)176
V = mean velocity (ft/s)3.70
Tc Gutter Flow (minutes) =0.79
Tc Total =14.31
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.51 (calculated above)
I = 0.78 Tc-0.64 (in/hr)1.95 (25-yr storm)
A = area (acres)1.42 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)1.42 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 0.15' Below Top of Curb
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0152
Q = PROVIDED GUTTER CAPACITY (cfs)4.58
REQ'D PIPE CAPACITY
DA 9G 6.25 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:Pipe 9G Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 12 inches
d= 11.26 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.0183 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2
Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
0.77 2.64 0.29 9.79 7.49 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 9H
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Local 0.76 17977 13662
Residential - Low-Med 0.35 20009 7003
Total 37985 20665
A = Area (acres)0.87
C = Weighted C Factor 0.54
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)2.00 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.35 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)97 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)10.45
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0180
L = length of gutter (ft)272
V = mean velocity (ft/s)4.02
Tc Gutter Flow (minutes) =1.13
Tc Total =11.58
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.54 (calculated above)
I = 0.78 Tc-0.64 (in/hr)2.24 (25-yr storm)
A = area (acres)0.87 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)1.06 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 0.15' Below Top of Curb
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0180
Q = PROVIDED GUTTER CAPACITY (cfs)4.99
REQ'D PIPE CAPACITY
DA 9H 1.06 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:Pipe 9H Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 12 inches
d= 11.26 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.0038 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2
Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
0.77 2.64 0.29 4.46 3.41 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 9I
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Local 0.76 11917 9057
Residential - Dense 0.75 41833 31375
Total 53749 40431
A = Area (acres)1.23
C = Weighted C Factor 0.75
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)1.50 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.50 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)41 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)5.75
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0050
L = length of gutter (ft)963
V = mean velocity (ft/s)2.12
Tc Gutter Flow (minutes) =7.57
Tc Total =13.32
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.75 (calculated above)
I = 0.78 Tc-0.64 (in/hr)2.04 (25-yr storm)
A = area (acres)1.23 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)1.90 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 0.15' Below Top of Curb
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0050
Q = PROVIDED GUTTER CAPACITY (cfs)2.63
REQ'D PIPE CAPACITY
DA 9I 1.90 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:Pipe 9I Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 12 inches
d= 11.26 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.005 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2 Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
0.77 2.64 0.29 5.12 3.91 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 9J
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Collector 0.70 41138 28797
Total 41138 28797
A = Area (acres)0.94
C = Weighted C Factor 0.70
2. Assume min. Tc (will be designed in Phase 2)
Tc Total =5.00
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.70 (calculated above)
I = 0.78 Tc-0.64 (in/hr)3.83 (25-yr storm)
A = area (acres)0.94 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)2.53 (assuming no carry flow)
DRAINAGE AREA # 9K
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Local 0.76 5714 4343
Residential - Low-Med 0.35 12487 4370
Total 18201 8713
A = Area (acres)0.42
C = Weighted C Factor 0.48
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)1.50 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.35 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)125 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)13.06
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0060
L = length of gutter (ft)90
V = mean velocity (ft/s)2.32
Tc Gutter Flow (minutes) =0.65
Tc Total =13.70
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.48 (calculated above)
I = 0.78 Tc-0.64 (in/hr)2.01 (25-yr storm)
A = area (acres)0.42 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)0.40 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 0.15' Below Top of Curb
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0060
Q = PROVIDED GUTTER CAPACITY (cfs)2.88
REQ'D PIPE CAPACITY
DA 9K + Pipe 9H 1.46 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:Pipe 9k Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 12 inches
d= 11.26 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.005 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2 Wetted Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
0.77 2.64 0.29 5.12 3.91 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 9L
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
Residential - Dense 0.75 103406 77554
OS 0.20 50963 10193
Total 154369 87747
A = Area (acres)3.54
C = Weighted C Factor 0.57
2. Assume min. Tc (will be designed during site plan review)
Tc Total =5.00
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.57 (calculated above)
I = 0.78 Tc-0.64 (in/hr)3.83 (25-yr storm)
A = area (acres)3.54 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)7.71 (assuming no carry flow)
DRAINAGE AREA # 8A
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Local 0.76 36398 27663
ROW - Angled 0.93 20802 19346
Commercial 0.95 43975 41776
Park 0.20 12172 2434
OS 0.20 13111 2622
Residential - Dense 0.40 99407 39763
Total 225866 133604
A = Area (acres)5.19
C = Weighted C Factor 0.59
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)1.00 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.40 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)360 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)23.42
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0160
L = length of gutter (ft)535
V = mean velocity (ft/s)3.79
Tc Gutter Flow (minutes) =2.35
Tc Total =25.77
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.59 (calculated above)
I = 0.78 Tc-0.64 (in/hr)1.34 (25-yr storm)
A = area (acres)5.19 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)4.11 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 0.15' Below Top of Curb
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0160
Q = PROVIDED GUTTER CAPACITY (cfs)4.70
REQ'D PIPE CAPACITY
DA 8A 4.11 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:Pipe 8A Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 12 inches
d= 11.26 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.0096 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2 Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
0.77 2.64 0.29 7.09 5.42 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 8B
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Local 0.76 8489 6452
ROW - Angled 0.93 31758 29535
Total 40247 35987
A = Area (acres)0.92
C = Weighted C Factor 0.89
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)1.50 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.50 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)23 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)4.31
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0165
L = length of gutter (ft)985
V = mean velocity (ft/s)3.85
Tc Gutter Flow (minutes) =4.26
Tc Total =8.57
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.89 (calculated above)
I = 0.78 Tc-0.64 (in/hr)2.71 (25-yr storm)
A = area (acres)0.92 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)2.24 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 0.15' Below Top of Curb
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0165
Q = PROVIDED GUTTER CAPACITY (cfs)4.78
REQ'D PIPE CAPACITY
DA 8B + Pipe 8B3 + 8B2 9.24 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:Pipe 8B Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 15 inches
d= 14.07 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.0085 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2 Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
1.20 3.30 0.36 7.74 9.25 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 8B2
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
Commercial 0.95 81017 76966
Total 81017 76966
A = Area (acres)1.86
C = Weighted C Factor 0.95
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)0.50 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.95 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)595 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)5.75
Tc Total = (5 min Minimum )5.75
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.95 (calculated above)
I = 0.78 Tc-0.64 (in/hr)3.50 (25-yr storm)
A = area (acres)1.86 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)6.18 (assuming no carry flow)
REQ'D PIPE CAPACITY
DA 8B2 6.18 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:Pipe 8B2 Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 15 inches
d= 14.07 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.0055 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2 Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
1.20 3.30 0.36 6.23 7.44 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 8B3
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
Residential - Dense 0.40 59972 23989
Total 59972 23989
A = Area (acres)1.38
C = Weighted C Factor 0.40
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)1.00 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.40 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)313 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)21.84
Tc Total =21.84
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.40 (calculated above)
I = 0.78 Tc-0.64 (in/hr)1.49 (25-yr storm)
A = area (acres)1.38 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)0.82 (assuming no carry flow)
REQ'D PIPE CAPACITY
DA 8B3 0.82 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:Pipe 8B3 Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 15 inches
d= 14.07 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.0055 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2 Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
1.20 3.30 0.36 6.23 7.44 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 8C
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Local 0.76 11853 9008
Residential - Low-Med 0.35 25880 9058
Total 37733 18066
A = Area (acres)0.87
C = Weighted C Factor 0.48
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)1.50 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.35 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)114 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)12.47
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0053
L = length of gutter (ft)310
V = mean velocity (ft/s)2.18
Tc Gutter Flow (minutes) =2.37
Tc Total =14.84
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.48 (calculated above)
I = 0.78 Tc-0.64 (in/hr)1.91 (25-yr storm)
A = area (acres)0.87 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)0.79 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 0.15' Below Top of Curb
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0053
Q = PROVIDED GUTTER CAPACITY (cfs)2.71
REQ'D PIPE CAPACITY
PIPE 8A + DA 8C 4.90 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:Pipe 8C Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 15 inches
d= 14.07 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.005 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2
Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
1.20 3.30 0.36 5.94 7.10 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 8D
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Local 0.76 28957 22007
ROW - Alley 0.80 10487 8390
Park 0.20 19843 3969
Residential - Low-Med 0.35 104870 36704
Total 164156 71070
A = Area (acres)3.77
C = Weighted C Factor 0.43
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)1.00 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.35 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)118 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)14.52
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0050
L = length of gutter (ft)615
V = mean velocity (ft/s)2.12
Tc Gutter Flow (minutes) =4.83
Tc Total =19.36
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.43 (calculated above)
I = 0.78 Tc-0.64 (in/hr)1.61 (25-yr storm)
A = area (acres)3.77 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)2.62 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 0.15' Below Top of Curb
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0050
Q = PROVIDED GUTTER CAPACITY (cfs)2.63
REQ'D PIPE CAPACITY
DA 8D 2.62 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:Pipe 8D Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 12 inches
d= 11.26 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.005 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation Manning's n-values
Area,ft2 Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
0.77 2.64 0.29 5.12 3.91 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
d
q
D
REQ'D PIPE CAPACITY
PIPE 8B + Pipe 8D 11.87 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:Pipe 8D2 Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 18 inches
d= 16.88 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.006 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation Manning's n-values
Area,ft2
Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
1.72 3.96 0.44 7.34 12.64 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
d
q
D
DRAINAGE AREA # 8E
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Local 0.76 12430 9447
Residential - Low-Med 0.35 22158 7755
Total 34588 17202
A = Area (acres)0.79
C = Weighted C Factor 0.50
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)1.50 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.35 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)116 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)12.58
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0087
L = length of gutter (ft)141
V = mean velocity (ft/s)2.80
Tc Gutter Flow (minutes) =0.84
Tc Total =13.42
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.50 (calculated above)
I = 0.78 Tc-0.64 (in/hr)2.03 (25-yr storm)
A = area (acres)0.79 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)0.80 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 0.15' Below Top of Curb
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0087
Q = PROVIDED GUTTER CAPACITY (cfs)3.47
REQ'D PIPE CAPACITY
PIPE 8C + DA 8E 5.70 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:Pipe 8E Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 15 inches
d= 14.07 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.005 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2 Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
1.20 3.30 0.36 5.94 7.10 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 8F
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Local 0.76 6521 4956
Residential - Low-Med 0.35 19747 6911
Total 26268 11867
A = Area (acres)0.60
C = Weighted C Factor 0.45
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)1.50 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.35 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)131 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)13.37
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0094
L = length of gutter (ft)154
V = mean velocity (ft/s)2.91
Tc Gutter Flow (minutes) =0.88
Tc Total =14.25
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.45 (calculated above)
I = 0.78 Tc-0.64 (in/hr)1.96 (25-yr storm)
A = area (acres)0.60 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)0.53 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 0.15' Below Top of Curb
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0094
Q = PROVIDED GUTTER CAPACITY (cfs)3.60
REQ'D PIPE CAPACITY
PIPE 8E + DA 8F 6.24 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:Pipe 8F Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 15 inches
d= 14.07 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.005 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2 Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
1.20 3.30 0.36 5.94 7.10 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 8G
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Local 0.76 16169 12288
Residential - Low-Med 0.35 48000 16800
Total 64169 29088
A = Area (acres)1.47
C = Weighted C Factor 0.45
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)1.00 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.35 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)133 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)15.42
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0050
L = length of gutter (ft)422
V = mean velocity (ft/s)2.12
Tc Gutter Flow (minutes) =3.32
Tc Total =18.74
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.45 (calculated above)
I = 0.78 Tc-0.64 (in/hr)1.64 (25-yr storm)
A = area (acres)1.47 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)1.10 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 0.15' Below Top of Curb
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0050
Q = PROVIDED GUTTER CAPACITY (cfs)2.63
REQ'D PIPE CAPACITY
PIPE 8D + DA 8G 12.97 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:Pipe 8G Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 18 inches
d= 16.88 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.007 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2 Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
1.72 3.96 0.44 7.93 13.66 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 8H
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Local 0.76 2300 1748
OS 0.20 4500 900
Total 6800 1748
A = Area (acres)0.16
C = Weighted C Factor 0.26
Tc Total =5.00
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.26 (calculated above)
I = 0.78 Tc-0.64 (in/hr)3.83 (25-yr storm)
A = area (acres)0.16 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)0.15 (assuming no carry flow)
DRAINAGE AREA # 8I
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Local 0.76 2548 1937
OS 0.20 4435 887
Total 6983 2824
A = Area (acres)0.16
C = Weighted C Factor 0.40
Tc Total =5.00
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.40 (calculated above)
I = 0.78 Tc-0.64 (in/hr)3.83 (25-yr storm)
A = area (acres)0.16 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)0.25 (assuming no carry flow)
DRAINAGE AREA # 8J
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Local 0.76 16953 12885
Park 0.20 16304 3261
Residential - Dense 0.40 23902 9561
Total 57159 25706
A = Area (acres)1.31
C = Weighted C Factor 0.45
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)1.00 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.40 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)206 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)17.71
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0165
L = length of gutter (ft)206
V = mean velocity (ft/s)3.85
Tc Gutter Flow (minutes) =0.89
Tc Total =18.61
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.45 (calculated above)
I = 0.78 Tc-0.64 (in/hr)1.65 (25-yr storm)
A = area (acres)1.31 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)0.97 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 0.15' Below Top of Curb
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0165
Q = PROVIDED GUTTER CAPACITY (cfs)4.78
REQ'D PIPE CAPACITY
DA 8J 0.97 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:Pipe 8J Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 12 inches
d= 11.26 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.005 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2 Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
0.77 2.64 0.29 5.12 3.91 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 8K
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Local 0.76 8897 6762
Residential - Low-Med 0.35 15988 5596
Total 24885 12358
A = Area (acres)0.57
C = Weighted C Factor 0.50
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)1.00 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.35 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)105 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)13.70
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0100
L = length of gutter (ft)204
V = mean velocity (ft/s)3.00
Tc Gutter Flow (minutes) =1.13
Tc Total =14.83
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.50 (calculated above)
I = 0.78 Tc-0.64 (in/hr)1.91 (25-yr storm)
A = area (acres)0.57 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)0.54 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 0.15' Below Top of Curb
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0100
Q = PROVIDED GUTTER CAPACITY (cfs)3.72
REQ'D PIPE CAPACITY
Pipe 8J + DA 8K 1.52 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:Pipe 8K Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 15 inches
d= 14.07 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.004 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2 Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
1.20 3.30 0.36 5.31 6.35 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 8L
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Local 0.76 34076 25898
Park 0.20 4800 960
Residential - Dense 0.40 35468 14187
OS 0.20 3410 682
Total 77755 41727
A = Area (acres)1.79
C = Weighted C Factor 0.54
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)1.00 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.40 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)174 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)16.28
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0130
L = length of gutter (ft)519
V = mean velocity (ft/s)3.42
Tc Gutter Flow (minutes) =2.53
Tc Total =18.81
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.54 (calculated above)
I = 0.78 Tc-0.64 (in/hr)1.64 (25-yr storm)
A = area (acres)1.79 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)1.57 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 0.15' Below Top of Curb
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0130
Q = PROVIDED GUTTER CAPACITY (cfs)4.24
REQ'D PIPE CAPACITY
DA 8L 1.57 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:Pipe 8L Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 15 inches
d= 14.07 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.005 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2 Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
1.20 3.30 0.36 5.94 7.10 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
REQ'D PIPE CAPACITY
Pipe 8L + Pipe 8K + Pipe 8N 3.36 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:Pipe 8L2 Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 15 inches
d= 14.07 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.004 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2 Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
1.20 3.30 0.36 5.31 6.35 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 8M
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Local 0.76 13224 10051
Residential - Low-Med 0.35 38062 13322
Total 51286 23372
A = Area (acres)1.18
C = Weighted C Factor 0.46
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)1.00 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.35 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)124 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)14.89
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0050
L = length of gutter (ft)222
V = mean velocity (ft/s)2.12
Tc Gutter Flow (minutes) =1.75
Tc Total =16.63
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.46 (calculated above)
I = 0.78 Tc-0.64 (in/hr)1.77 (25-yr storm)
A = area (acres)1.18 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)0.95 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 0.15' Below Top of Curb
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0050
Q = PROVIDED GUTTER CAPACITY (cfs)2.63
REQ'D PIPE CAPACITY
Pipe 8L2 + DA 8M 4.31 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:Pipe 8M Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 15 inches
d= 14.07 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.005 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2 Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
1.20 3.30 0.36 5.94 7.10 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 8N
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Local 0.76 3580 2721
Residential - Low-Med 0.35 9242 3235
Total 12822 5955
A = Area (acres)0.29
C = Weighted C Factor 0.46
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)1.00 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.35 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)101 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)13.44
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0050
L = length of gutter (ft)45
V = mean velocity (ft/s)2.12
Tc Gutter Flow (minutes) =0.35
Tc Total =13.79
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.46 (calculated above)
I = 0.78 Tc-0.64 (in/hr)2.00 (25-yr storm)
A = area (acres)0.29 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)0.27 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 0.15' Below Top of Curb
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0050
Q = PROVIDED GUTTER CAPACITY (cfs)2.63
REQ'D PIPE CAPACITY
DA 8N 0.27 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:Pipe 8N Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 12 inches
d= 11.26 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.005 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2 Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
0.77 2.64 0.29 5.12 3.91 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 6A
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Alley 0.80 17950 14360
OS 0.20 2253 451
Residential - Dense 0.75 96773 72580
Total 116975 87390
A = Area (acres)2.69
C = Weighted C Factor 0.75
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)2.00 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.75 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)144 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)4.90
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0175
L = length of gutter (ft)478
V = mean velocity (ft/s)3.97
Tc Gutter Flow (minutes) =2.01
Tc Total =6.91
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.75 (calculated above)
I = 0.78 Tc-0.64 (in/hr)3.11 (25-yr storm)
A = area (acres)2.69 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)6.24 (assuming no carry flow)
DRAINAGE AREA # 6B
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Collector 0.70 28881 20216
ROW - Angled 0.93 6517 6061
Total 35398 26277
A = Area (acres)0.81
C = Weighted C Factor 0.74
2. Calculate Tc (Time to Concentration)
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0134
L = length of gutter (ft)828
V = mean velocity (ft/s)3.47
Tc Gutter Flow (minutes) =3.98
Tc Total =3.98
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.74 (calculated above)
I = 0.78 Tc-0.64 (in/hr)4.43 (25-yr storm)
A = area (acres)0.81 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)2.67 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 9 feet into Drive Aisle
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0134
Q = PROVIDED GUTTER CAPACITY (cfs)4.30
REQ'D PIPE CAPACITY
DA 6B 2.67 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:PIPE 6B Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 12 inches
d= 11.26 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.006 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2 Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
0.77 2.64 0.29 5.60 4.29 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 6C
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
OS 0.20 8017 1603
Total 8017 1603
A = Area (acres)0.18
C = Weighted C Factor 0.20
2. Calculate Tc (Time to Concentration)
Tc Total =5.00
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.20 (calculated above)
I = 0.78 Tc-0.64 (in/hr)3.83 (25-yr storm)
A = area (acres)0.18 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)0.14 (assuming no carry flow)
DRAINAGE AREA # 7A
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Collector 0.70 49013 34309
ROW - Angled 0.93 6218 5783
Commercial 0.95 131497 124922
Total 186728 165014
A = Area (acres)4.29
C = Weighted C Factor 0.88
2. Assume min. Tc (will be designed in Phase 3)
Tc Total =5.00
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.88 (calculated above)
I = 0.78 Tc-0.64 (in/hr)3.83 (25-yr storm)
A = area (acres)4.29 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)14.49 (assuming no carry flow)
DRAINAGE AREA # 7B
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Collector 0.70 3550 2485
ROW - Local 0.76 16101 12237
Residential - Dense 0.75 37248 28048
Total 56899 42769
A = Area (acres)1.31
C = Weighted C Factor 0.75
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)1.50 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.75 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)125 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)5.02
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0074
L = length of gutter (ft)379
V = mean velocity (ft/s)2.58
Tc Gutter Flow (minutes) =2.45
Tc Total =7.47
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.75 (calculated above)
I = 0.78 Tc-0.64 (in/hr)2.96 (25-yr storm)
A = area (acres)1.31 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)2.91 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 9 feet into Drive Aisle
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0074
Q = PROVIDED GUTTER CAPACITY (cfs)3.20
REQ'D PIPE CAPACITY
DA 7B 2.91 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:PIPE 7B Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 12 inches
d= 11.26 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.02 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2
Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
0.77 2.64 0.29 10.23 7.83 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 7C
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Collector 0.70 16245 11372
ROW - Local 0.76 13401 10185
Residential - Low-Med 0.35 62558 21895
Total 92204 21556
A = Area (acres)2.12
C = Weighted C Factor 0.23
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)2.00 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.35 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)123 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)11.77
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0120
L = length of gutter (ft)499
V = mean velocity (ft/s)3.28
Tc Gutter Flow (minutes) =2.53
Tc Total =14.30
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.23 (calculated above)
I = 0.78 Tc-0.64 (in/hr)1.95 (25-yr storm)
A = area (acres)2.12 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)0.97 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 9 feet into Drive Aisle
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0120
Q = PROVIDED GUTTER CAPACITY (cfs)4.07
REQ'D PIPE CAPACITY
DA 7C 0.97 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:PIPE 7C Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 12 inches
d= 11.26 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.003 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2
Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
0.77 2.64 0.29 3.96 3.03 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 7D
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Collector 0.70 84687 59281
Total 84687 59281
A = Area (acres)1.94
C = Weighted C Factor 0.70
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)2.00 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.50 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)37 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)4.97
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0150
L = length of gutter (ft)597
V = mean velocity (ft/s)3.67
Tc Gutter Flow (minutes) =2.71
Tc Total =7.67
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.70 (calculated above)
I = 0.78 Tc-0.64 (in/hr)2.91 (25-yr storm)
A = area (acres)1.94 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)3.96 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 9 feet into Drive Aisle
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0150
Q = PROVIDED GUTTER CAPACITY (cfs)4.55
REQ'D PIPE CAPACITY
DA 7D + DA 7A 18.45 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:PIPE 7D Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 21 inches
d= 19.70 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.006 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2 Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
2.34 4.62 0.51 8.14 19.07 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 7E
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Collector 0.70 6785 4750
ROW - Local 0.76 4125 3135
Total 10911 7885
A = Area (acres)0.25
C = Weighted C Factor 0.72
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)2.00 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.50 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)48 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)5.66
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0170
L = length of gutter (ft)182
V = mean velocity (ft/s)3.91
Tc Gutter Flow (minutes) =0.78
Tc Total =6.43
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.72 (calculated above)
I = 0.78 Tc-0.64 (in/hr)3.26 (25-yr storm)
A = area (acres)0.25 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)0.59 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 9 feet into Drive Aisle
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0170
Q = PROVIDED GUTTER CAPACITY (cfs)4.85
REQ'D PIPE CAPACITY
DA 7E 0.59 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:PIPE 7E Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 12 inches
d= 11.26 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.005 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2
Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
0.77 2.64 0.29 5.12 3.91 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 7F
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Collector 0.70 1075 753
ROW - Local 0.76 3465 2634
Total 4541 3386
A = Area (acres)0.10
C = Weighted C Factor 0.75
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)2.00 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.50 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)20 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)3.65
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0040
L = length of gutter (ft)53
V = mean velocity (ft/s)1.90
Tc Gutter Flow (minutes) =0.47
Tc Total =4.12
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.75 (calculated above)
I = 0.78 Tc-0.64 (in/hr)4.33 (25-yr storm)
A = area (acres)0.10 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)0.34 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 9 feet into Drive Aisle
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0040
Q = PROVIDED GUTTER CAPACITY (cfs)2.35
REQ'D PIPE CAPACITY
PIPE 7E + DA 7F 0.93 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:PIPE 7F Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 12 inches
d= 11.26 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.005 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2
Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
0.77 2.64 0.29 5.12 3.91 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
REQ'D PIPE CAPACITY
PIPE 7B + PIPE 7F + PIPE 7D 22.28 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:PIPE 7F2 Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 21 inches
d= 19.70 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.0086 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2
Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
2.34 4.62 0.51 9.74 22.83 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 7G
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Collector 0.70 14593 10215
Total 14593 10215
A = Area (acres)0.34
C = Weighted C Factor 0.70
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)2.00 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.50 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)22 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)3.83
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0135
L = length of gutter (ft)182
V = mean velocity (ft/s)3.48
Tc Gutter Flow (minutes) =0.87
Tc Total =4.70
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.70 (calculated above)
I = 0.78 Tc-0.64 (in/hr)3.98 (25-yr storm)
A = area (acres)0.34 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)0.93 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 9 feet into Drive Aisle
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0135
Q = PROVIDED GUTTER CAPACITY (cfs)4.32
REQ'D PIPE CAPACITY
DA 7G 0.93 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:PIPE 7G Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 12 inches
d= 11.26 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.0032 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2 Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
0.77 2.64 0.29 4.09 3.13 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
REQ'D PIPE CAPACITY
PIPE 7F2 + PIPE 7G + PIPE 7C 24.18 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe: PIPE 7G2 Project: Blackwood Groves Subdivision Phase 1
INPUT
D=21 inches
d= 19.70 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.01 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2 Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
2.34 4.62 0.51 10.51 24.62 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 7H
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
PARK 0.20 21814 4363
ROW - Collector 0.70 5189 3633
Total 27003 7995
A = Area (acres)0.62
C = Weighted C Factor 0.30
2. Calculate Tc (Time to Concentration)
Tc Total =5.00
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.30 (calculated above)
I = 0.78 Tc-0.64 (in/hr)3.83 (25-yr storm)
A = area (acres)0.62 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)0.70 (assuming no carry flow)
DRAINAGE AREA # 5A
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Local 0.76 31128 23657
ROW - Angled 0.93 16099 14972
Commercial 0.95 95851 91058
Total 143078 129688
A = Area (acres)3.28
C = Weighted C Factor 0.91
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)1.00 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.95 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)650 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)4.77
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0152
L = length of gutter (ft)361
V = mean velocity (ft/s)3.70
Tc Gutter Flow (minutes) =1.63
Tc Total =6.40
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.91 (calculated above)
I = 0.78 Tc-0.64 (in/hr)3.27 (25-yr storm)
A = area (acres)3.28 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)9.73 (assuming no carry flow)
REQ'D PIPE CAPACITY
DA 5A 9.73 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:PIPE 5A Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 18 inches
d= 16.88 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.005 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2 Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
1.72 3.96 0.44 6.70 11.54 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 5B
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Angled 0.93 12707 11818
ROW - Local 0.76 13202 10033
Park 0.20 15270 3054
Residential - Dense 0.75 44174 33131
Total 85354 58036
A = Area (acres)1.96
C = Weighted C Factor 0.68
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)1.00 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.75 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)217 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)7.58
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0080
L = length of gutter (ft)350
V = mean velocity (ft/s)2.68
Tc Gutter Flow (minutes) =2.18
Tc Total =9.75
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.68 (calculated above)
I = 0.78 Tc-0.64 (in/hr)2.50 (25-yr storm)
A = area (acres)1.96 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)3.32 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 9 feet into Drive Aisle
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0080
Q = PROVIDED GUTTER CAPACITY (cfs)3.33
REQ'D PIPE CAPACITY
DA 5B 3.33 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:PIPE 5B Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 15 inches
d= 14.07 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.005 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2
Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
1.20 3.30 0.36 5.94 7.10 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # 5C
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Angled 0.93 8517 7921
ROW - Local 0.76 13607 10341
Park 0.20 24597 4919
Total 46720 23181
A = Area (acres)1.07
C = Weighted C Factor 0.50
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)1.00 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.75 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)216 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)7.56
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0077
L = length of gutter (ft)350
V = mean velocity (ft/s)2.63
Tc Gutter Flow (minutes) =2.22
Tc Total =9.77
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.50 (calculated above)
I = 0.78 Tc-0.64 (in/hr)2.49 (25-yr storm)
A = area (acres)1.07 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)1.33 (assuming no carry flow)
PROVIDED GUTTER CAPACITY
1. Calculate Gutter Capacity @ 9 feet into Drive Aisle
Q = (1.486/n)AR2/3 S1/2
n = Mannings Coefficient 0.013
A = Area (ft2)1.24 (0.15' below top of curb)
P = Wetted perimeter (ft)9.23 (0.15' below top of curb)
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0077
Q = PROVIDED GUTTER CAPACITY (cfs)3.26
REQ'D PIPE CAPACITY
PIPE 5B + PIPE 5A + DA 5C 14.38 cfs
MANNING'S EQUATION FOR PIPE FLOW
Pipe:PIPE 5C Project:Blackwood Groves Subdivision Phase 1
INPUT
D= 21 inches
d= 19.70 inches
Mannings Formula n= 0.009 mannings
q=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.004 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter
S=slope of channel V=(1.49/n)Rh2/3S1/2
n=Manning's roughness coefficient Q=V x A
Solution to Mannings Equation
Area,ft2 Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
2.34 4.62 0.51 6.64 15.57 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
DRAINAGE AREA # ALDER CREEK SPRING RIDGE AND S. 15TH
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft
2 ) C * Area
ROW - Local 0.76 12000 9120
Total 12000 9120
A = Area (acres)0.28
C = Weighted C Factor 0.76
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)1.00 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.50 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)380 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)20.05
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0144
L = length of gutter (ft)279
V = mean velocity (ft/s)3.60
Tc Gutter Flow (minutes) =1.29
Tc Total =21.34
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.76 (calculated above)
I = 0.78 Tc-0.64 (in/hr)1.51 (25-yr storm)
A = area (acres)0.28 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)0.32 (assuming no carry flow)
4. Calculate Additional Runoff Volume
Q = CIA
V=7200Q
C = Weighted C Factor 0.76
I = intensity (in/hr) 0.41 (10 yr, 2hr storm)
A = Area (acres)0.28
Q = runoff (cfs)0.09
V = REQUIRED VOL (ft3)618
DRAINAGE AREA # ALDER CREEK S. 11TH
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft
2 ) C * Area
ROW - Collector 0.70 5386 3770
Total 5386 3770
A = Area (acres)0.12
C = Weighted C Factor 0.70
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)1.00 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.50 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)380 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)20.05
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (ft/ft)0.0144
L = length of gutter (ft)279
V = mean velocity (ft/s)3.60
Tc Gutter Flow (minutes) =1.29
Tc Total =21.34
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.70 (calculated above)
I = 0.78 Tc-0.64 (in/hr)1.51 (25-yr storm)
A = area (acres)0.12 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs)0.13 (assuming no carry flow)
4. Calculate Additional Runoff Volume
Q = CIA
V=7200Q
C = Weighted C Factor 0.70
I = intensity (in/hr) 0.41 (10 yr, 2hr storm)
A = Area (acres)0.12
Q = runoff (cfs)0.04
V = REQUIRED VOL (ft3)255
APPENDIX D
Pond Sizing Calculations
POND 5 - Temporary Retention
REQUIRED VOLUME
1. Calculate Area and Weighted C Factor (Post-Development)
Contributing Area DA C Area (ft2 )C * Area
ROW - Local 5 0.76 26808 20441
Total 26808 20441
A = Area (acres)0.62
C = Weighted C Factor 0.76
2. Calculate Required Volume
Q = CIA
V=7200Q
C = Weighted C Factor 0.62
I = intensity (in/hr) 0.41 (10 yr, 2hr storm)
A = Area (acres)0.62
Q = runoff (cfs)0.16
V = REQUIRED VOL (ft3)1118
Check the half inch requirement (per DSSP II.A.4)
1. Determine Area of Hardscape within Drainage Area #2
Contributing Area Area (ft2 )
Hardscape 20,106
2. Calculate 1/2" runoff volume over hardscape
(aka Runoff Reduction Volume [RRV] as calculated in Montana Post-
Construction Storwater BMP Manual - Equation 3-1)
RRV = [P*Rv*A]/12
P = Water quality rainfall depth 0.50 inches
Rv = Dimensionless runoff coefficient 0.73 0.05 + 0.9*I
I = Percent impervious cover (decimal)0.75 decimal
A = Entire drainage area 0.62 acres
RRV = Runoff Reduction Volume 0.019 acre-ft
RRV = Runoff Reduction Volume 810 cubic feet
Because the runoff volume from the 10-yr, 2-hr storm (for flood control) is
greater than the runoff volume produced by the half inch rainfall (for water quality)
the temporary retention facility is sized to handle the larger volume (1,118 cf).
Temporary Retention Pond A NORTH 100 FT OF AVENUE A
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
ROW - Local 0.76 6816 5180
Total 6816 5180
A = Area (acres)0.16
C = Weighted C Factor 0.76
2. Calculate Required Volume
Q = CIA
V=7200Q
C = Weighted C Factor 0.76
I = intensity (in/hr) 0.41 (10 yr, 2hr storm)
A = Area (acres)0.16
Q = runoff (cfs)0.05
V = REQUIRED VOL (ft3)351
POND 6 - DETENTION
REQUIRED VOLUME
1. Calculate Area and Weighted C Factor (Post-Development)
Contributing Area DA C Area (ft 2)C * Area
ROW - Collector 6B 0.70 28881 20216
ROW - Angled 6B 0.93 6517 6061
ROW - Alley 6A 0.80 17950 14360
OS 6C 0.20 8017 1603
OS 6A 0.20 2253 451
Residential - Dense 6A 0.75 96773 72580
Total 160390 115271
A = Area (acres)3.68
C = Weighted C Factor 0.72
2. Pre-Development Conditions
Pre-Development Drainage Area Name = EX 4
Pre-Development Drainage Area Size = 39.24 (acres)
Pre Development Tc =70 (minutes)
Pre-Development Runoff Rate (Total) =4.55 (cfs)
Pre-Development Runoff Rate (Pond 6) =1.00 (cfs)
Pre-Development Runoff Rate (Pond 7) =1.90 (cfs)
Pre-Development Runoff Rate (Total) =2.90 (cfs)
5. Calculate Required Pond Volume
Total Area (acres) =3.68 acres
Weighted C =0.72
Discharge Rate (cfs) =1.00 cfs (Equal to Pre-Development Runoff Rate)
Duration(min)Duration(hrs)Intensity
(in/hr)Qin (cfs)Runoff
Volume
Release
Volume
Required
Storage
(ft3)
24 0.40 1.16 3.07 4424 0 4424.20
25 0.42 1.13 2.99 4488 0 4487.86
26 0.43 1.10 2.92 4550 0 4549.89
27 0.45 1.08 2.85 4610 0 4610.39
28 0.47 1.05 2.78 4669 0 4669.45
29 0.48 1.03 2.72 4727 60 4667.15
30 0.50 1.00 2.66 4784 120 4663.58
31 0.52 0.98 2.60 4839 180 4658.79
32 0.53 0.96 2.55 4893 240 4652.86
33 0.55 0.94 2.50 4946 300 4645.84
PROVIDED VOLUME (ft3)4,777
OUTLET STRUCTURE SLOT
Q=CLH3/2
Q = Discharge (cfs)1.00
C = Weir Coefficient 3.33 (per COB Design Standards)
H = Head (ft)1.5
L = Horizontal Length (ft)0.16
L = Slot Width (inches)2.0
Check the half inch requirement (per DSSP II.A.4)
1. Determine Area of Hardscape within Drainage Basin
Contributing Area Area (ft 2 )
Hardscape 110,924
2. Calculate 1/2" runoff volume over hardscape
(aka Runoff Reduction Volume [RRV] as calculated in Montana Post-
Construction Storwater BMP Manual - Equation 3-1)
RRV = [P*Rv*A]/12
P = Water quality rainfall depth 0.50 inches
Rv = Dimensionless runoff coefficient 0.67 0.05 + 0.9*I
I = Percent impervious cover (decimal)0.69 decimal
A = Entire drainage area 3.68 acres
RRV = Runoff Reduction Volume 0.103 acre-ft
RRV = Runoff Reduction Volume 4494 cubic feet
POND 7 - DETENTION
REQUIRED VOLUME
1. Calculate Area and Weighted C Factor (Post-Development)
Contributing Area DA C Area (ft 2 )C * Area
ROW - Collector 7A 0.70 49013 34309
ROW - Collector 7B 0.70 3550 2485
ROW - Collector 7C 0.70 16245 11372
ROW - Collector 7D 0.70 28687 20081
ROW - Collector 7E 0.70 6785 4750
ROW - Collector 7F 0.70 1075 753
ROW - Collector 7G 0.70 14593 10215
ROW - Collector 7H 0.70 5189 3633
ROW - Local 7B 0.76 16101 12237
ROW - Local 7C 0.76 13401 10218
ROW - Local 7E 0.76 4125 3135
ROW - Local 7F 0.76 3465 2634
ROW - Angled 7A 0.93 6218 5783
Park 7H 0.20 21814 4363
Commercial 7A 0.95 131497 124922
Residential - Dense 7B 0.75 37248 27936
Residential - Low-Med 7C 0.35 62558 21895
Total 421566 300720
A = Area (acres)9.68
C = Weighted C Factor 0.71
2. Pre-Development Conditions
Pre-Development Drainage Area Name = EX 4
Pre-Development Drainage Area Size = 39.24 (acres)
Pre Development Tc =70 (minutes)
Pre-Development Runoff Rate (Total) =4.55 (cfs)
Pre-Development Runoff Rate (Pond 6) =1.00 (cfs)
Pre-Development Runoff Rate (Pond 7) =1.90 (cfs)
Pre-Development Runoff Rate (Total) =2.90 (cfs)
5. Calculate Required Pond Volume
Total Area (acres) =9.68 acres
Weighted C =0.71
Discharge Rate (cfs) =1.90 cfs (Equal to Pre-Development Runoff Rate)
Duration(min)Duration(hrs)Intensity
(in/hr)Qin (cfs)Runoff
Volume
Release
Volume
Required
Storage
(ft3)
40 0.67 0.83 5.75 13,801 1,596 12,205
41 0.68 0.82 5.66 13,921 1,710 12,211
42 0.70 0.81 5.57 14,039 1,824 12,215
43 0.72 0.79 5.49 14,155 1,938 12,217
44 0.73 0.78 5.41 14,270 2,052 12,218
45 0.75 0.77 5.33 14,382 2,166 12,216
46 0.77 0.76 5.25 14,493 2,280 12,213
47 0.78 0.75 5.18 14,603 2,394 12,209
48 0.80 0.74 5.11 14,711 2,508 12,203
49 0.82 0.73 5.04 14,817 2,622 12,195
PROVIDED VOLUME (ft3)12,484
OUTLET STRUCTURE SLOT
Q=CLH3/2
Q = Discharge (cfs)1.90
C = Weir Coefficient 3.33 (per COB Design Standards)
H = Head (ft)1.5
L = Horizontal Length (ft)0.31
L = Slot Width (inches)3.7
Check the half inch requirement (per DSSP II.A.4)
1. Determine Area of Hardscape within Drainage Basin
Contributing Area Area (ft 2 )
Hardscape 288,542
2. Calculate 1/2" runoff volume over hardscape
(aka Runoff Reduction Volume [RRV] as calculated in Montana Post-
Construction Storwater BMP Manual - Equation 3-1)
RRV = [P*Rv*A]/12
P = Water quality rainfall depth 0.50 inches
Rv = Dimensionless runoff coefficient 0.67 0.05 + 0.9*I
I = Percent impervious cover (decimal)0.68 decimal
A = Entire drainage area 9.68 acres
RRV = Runoff Reduction Volume 0.269 acre-ft
RRV = Runoff Reduction Volume 11699 cubic feet
POND 8C - DETENTION
REQUIRED VOLUME
1. Calculate Area and Weighted C Factor (Post-Development)
Contributing Area DA C Area (ft2)C * Area
Park 8J 0.20 16304 3261
Residential - Dense (Reduced C) 8J 0.40 23902 9561
ROW - Local 8J 0.76 16953 12885
Residential - Low-Med 8K 0.35 15988 5596
ROW - Local 8K 0.76 8897 6762
Residential - Low-Med 8L 0.35 21604 7561
Residential - Dense (Reduced C) 8L 0.40 35468 14187
Park 8L 0.20 4800 960
OS 8L 0.20 3410 682
ROW - Local 8L 0.76 34076 25898
Residential - Low-Med 8M 0.35 38062 13322
ROW - Local 8M 0.76 13224 10051
Park 8M 0.20 6000 1200
Residential - Low-Med 8N 0.35 9242 3235
ROW - Local 8N 0.76 3580 2721
Total 251511 117880
A = Area (acres)5.77
C = Weighted C Factor 0.47
2. Pre-Development Conditions
Pre-Development Drainage Area Name = EX 2
Pre-Development Drainage Area Size = 92.60 (acres)
Pre Development Tc =96 (minutes)
Pre-Development Runoff Rate (Total) =8.73 (cfs)
Pre-Development Runoff Rate (Pond 8C) = 1.26 (cfs)
Pre-Development Runoff Rate (Pond 8A) =1.88 (cfs)
Pre-Development Runoff Rate (Pond 8B) =4.94 (cfs)
Pre-Development Runoff Rate (Pond 9) =0.65 (cfs)
Pre-Development Runoff Rate (Total) =8.73 (cfs)
5. Calculate Required Pond Volume
Total Area (acres) =5.77 acres
Weighted C =0.47
Discharge Rate (cfs) =1.26 cfs (Equal to Pre-Development Runoff Rate)
Duration(min)Duration(hrs)Intensity
(in/hr)Qin (cfs)Runoff
Volume
Release
Volume
Required
Storage
(ft3)
15 0.25 2 4 3,838 227 3,611
16 0.27 2 4 3,926 302 3,623
17 0.28 1 4 4,010 378 3,632
18 0.30 1 4 4,091 454 3,637
19 0.32 1 4 4,169 529 3,640
20 0.33 1 4 4,245 605 3,640
21 0.35 1 3 4,318 680 3,637
22 0.37 1 3 4,389 756 3,633
23 0.38 1 3 4,457 832 3,626
24 0.40 1 3 4,524 907 3,617
PROVIDED VOLUME (ft3)3,925
OUTLET STRUCTURE SLOT
Q=CLH3/2
Q = Discharge (cfs)1.26
C = Weir Coefficient 3.33 (per COB Design Standards)
H = Head (ft)1.5
L = Horizontal Length (ft)0.21
L = Slot Width (inches)2.5
Check the half inch requirement (per DSSP II.A.4)
1. Determine Area of Hardscape within Drainage Basin
Contributing Area Area (ft 2 )
Hardscape 90,103
2. Calculate 1/2" runoff volume over hardscape
(aka Runoff Reduction Volume [RRV] as calculated in Montana Post-
Construction Storwater BMP Manual - Equation 3-1)
RRV = [P*Rv*A]/12
P = Water quality rainfall depth 0.50 inches
Rv = Dimensionless runoff coefficient 0.37 0.05 + 0.9*I
I = Percent impervious cover (decimal)0.36 decimal
A = Entire drainage area 5.77 acres
RRV = Runoff Reduction Volume 0.090 acre-ft
RRV = Runoff Reduction Volume 3903 cubic feet
POND 8B - DETENTION
REQUIRED VOLUME
1. Calculate Area and Weighted C Factor (Post-Development)
Contributing Area DA C Area (ft2 )C * Area
ROW - Angled 8B 0.93 31758 29535
Commercial 8B 0.95 0 0
ROW - Local 8B 0.76 8489 6452
ROW - Local 8D 0.76 28957 22007
Park 8B 0.20 0 0
Residential - Dense (Reduced C)8B 0.40 0 0
Residential - Low-Med 8D 0.35 104870 36704
ROW - Local 8G 0.76 16169 12288
ROW - Alley 8D 0.80 10487 8390
Residential - Low-Med 8G 0.35 48000 16800
ROW - Local 8I 0.76 2548 1937
OS 8I 0.20 4469 894
Total 255747 135007
A = Area (acres)5.87
C = Weighted C Factor 0.53
2. Pre-Development Conditions
Pre-Development Drainage Area Name = EX 2
Pre-Development Drainage Area Size = 92.60 (acres)
Pre Development Tc =96 (minutes)
Pre-Development Runoff Rate (Total) =8.73 (cfs)
Pre-Development Runoff Rate (Pond 8B) =4.94 (cfs)
Pre-Development Runoff Rate (Pond 8C)=1.26 (cfs)
Pre-Development Runoff Rate (Pond 8A)=1.88 (cfs)
Pre-Development Runoff Rate (Pond 9) =0.65 (cfs)
Pre-Development Runoff Rate (Total) =8.73 (cfs)
5. Calculate Required Pond Volume
Total Area (acres) =5.87 acres
Weighted C =0.53
Discharge Rate (cfs) =4.94 cfs (Equal to Pre-Development Runoff Rate)
Duration(min)Duration(hrs)Intensity
(in/hr)Qin (cfs)Runoff
Volume
Release
Volume
Required
Storage
(ft3)
3 0.05 4 25 4,448 0 4,448
4 0.07 4 20 4,919 0 4,919
5 0.08 3 18 5,318 296 5,022
6 0.10 3 16 5,669 593 5,076
7 0.12 3 14 5,983 889 5,094
8 0.13 2 13 6,269 1,186 5,084
9 0.15 2 12 6,533 1,482 5,051
10 0.17 2 11 6,778 1,778 5,000
11 0.18 2 11 7,008 2,075 4,934
12 0.20 2 10 7,225 2,371 4,854
PROVIDED VOLUME (ft3)5,095
OUTLET STRUCTURE SLOT
Q=CLH3/2
Q = Discharge (cfs)4.94
C = Weir Coefficient 3.33 (per COB Design Standards)
H = Head (ft)1.5
L = Horizontal Length (ft)0.81
L = Slot Width (inches)9.7
Check the half inch requirement (per DSSP II.A.4)
1. Determine Area of Hardscape within Drainage Basin
Contributing Area Area (ft2 )
Hardscape 111,810
1/2" of Runoff for Block 17, Block 12 will be
handled on each site during the site plan process
2. Calculate 1/2" runoff volume over hardscape
(aka Runoff Reduction Volume [RRV] as calculated in Montana Post-
Construction Storwater BMP Manual - Equation 3-1)
RRV = [P*Rv*A]/12
P = Water quality rainfall depth 0.50 inches
Rv = Dimensionless runoff coefficient 0.44 0.05 + 0.9*I
I = Percent impervious cover (decimal)0.437 decimal
A = Entire drainage area 5.87 acres
RRV = Runoff Reduction Volume 0.108 acre-ft
RRV = Runoff Reduction Volume 4726 cubic feet
POND 8A - DETENTION
REQUIRED VOLUME
1. Calculate Area and Weighted C Factor (Post-Development)
Contributing Area DA C Area (ft 2)C * Area
ROW - Local 8A 0.76 36398 27754
ROW - Angled 8A 0.93 20802 19346
Residential - Dense (Reduced C)8A 0.40 99407 39763
Commercial 8A 0.95 43975 41776
Park 8A 0.20 12172 2434
OS 8A 0.20 13111 2622
ROW - Local 8C 0.76 11853 9008
Residential - Low-Med 8C 0.35 25880 9058
ROW - Local 8E 0.76 12430 9447
Residential - Low-Med 8E 0.35 22158 7755
Residential - Low-Med 8F 0.35 19747 6911
ROW - Local 8F 0.76 6521 4956
ROW - Local 8H 0.76 2300 1748
OS 8H 0.20 4500 900
Total 331254 183479
A = Area (acres)7.60
C = Weighted C Factor 0.55
2. Pre-Development Conditions
Pre-Development Drainage Area Name = EX 2
Pre-Development Drainage Area Size = 92.60 (acres)
Pre Development Tc =96 (minutes)
Pre-Development Runoff Rate (Total) =8.73 (cfs)
Pre-Development Runoff Rate (Pond 8A) =1.88 (cfs)
Pre-Development Runoff Rate (Pond 8C) =1.26 (cfs)
Pre-Development Runoff Rate (Pond 8B) =4.94 (cfs)
Pre-Development Runoff Rate (Pond 9) =0.65 (cfs)
Pre-Development Runoff Rate (Total) =8.73 (cfs)
5. Calculate Required Pond Volume
Total Area (acres) =7.60 acres
Weighted C =0.55
Discharge Rate (cfs) =1.88 cfs (Equal to Pre-Development Runoff Rate)
Duration(min)Duration(hrs)Intensity
(in/hr)Qin (cfs)Runoff
Volume
Release
Volume
Required
Storage
(ft3)
17 0.28 1 6 6,241 1,241 5,001
18 0.30 1 6 6,368 1,354 5,014
19 0.32 1 6 6,489 1,466 5,023
20 0.33 1 6 6,607 1,579 5,028
21 0.35 1 5 6,721 1,692 5,029
22 0.37 1 5 6,831 1,805 5,026
23 0.38 1 5 6,938 1,918 5,020
24 0.40 1 5 7,042 2,030 5,012
25 0.42 1 5 7,143 2,143 5,000
26 0.43 1 5 7,242 2,256 4,986
PROVIDED VOLUME (ft3)5,130
OUTLET STRUCTURE SLOT
Q=CLH3/2
Q = Discharge (cfs)1.88
C = Weir Coefficient 3.33 (per COB Design Standards)
H = Head (ft)1.5
L = Horizontal Length (ft)0.31
L = Slot Width (inches)3.7
Check the half inch requirement (per DSSP II.A.4)
1. Determine Area of Hardscape within Drainage Basin
Contributing Area Area (ft 2 )
Hardscape 156,304
2. Calculate 1/2" runoff volume over hardscape
(aka Runoff Reduction Volume [RRV] as calculated in Montana Post-
Construction Storwater BMP Manual - Equation 3-1)
RRV = [P*Rv*A]/12
P = Water quality rainfall depth 0.50 inches
Rv = Dimensionless runoff coefficient 0.475 0.05 + 0.9*I
I = Percent impervious cover (decimal)0.472 decimal
A = Entire drainage area 7.60 acres
RRV = Runoff Reduction Volume 0.150 acre-ft
RRV = Runoff Reduction Volume 4586 cubic feet
POND 9 - DETENTION
REQUIRED VOLUME
1. Calculate Area and Weighted C Factor (Post-Development)
Contributing Area DA C Area (ft 2)C * Area
ROW - Local 9A 0.76 14613 11106
Residential - Dense 9A 0.75 84215 63161
ROW - Local 9B 0.76 46828 35590
Park 9B 0.20 20901 4180
Residential - Dense 9B 0.75 153570 115178
ROW - Local 9C 0.76 22307 16953
Commercial 9C 0.95 26505 25180
Residential - Dense (Reduced C) 9C 0.40 45055 18022
ROW - Local 9D 0.76 12697 9649
Residential - Dense 9D 0.40 11619 4647
OS 9D 0.20 3357 671
ROW - Local 9E 0.76 21527 16360
Residential - Dense 9E 0.75 102610 76958
ROW - Local 9F 0.76 7859 5973
ROW - Local 9G 0.76 9046 6875
OS 9G 0.20 13120 2624
Park 9G 0.20 4251 850
Residential - Dense 9G 0.75 35478 26609
ROW - Local 9H 0.76 17977 13662
Residential - Low-Med 9H 0.35 20009 7003
ROW - Local 9I 0.76 11917 9057
ROW - Collector 9I 0.70 35815 25070
Residential - Dense 9I 0.75 46397 34798
ROW - Collector 9J 0.70 41138 28797
ROW - Local 9K 0.76 5714 4343
Residential - Low-Med 9K 0.35 12487 4370
Residential - Dense 9L 0.75 103406 77554
OS 9L 0.20 50963 10193
Total 981380 655434
A = Area (acres)22.53
C = Weighted C Factor 0.67
2. Pre-Development Conditions
Pre-Development Drainage Area Name = EX 2
Pre-Development Drainage Area Size = 92.60 (acres)
Pre Development Tc =96 (minutes)
Pre-Development Runoff Rate (Total) =8.73 (cfs)
Pre-Development Runoff Rate (Pond 8A) =1.88 (cfs)
Pre-Development Runoff Rate (Pond 8B) =4.94 (cfs)
Pre-Development Runoff Rate (Pond 8C) =1.26
Pre-Development Runoff Rate (Pond 9) =0.65 (cfs)
Pre-Development Runoff Rate (Total) =8.73 (cfs)
5. Calculate Required Pond Volume
Total Area (acres) =22.53 acres
Weighted C =0.67
Discharge Rate (cfs) =0.65 cfs (Equal to Pre-Development Runoff Rate)
Duration(min)Duration(hrs)Intensity
(in/hr)Qin (cfs)Runoff
Volume
Release
Volume
Required
Storage
(ft3)
751 12.52 0.12 1.86 83,955 28,392 55,563
752 12.53 0.12 1.86 83,994 28,431 55,563
753 12.55 0.12 1.86 84,033 28,470 55,563
754 12.57 0.12 1.86 84,072 28,509 55,563
755 12.58 0.12 1.86 84,111 28,548 55,563
756 12.60 0.12 1.86 84,150 28,587 55,563
757 12.62 0.12 1.85 84,189 28,626 55,563
758 12.63 0.12 1.85 84,228 28,665 55,563
759 12.65 0.12 1.85 84,267 28,704 55,563
760 12.67 0.12 1.85 84,305 28,743 55,562
PROVIDED VOLUME (ft3)57,340
OUTLET STRUCTURE SLOT
Q=CLH3/2
Q = Discharge (cfs)0.65
C = Weir Coefficient 3.33 (per COB Design Standards)
H = Head (ft)0.75
L = Horizontal Length (ft)0.30
L = Slot Width (inches)3.6
Check the half inch requirement (per DSSP II.A.4)
1. Determine Area of Hardscape within Drainage Basin
Contributing Area Area (ft 2 )
Hardscape 612,210
2. Calculate 1/2" runoff volume over hardscape
(aka Runoff Reduction Volume [RRV] as calculated in Montana Post-
Construction Storwater BMP Manual - Equation 3-1)
RRV = [P*Rv*A]/12
P = Water quality rainfall depth 0.50 inches
Rv = Dimensionless runoff coefficient 0.61 0.05 + 0.9*I
I = Percent impervious cover (decimal)0.62 decimal
A = Entire drainage area 22.53 acres
RRV = Runoff Reduction Volume 0.574 acre-ft
RRV = Runoff Reduction Volume 25002 cubic feet
APPENDIX E
Groundwater Monitoring Results
Project Engineer:
Project:
South Bozeman, Gallatin County, MT
Well Information:bgs = below ground surface ags = above ground surface
MW-1 MW-2 MW-3 MW-4 MW-5 MW-6 MW-7 MW-8 MW-9 MW-10 MW-11 MW-12 MW-13 MW-14 MW-15 MW-16 MW-17 MW-18 MW-19 MW-20
3.83 3.00 3.08 3.67 1.50 2.42 2.08 3.58 2.92 2.92 3.83 2.92 3.92 3.58 4.08 3.00 3.92 3.50 3.58 2.92
Groundwater Information:
MW-1 MW-2 MW-3 MW-4 MW-5 MW-6 MW-7 MW-8 MW-9 MW-10 MW-11 MW-12 MW-13 MW-14 MW-15 MW-16 MW-17 MW-18 MW-19 MW-20
3.34 3.05 3.02 2.78 3.45 1.58 4.24 4.27 2.55 4.13 3.99 4.36 2.25 2.27 2.26 5.50 2.71 2.20 2.97 2.38
3.47 3.18 3.11 2.85 3.49 1.50 4.42 4.42 2.64 4.34 4.31 4.78 2.50 2.32 2.60 6.10 2.85 2.42 3.40 2.77
3.57 3.23 3.13 2.94 4.10 1.64 4.53 4.53 2.67 4.45 4.36 4.90 2.54 2.39 2.65 6.21 2.92 2.74 3.74 2.96
3.75 3.42 3.26 3.18 3.74 1.88 4.72 4.70 2.80 4.59 4.50 5.16 2.84 2.54 2.84 6.32 3.18 3.14 4.07 3.19
3.78 3.63 3.36 3.35 3.81 1.94 4.90 4.98 2.99 4.86 4.56 5.31 3.16 2.83 3.23 DRY 3.79 3.68 4.31 3.49
3.76 3.65 3.41 3.43 3.76 1.91 4.94 5.11 3.09 4.98 4.68 5.48 3.25 2.79 3.30 DRY 4.17 3.91 4.51 3.56
3.94 3.82 3.52 3.45 3.83 2.00 4.90 5.23 3.27 5.08 4.82 5.60 3.42 2.88 3.37 DRY 4.29 4.05 4.67 3.59
3.90 3.68 3.38 3.31 3.75 1.94 4.85 4.93 3.08 5.02 4.86 5.66 3.37 2.88 3.20 DRY 4.22 4.11 4.80 3.48
4.00 3.87 3.55 3.60 4.01 2.24 5.11 5.23 3.44 5.18 4.82 5.65 3.54 3.13 3.46 DRY 4.59 4.31 4.87 3.80
4.09 3.52 3.34 3.33 3.81 2.09 5.06 5.03 3.11 4.99 5.42 5.08 3.34 2.89 3.37 DRY 4.59 4.41 4.47 3.60
4.14 4.09 3.69 3.72 3.92 2.34 5.24 5.42 3.69 5.39 4.95 5.78 3.73 3.34 3.69 DRY 4.87 4.65 5.03 3.89
4.16 4.38 4.13 4.01 4.12 2.49 5.43 5.70 4.06 5.99 5.27 6.24 4.20 3.79 3.99 DRY 5.29 5.19 5.63 4.07
ICE 2.50 2.49 2.03 ICE 0.93 3.43 3.60 2.39 ICE 3.69 3.88 1.38 1.47 1.82 4.04 2.27 0.96 2.07 2.01
1.99 1.95 2.16 1.64 3.00 0.63 3.04 3.29 2.19 3.08 3.07 3.33 0.72 0.72 0.87 3.57 2.10 0.60 1.67 1.28
2.65 2.25 2.37 1.93 3.35 1.03 3.14 3.47 2.29 3.26 3.29 3.60 1.18 1.62 1.57 3.60 2.30 1.20 2.19 1.45
2.94 2.50 2.53 2.17 1.90 1.54 3.32 3.68 2.33 3.53 3.63 3.83 1.56 1.53 1.86 4.13 2.40 1.45 2.47 1.86
3.27 2.97 2.84 2.64 2.35 1.42 3.72 4.30 2.48 3.95 3.92 4.23 2.00 1.67 2.13 4.52 2.68 2.04 3.07 2.38
3.47 3.20 3.00 2.85 2.50 1.52 3.94 4.38 2.59 4.23 4.17 4.61 2.30 2.29 2.42 4.97 2.81 2.55 3.42 2.70
3.57 3.28 3.10 2.98 2.60 1.68 4.13 4.52 2.65 4.39 4.37 4.88 2.53 2.35 2.64 DRY 2.91 2.92 3.85 2.93
3.68 3.38 3.21 3.10 2.70 1.74 4.29 4.68 2.70 4.54 4.57 5.10 2.73 2.43 2.81 DRY 3.12 3.30 4.13 3.17
3.79 3.51 3.32 3.20 2.66 1.89 4.51 4.79 2.81 4.71 4.74 5.32 2.93 2.60 2.97 DRY 3.47 3.56 4.37 3.33
3.92 3.63 3.51 3.38 2.79 1.95 4.79 4.90 2.92 4.89 4.78 5.49 3.08 2.63 3.08 DRY 3.73 4.09 4.57 3.59
5.15.20
4.10.20
4.17.20
4.24.20
5.1.20
5.8.20
Well ID
Well Depth (feet-bgs)
Top of Well (feet-ags)
Ground Elevation
4.6.20
Date
5.10.19
6.10.19
6.17.19
6.20.19
6.28.19
7.12.19
7.26.19
8.9.19
Monitor Well Data
Depth to Ground Water (feet-bgs)
Project Number: 190390
South Bozeman Groundwater Monitoring
Project Location:
8.23.19
3.24.20
5.20.19
5.24.19
5.31.19
5.22.205.29.20