Commission Memorandum
REPORT TO: Mayor and City Commission
FROM: Susana Montana, Senior Planner, Development Review Division,
Community Development Department
SUBJECT: Eastlake Professional Center Minor Subdivision Preliminary
Plat Modification; Application No. 21447
MEETING DATE: March 1, 2022
AGENDA ITEM TYPE: Action (Quasi-Judicial)
PROJECT LEGAL DESCRIPTION: Lot 1A of the Minor Subdivision 221E, located in Section
26, Township 01 South, Range 05 East, PMM, Bozeman, Montana.
PROJECT SUMMARY: The Preliminary Plat (PP) for this Eastlake Professional Center
Subsequent Minor Subdivision was approved on August 10, 2021 by a Findings of Fact and
Order signature by Mayor Andrus. This application is a modification to that previously-
approved PP to allow the Applicant to request concurrent construction of public and private
infrastructure for the subdivision--concurrent with the construction of a first phase medical
office building for Lot 4.
The subdivision divides the 7.65 acres parcel into four commercially-zoned lots. The
property is zoned B-2M, Community Business District - Mixed.
DEVELOPMENT REVIEW COMMITTEE (DRC) RECOMMENDATION: The January 7, 2022
revised application materials to the November 29, 2021 initial application conforms to
standards and is sufficient for approval with conditions and code provisions.
STRATEGIC PLAN: Vision Statement: 4. A Well-Planned City. We consistently improve our
community’s quality of life as it grows and changes, honoring our sense of place and the
‘Bozeman feel’ as we plan for a livable, affordable, more connected city.
4.2 High Quality Urban Approach. Continue to support high quality planning, ranging from
building design to neighborhood layouts, while pursuing urban approaches to issues such as
multimodal transportation, infill, density, connected trails and parks, and walkable
neighborhoods.
4.3 Strategic Infrastructure Choices. Prioritize long-term investment and maintenance for
existing and new infrastructure.
Page 2 of 3
Commission Memorandum
BACKGROUND: Subsequent to the August 2021 approval of the PP, the Applicant discovered
that he needed to request concurrent construction of public and private infrastructure for
this subdivision. The Bozeman Municipal Code (BMC) Section 38.270.030.B.1.a, Completion
of Improvements, requires all improvements to subdivisions to be completed and approved
by the City before any building permit for any lot within the subdivision can be issued. The
exception to this rule is when the Applicant requests concurrent construction of
infrastructure improvements at the initial application for the subdivision—at preliminary
plat application. The Applicant for this subdivision did not request concurrent construction
or submit an Improvements Agreement request at the initial submittal of the PP. This
Modification to the previously approved PP represents the proper route for submittal of the
Concurrent Construction request, pursuant to 38.270.030.D Exception for Concurrent
construction, and allows the Applicant to request to enter into an Improvements Agreement
(IA) for those improvements, pursuant to 38.270.030.B.1.b.2.
The PP map remains the same as was approved in August 2021. Since that time, however,
some of the original conditions of approval and BMC code provisions have been met by the
Applicant and are no longer listed in the PP recommended conditions and code provisions.
Remaining unmet conditions and code provisions from the August 2021 PP approval are
carried forward to this PP. This Modification to the PP would add six new BMC code
provisions that must be met with the Final Plat. These code provisions would allow the
Applicant to submit an Improvements Agreement and Financial Surety documents to assure
that roads, water and sewer lines, stormwater ponds, landscaping in public rights-of-way
and other improvements for the subdivision would be completed, inspected and accepted by
the City prior to issuance of any certificate of occupancy for any building within the
subdivision. Importantly, it would allow the Applicant to submit building permits for the
medical office building on Lot 4 and, when approved, to construct the building and site
improvements concurrently with the construction of private and public infrastructure for
the subdivision.
Public notice of this Preliminary Plat Modification was given on February 4th through the
25th, 2022 by posting of the property, by first class mail notice to adjacent property owners,
by certified mail notice to owners of property contiguous to the subdivision, by certified mail
to persons under contract to purchase land within the subdivision and to the Applicant, and
by newspaper legal ad notice on Sunday February 6th and 13th. No written public comment
has been received to date.
The final decision for a second subsequent minor subdivision Preliminary Plat with less than
50 lots must be made within 60 working days of the date it was deemed adequate by the
Development Review Committee (DRC). The DRC deemed the application adequate for
continued review on January 7, 2022. Pursuant to BMC 38.240.130 the City Commission shall
approve, conditionally approve or deny the subdivision application by April 4, 2022, unless
Page 3 of 3
Commission Memorandum
there is a written extension from the developer, not to exceed one year. The March 1, 2022
hearing on this application meets that deadline.
UNRESOLVED ISSUES: There are no unresolved issues for this subdivision at this
Preliminary Plat stage. The final plat must satisfy all of the recommended preliminary plat
conditions of approval and all relevant Bozeman Municipal Code (BMC) code provisions
noted in the attached staff report.
ALTERNATIVES:
1. Approve the application with the recommended conditions;
2. Approve the application with clarifications/corrections or minor modifications to the
staff-recommended conditions;
3. Deny the application based on the Commission’s findings of non-compliance with the
applicable criteria contained within the staff report; or
4. Open and continue the public hearing on the application to a later date, with specific
direction to staff or the Applicant to supply additional information or to address
specific items. This alternative is requested if the City Commission wishes to amend
or add conditions of approval.
FISCAL EFFECTS: Fiscal impacts are undetermined at this time, but will include increased
property tax revenues from new development, along with increased costs to deliver
municipal services to the property. Impact fees will be collected at the time of issuance of
building permits for individual developments along with City sewer and water connection
fees.
Attachments:
Staff Report
Applicant Narrative Application
Preliminary Plat MOD Map Sheets
Master Site Plan green plan
Master Site Plan phasing plan
Report compiled on: February 14, 2022