HomeMy WebLinkAbout006_21208 Ridge Lot 6 MOD Approval
September 1, 2021
Martina Parrish
45 Architecture
1216 West Lincoln Street, Suite D
Bozeman, MT 59715
mparrish@45arch.com
RE: Ridge Lot 6 PUD - Modification Application 21208
Dear Applicant,
The Bozeman Department of Community Development is pleased to award approval of your modification
application for the project referenced above. The application requests approval for the following modifications
to the final plan of the Ridge Final PUD 17562:
• Changes to lot 6 uses and building square footage
Staff forwarded a recommendation to the Community Development Director who is responsible for the final
decision. Pursuant to section 38.230.150, BMC, amendments to approved plans must be reviewed and may be
approved by the community development director upon determining that the amended plan is in substantial
compliance with the originally approved plan.
Please be aware that as the applicant you must comply with all provisions of Chapter 38 of the Bozeman
Municipal Code that are applicable to this project, including but not limited to the following:
Code Provisions
Per Section 38.100.080 & 38.200.110, the proposed project shall be completed as approved and in this
application. Any modifications to the submitted and approved application materials shall invalidate the
project's legitimacy, unless the applicant submits the proposed modifications for review and approval
by the Department of Community Development prior to undertaking said modifications. The only
exception to this law is repair.
You have the right to appeal this decision of the Community Development Director pursuant to the provisions
of the Bozeman Municipal Code. Please note that this decision is subject to appeal by other aggrieved parties as
defined by Sec. 38.700.020 of the Bozeman Municipal Code. Such appeals must be filed pursuant to the
provisions of Sec. 38.250.030 of the Bozeman Municipal Code. An appeal must be filed within 10 working days
following the date of this decision. If a valid appeal is filed, no further action on the project may proceed until a
decision on the appeal is made by the City Commission, and the Community Development Department and
Building Division will not be able to approve any building permits or to perform any inspections related to this
application.
If you have any more questions, or if the Community Development Department can be of further assistance,
please do not hesitate to contact me at bkrueger@bozeman.net.
Best Regards,
Brian Krueger, Department of Community Development
For office use only
DATE OF FINAL DECISION ______________________________