HomeMy WebLinkAboutCILWR Correspondance1
Celine Saucier
From:Celine Saucier
Sent:Thursday, August 12, 2021 7:06 AM
To:Griffin Nielsen
Subject:CILWR Bozeman Gateway Site A - Everhome Hotel (#20138)
Attachments:Site A _ C300 Overall Site Plan _ 8-11-21.pdf; Site A _ C301 Overall Site Plan _
8-11-21.pdf
Griffin –
I’m working on the Bozeman Gateway Site A Everhome Hotel Site Plan Application (#20138). We were
advised to contact you per the site plan checklist in regards to the CILWR. The proposed Everhome (attached)
will consist of a 4 floor hotel with an approximate gross floor area of 62,108SF. Was hoping you can provided
a CIL number based on this information.
Let me know if there is anything additional I can provide for you to determine the CILWR number, thanks!
Celine Saucier, PE
Civil Engineer, Morrison-Maierle
+14069226822
2880 Technology Blvd W, Bozeman, MT 59718