HomeMy WebLinkAbout22- Amendment 1 - PSA Morrison Maierle - Structural Assessments
1ST Amendment to Professional Services Agreement for Structural Assessments
FY 2022 – FY 2023
Page 1 of 2
FIRST AMENDMENT TO PROFESSIONAL SERVICES AGREEMENT
THIS FIRST AMENDMENT TO THE PROFESSIONAL SERVICES AGREEMENT FOR
Structural Assessments dated ______________ (the “Agreement”) is made and entered into this
_____ day of ____________, 2022, by and between the CITY OF BOZEMAN, MONTANA, a
self governing municipal corporation organized and existing under its Charter and the laws of the
State of Montana, 121 North Rouse Street, Bozeman, Montana, with a mailing address of PO Box
1230, Bozeman, MT 59771, hereinafter referred to as “City,” and Morrison Maierle, 2880
Technology Blvd. W., Drive, Bozeman, MT 59771, hereinafter referred to as “Contractor.”
In consideration of the mutual covenants and agreements herein contained, the receipt and
sufficiency whereof being hereby acknowledged, the parties hereto agree to amend the Agreement
as follows:
1. Extension of Term. Section 2 of the Agreement is extended for an additional six (6) month
period. The Agreement shall terminate on the 30th day of December, 2022.
2. Addition to Scope of Work. Tier 1 seismic assessment and expanded analysis of roof
trusses as described in Exhibit A.
3. Addition to Payment. See Exhibit A for not to exceed fee estimates for services provided.
4. Agreement still valid. All remaining terms and provisions of the Agreement remain valid.
**** END OF AGREEMENT EXCEPT FOR SIGNATURES ****
DocuSign Envelope ID: C72D3F33-7BBF-4042-98BB-03FD61CCA781
April
February 8, 2022
5th
1ST Amendment to Professional Services Agreement for Structural Assessments
FY 2022 – FY 2023
Page 2 of 2
IN WITNESS WHEREOF, the parties hereto have executed this instrument the day and
year first above written.
CITY OF BOZEMAN, MONTANA MORRISON MAIERLE
By________________________________ By_____________________________
Jeff Mihelich, City Manager Print Name: Jay Fisher
Title: Project Manager
APPROVED AS TO FORM
By_______________________________
Greg Sullivan, Bozeman City Attorney
DocuSign Envelope ID: C72D3F33-7BBF-4042-98BB-03FD61CCA781
Bozeman Operations Manager
Travis Eickman
---------
----------
EXHIBIT A
DocuSign Envelope ID: C72D3F33-7BBF-4042-98BB-03FD61CCA781
March 17, 2022
City of Bozeman
Attn.: Mike Gray and Max Ziegler
Facilities Superintendent and Facilities Project Coordinator
20 E Olive Street
Bozeman, MT 59715
Re: Swim Center Tier 1 Seismic Evaluation and Initial Roof Truss Assessment and Analysis
Dear Mike and Max:
Thank you for this opportunity to continue assisting the City with the assessment of and long-term
planning for the Swim Center. As requested, the following is our understanding of the scope of
services, fee, assumptions, and limitations associated with performing a Tier 1 Seismic Evaluation
for the building and completing an initial visual structural assessment of the long-span wooden
roof trusses over the natatorium.
Assumptions/Limitations
Our structural engineering fees were based on the following assumptions and limitations:
• Existing drawings and previous condition reports have been provided to MMI.
• MMI will perform a Tier 1 Seismic Evaluation of the Swim Center and prepare a
statement to supplement the evaluation checklist if necessary. We understand ladders or
other means of access necessary to perform the Tier 1 Seismic Evaluation will be
provided by others on site.
• MMI will perform a preliminary structural analysis of the wooden roof trusses spanning
the natatorium using the information currently available to our team. Please note that this
analysis will assume that all members are structurally sound with no failures and will not
take into consideration the current condition of the members. The purpose of this
analysis is to better understand the system behavior and end reactions as well as failure
modes with which the system may be predisposed.
• MMI will perform a non-destructive, limited visual assessment of the long-span wooden
roof trusses over the natatorium. We understand that access will be limited, and, due to
the safety of our personnel as well as access constraints, a thorough, unobstructed
assessment of the full length of the trusses is not possible at this time. Our visual
assessment will be limited to those items which can be observed from the scaffolding on
the pool deck.
• We understand that scaffolding will be provided by others for our use during the
assessment. We understand the ceiling tiles will not be removed prior to our
assessment and that MMI will be responsible for removing ceiling tiles as required to
access the trusses and for re-positioning them following the assessment. MMI will not be
responsible for replacing ceiling tiles that break or are damaged during the process of
removing and repositioning the tiles. The fee below includes budget for these services.
• The truss assessment does not include scope / fee for providing specific options and
recommendations to update the system if required, preparing a cost estimate, nor
DocuSign Envelope ID: C72D3F33-7BBF-4042-98BB-03FD61CCA781
bringing a specialist (i.e., wood scientist or other) to provide a more specialized
investigation of the wood truss chords. These services may be deemed necessary
pending the findings of the assessment. Should these services be deemed necessary
we can amend our scope and fee at that time.
• MMI will develop a report for the City documenting the findings of the Tier 1 Seismic
Evaluation and truss assessment and will provide recommendations for moving forward.
Please note that this initial visual assessment of the roof trusses is intended to serve as
a follow-up to our initial conditional assessment, and that the comprehensiveness of this
visual assessment will be limited by the limited ceiling and scaffold access which is
being provided. Only those portions of the existing framing which are accessible and
viewable will be evaluated for potential damage and deterioration. As a result, we will be
unable to determine with a high level of certainty the overall integrity of the structural roof
system and our conclusions regarding the overall structural adequacy of the roof framing
system and condition of its members will be correspondingly limited. Only after each
roof truss is fully exposed and visually evaluated will we be able to provide a
comprehensive assessment of the structural adequacy of the roof system.
• The anticipated project schedule is as follows:
o Assessments will be completed by mid-April of 2022.
o A draft of the reports documenting our findings will be delivered to the City by
end of April 2022.
Scope of Services and Fee
The following is our understanding of the scope of services:
• Draft and submit the City’s Standard Agreement for approval.
• Tier 1 Seismic Evaluation
o Travel to the Swim Center and perform a Tier 1 Seismic Evaluation of the
building
o Take photographs to document the existing conditions.
o Take relevant measurements of existing members to determine the extent of
their damage / deterioration.
o Take measurements to determine the vertical alignment of walls using a level,
plumb bob, or similar device.
o Complete the Tier 1 Seismic Evaluation checklist and prepare a statement to
supplement the checklist if necessary.
• Analysis and Initial Visual Assessment of Wood Roof Trusses
o Perform analysis and calculations using current building code gravity and lateral
loads to verify the structural stability and strength of the trusses spanning the
natatorium to better understand their behavior and reactions, as well as the
failure modes with which the system may be predisposed.
o Travel to the Swim Center and perform a visual assessment of the roof trusses
from scaffolding supported by the pool deck.
o Take photographs to document the existing conditions.
o Based on the results from the above tasks, prepare a report documenting the
findings of the assessment and provide general recommendations for possible
options for repair (if necessary / possible) and for the next steps moving forward.
DocuSign Envelope ID: C72D3F33-7BBF-4042-98BB-03FD61CCA781
Please note that the scope of services does not include providing specific options
and recommendations to update the system if required.
• Present the Tier 1 Seismic Evaluation and assessment report to City representatives.
For the scope of services outlined above, we have estimated a lump-sum fee of $18,500. We
are agreeable to negotiate additional services if additional scope items are added or found to be
necessary. Once we receive your approval of this proposal, we will proceed with beginning our
work on this project.
Sincerely,
Jay Fischer, PE
Structural Engineer / Project Manager
Rebecca Scheetz, PE
Structural Engineer / Project Engineer
TASK COST
Tier 1 Seismic Evaluation and Reporting $2,750
Analysis of Existing Conditions $2,200
Site Visits for Truss Inspection $4,400
Assessment Report $6,950
Final QA/QC $2,200
Total Cost of Structural Assessment and Cost Estimate: $18,500