HomeMy WebLinkAboutResolution 3240 Approve alternation of contract for Teton Communications, Inc.
..-. -- ..-. -----.-. - -..
COMMISSION RESOLUTION NO. 3240
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF BOZEMAN,
MONTANA, APPROVING ALTERATION/MODIFICATION OF CONTRACT
WITH TETON COMMUNICATIONS, INC.
WHEREAS, the City Commission did, on the 14th day of July 1997, authorize and
approve that certain contract with Teton Communications, Inc., for the purchase and
installation of an E911 Dispatch System; and
WHEREAS, Section 7-5-4308, Montana Code Annotated, provides that any such
alterations or modifications of the specifications and/or plans of the contract be made by
resolution; and
WHEREAS, it has become necessary in the prosecution of the work to make
alterations or modifications to the specifications and/or plans of the contract.
NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of
Bozeman, Montana, that the proposed modifications and/or alterations to the contract
between the City of Bozeman, a municipal corporation, and Teton Communications, Inc., as
contained in Change Orders Nos. 1,3,4,5,6,7,8,10,11,13 and 15, attached hereto,
be and the same are hereby approved; and the City Manager is hereby authorized and
directed to execute the contract change orders for and on behalf of the City; and the Clerk
of the Commission is authorized and directed to attest such signature.
PASSED AND ADOPTED by the City Commission of the City of Bozeman, Montana,
at a regular session thereof held on the 1 st day of June 1998.
~j1?p ~
ALF M. STI~F, Mayor
ATTEST:
(l~J Jdfr~
ROBIN L. SULLIVAN
Clerk of the Commission
APPROVED AS TO FORM:
- --.- ~_.,-_.__..
.
.
I
\
TETON COMMUNICATIONS,
INCORPORATED
PROJECT FIELD CHANGE ORDER
CONTRACT: Gallatin Co. Bozeman FC0*:
1 DATE: 8/4/97
City E911 Division
DESCRIPTION OF MATERIAL AND/OR LABOR CHANGE:
Chang~ Logging Recorder from the Racal brand to the Eventide
brand. This change has no effect on capability,
but is in
compliance with the contract to offer the newest/best technology
as it becomes available.
MATERIAL LIST CHANGE: EQUIPMENT
LABOR
Supply Eventide Logging Recorder ($5,000.00)
-0-
in lieu of the Racal Wordnet ~. ~ t~ f. i> ! T--
-.r
COST TOTAL CHANGES:
($5,000.00) $ -0-
- C 12. t '0 ) 'T--
SCHEDULE IMPACT: None
APPROVALS:
INC.
GALLATIN COUNTY/BOZEMAN CITY
E911 DIVISION REPRESENTATIVE
------ .- -., -..--..-.---
______._...,,_._ ___._._n_____.".n_.".
____._.n._ _. .-.---..
~_. -
I ~ .
.-:-
!
~
TETON COMMUNICATIONS,
I NCORPORRTED
PROJECT FIELD CHRNGE ORDER
Gallatin County/Bozeman City
CONTRACT: E-911 Division FC0": 3
DATE: 9/3/97
DESCRIPTION OF MATERIAL AND/OR LABOR CHANGE:
Add 4 ea "Area" lights to each of the 4 console furniture positions.
MATERIAL LIST CHANGE: EQUIPMENT LABOR
4 ea Watson Furniture
Geneva Talk Lights $1050.00
0
COST TOTAL CHANGES: $
1050.00 $ 0
SCHEDULE IMPACT:
None
APPROVALS:
INC.
GALLATIN COUNTY/BOZEMAN CITY
,
Eql1 DIVISION REPRESENTATIVE
....- ..-...". .....-.--.--- -.-.-
..-.-...-... ---.".--- ... .------.- _n..._..n_.._..._.__
.... .~~._. . -.-.-... .'-.-."" -
..--
.
TETON COMMUNICATIONS, INCORPORATED
PROJECT FIELD CHANGE ORDER
CONTRACT: Gallatin Co/Bozeman City FC0tt: 4
DATE: 9/12/97
E-911 Division
-
DESCRIPTION OF MATERIAL AND/OR LABOR CHANGE:
Delete one Personal Computer.
To be replaced by a computer the county already owns.
- .
MATERIAL LIST CHANGE: EGlUIPMENT LABOR
1 Personal Computer -$1500.00
0
(credit)
COST TOTAL CHANGES: . -1500.00
. 0
(credit)
SCHEDULE IMPACT:
None
APPROVALS:
I
INC. GALLATIN COUNTY/BOZEMAN
CITY I
Eqll DIVISION REPRESENTATIVE
.... -.-...-.-. .-..-'--.
....-.---...
---.---..-.-...--....... .----.-...-....
---....
- ._._~~.
.
TETON COMMUNICATIONS, INCORPORATED
PROJECT FIELD CHANGE ORDER
CONTRACT: Gallatin Co/Bozeman City FC0tt: 5
DATE: 9/12/97
E-911 Division
DESCRIPTION OF MATERIAL AND/OR LABOR CHANGE:
Supply Watson Furniture for the 5th dispatch position to be located
in the Supervisors Office. The Furniture is to be the same
configuration~ style~ and color as the existing positions.
MATERIAL LIST CHANGE: EQUIPMENT LABOR
1 Additional "Basic 5"
Dispatchers Position $15~700.00 Included
COST TOTAL CHANGES: . 15.700.00
. Included
SCHEDULE IMPACT:
Furniture & Radio Console Dilivery now set for October 20~ 1997 through
Ocotber 24~ 1997.
APPROVALS:
I
INC. GALLATIN COUNTY/BOZEMAN CITY
Eq11 DIVISION REPRESENTATIVE
I
.-----
__.._.u_
.--------..--.. ..
-...-..--..-----...--..-----
- ,
TETON COMMUNICATIONS, INCORPORATED
PROJECT FIELD CHANGE ORDER
CONTRACT: Gallatin Co/Bozeman City FC0tt: 6 DATE:
10/01/97
E-911 Division
DESCRIPTION OF MATERIAL AND/OR LABOR CHANGE:
Supply a reconditioned Zetron 640 Paging Terminal in lew of a New 640
Paging Terminal.
MATERIAL LIST CHANGE: EQUIPMENT LABOR
640 (Reconditioned) 2500
None
(Credit)
!
COST TOTAL CHANGES: . 2500 (Credit)
$
SCHEDULE IMPACT:
None
APPROVALS:
INC. GALLATIN COUNTY/BOZEMAN CITY
,E911 DIVISION REPRESENTATIVE
-.--.--
... ,,---""'.. .----.-.- ---.---.-....-
. - . -.....,....-.
".-.11
, ,
T~TON COMMUNICATioNs, tWCORPdRAtED
PROJECT FIELD CHANGE ORDER
I
CONTRACT: Gallatin Co/Bozeman City 'FC0tt= 7
DATE: 10/01/97
E-911 Division
DESCRIPTION OF MATERIAL AND/OR LABOR CHANGE:
Add Signaling Lights at each Operator Position for: Telco off Hook
Radio Transmitt
"Help"
.-
MATERIAL LIST CHANGE: EQUIPMENT
LABOR
1 Lot Signaling Lights
Cables & Switches 600
1125
COST TOTAL CHANGES! $ 600
~ 1125
SCHEDULE IMPACT,
None
APPROVALS:
i
TETON ~MM~C~ INC.
I
GALLATIN COUNTY/BOZEMAN CITY I
REPRESENTATI....E E911 DIVISION REPRESENTAtIVE
...-..--.
.- .~
TETON COMMUNICATIONS, I NCORPORRTED
PROJECT FIELD CHANGE ORDER
CONTRACT: Gallatin Co ./Bozeman City FC0tt: 8
DATE: 10/01/97
E-911 Division
DESCRIPTION OF MATERIAL AND/OR LABOR CHANGE:
Add a cable tray to the equipment room for routing of overhead cables.
MATERIAL LIST CHANGE: EQUIPMENT LABOR
1 Lot Cable Ladder & Fittings 425 75
COST TOTAL CHANGES: $ 425
$ 75
SCHEDULE IMPACT:
None
APPROVALS:
TETON ~7CA~ INC. GALLATIN COUNTY/BOZEMAN CITY
REPRESENTATIVE Eqll DIVISION REPRESENTATIVE
-. --------.-
----- -------
.. -.-.----------- .--'-".. .-.---.'.-'---"-- . ----..----
.
TETON COMMUNICATIONS, INCORPORATED
PROJECT FIELD CHANGE ORDER
CONTRACT: Gallatin Co./Bozeman City FC0tt: 10
DOTE: 2/9/98
E911 Divsion
-
DESCRIPTION OF MATERIAL AND/OR LABOR CHANGE:
Substitute different Headsets and Headset Cables as per the customer
request, and price change.
...'-~
-. - ..-~.. ..~- -~...~. ..
--
MATERIAL LIST CHANGE: EQUIPMENT LABOR
Change from P10 adaptor
20ea to the SRS 1890-15 Headset Cable $30.00 None
10ea Substitute starset for standard
"over the head" Headset. $20.00
None
---
COST TOTAL CHANGESz . 800.00
. None
SCHEDULE IMPACT:
None
APPROVALS:
T INC. GALLATIN COUNTY/BOZEMAN CITY
E911 DIVISION REPRESENTATIVE
.-... ...---..-----
....
.
r
TETON COMMUNICATIONS, INCORPORATED
PROJECT FIELD CHANGE ORDER
CONTRACT: GALLATIN CO/BOZEMAN CITY FC"": 11
DATE: 2/26/98
E-911 DIVISION
DESCRIPTION OF MATERIAL AND/OR LABOR CHANGE:
Add a Cable Tray to the Equipment Room for routing of overhead cables. above
the Intergraph Equipment.
MATERIAL LIST CHANGE: EQUIPMENT LABOR
1 Lot Cable Ladder & Fittings $475.00 $225.00
COST TOTAL CHANGES: . 47').00
$ 225.00
SCHEDULE IMPACT:
NONE
APPROVALS:
TETON COMMUNICATIONS, INC. GALLATIN COUNTY/BOZEMAN CITY
REPRESENTATIVE E911 DIVISION REPRESENTATIVE
.---.---.--., .----- ....---....-...-.-- --.--....----
I --
-...."._'.
TETON COMMUNICATIONS, INCORPORATED
PROJECT FIELD CHANGE ORDER
CONTRACT: GALLATIN CO/BOZEMAN CITY FC0tt:
13 DATE: 2/26/98
E-911 DIVISION
DESCRIPTION OF MATERIAL AND/OR LABOR CHANGE:
Supply and install a new 100 watt, 4 channel Tone ~emote Control Base
Station at High Flat, to replace the old base. TIlis upgrade will eliminate
the need for beep tone to be installed in the new consoles ~nd upgrade
the current old equipment.
MATERIAL LIST CHANGE: EQUIPMENT LABOR
1 Tait T800 100 watt VHF
Base Station.
Complete with:
Lightning Arrestor and Jumper Cables
Test & Repair cables
Cabinet and Service Mic. $9877
. 00 $1725.00
.
COST TOTAL CHANGES: .9877 .00
. 1725 . 00
SCHEDULE IMPACT:
None
APPROVALS:
I
I
TETON COMMUNICATIONS, INC. GALLATIN COUNTY/BOZEMAN CITY
I
REPRESENTATIVE E911 DIVISION
REPRESENTATIVE
... ..-.-.-
. .
TETON COMMUNICATIONS, INCORPORATED
PROJECT FIELD CHANGE ORDER
CONTRACT: GALLATIN CO/BOZEMAN CITY FCQJtt: 15
DATE: 2/27/98
E-911 DIVISION
DESCRIPTION OF MATERIAL AND/OR LABOR CHANGE:
Supply Computer Networking Furniture
.~
.
MATERIAL LIST CHANGE: EQUIPMENT LABOR
1 72" Heavy Duty Law Station Furniture
Complete with:
Casters
AC Power Strips
Wire Management Channel
$170.00
Shipping & Delivery
$2425.00
,
COST TOTAL CHANGES: . 2425.00
. 170.00
SCHEDULE IMPACT:
I
APPROVALS:
cr;~c#~ INC. GALLATIN COUNTY/BOZEMAN CITY
TETON COMMUN CATIONS,
REPRESENTATIVE E911 DIVISION REPRESENTATIVE
I