HomeMy WebLinkAbout21447 Applicant PP MOD NarrativeEASTLAKE PROFESSIONAL CENTER Preliminary Plat
Mod Narrative
November 2021
2 November 2021
Preliminary Plat MOD: Eastlake Professional Center
Table of Contents
1. Application Forms & Checklists
(Applications included - A1 Development Review, PP Subdivision Preliminary Plat, & N1 Noticing Checklist)
2. Project Team
3. Narrative
I. Project Overview
II. Project Details
III. Phasing Timelines
IV. Concurrent Construction Request
V. Modification to the Preliminary Plat Conditions of Approval
4. Appendices
Appendix A: Green Plan
Appendix B: Preliminary Plat
Appendix C: Phasing Plan
Appendix D: Release of Easement
Appendix E: Draft SID Waivers
Appendix F: Response to Conditions of Approval
Appendix G: Preliminary Plat Findings of Fact (21-016)
Appendix H: Weed Management Plan
Appendix I: Discharge Permit
Appendix J: SWPPP Confirmation
5. Plan Set
Civil
Preliminary Plat
Master Utility Plan
Site Survey
3 November 2021
Preliminary Plat MOD: Eastlake Professional Center
1. Application Forms & Fees
The required A1, PP, & N1 forms for the Eastlake Professional Center Subdivision
Preliminary Plat Application have been included in the application materials. The
calculated fee total is outlined below.
COMPONENT FEE QUANTITY TOTAL
PP Base Fee (Minor Subdivision) $2,459 1 $2,459.00
Additional fee per lot subject to Site
Plan Review
$40 4 $160.00
TOTAL $ 2,619.00
4 November 2021
Preliminary Plat MOD: Eastlake Professional Center
2. Project Team
OWNER Eastlake Professional Center LLC
Attn: Randy Scully
randy@scullywestproperties.com
5073 Patterson Road
Bozeman, MT 59718
p. 914.450.8803
APPLICANT ScullyWest Properties, LLC
Attn: Randy Scully
randy@scullywestproperties.com
5073 Patterson Road
Bozeman, MT 59718
p. 914.450.8803
PROJECT CONSULTANTS
Planning Intrinsik Architecture, Inc.
Attn: Tyler Steinway
tsteinway@intrinsikarchitecture.com
111 North Tracy Avenue,
Bozeman, MT 59715
p. 406.582.8988
Civil Engineering TD&H Engineering
Attn: Alex Edwards
Alex.Edwards@tdhengineering.com
234 East Babcock Street, Suite 3
Bozeman, MT 59715
p. 406.586.0277
Landscape Architect Design 5
Attn: Nate Beck
Nate@Design5la.com
37 East Main Street, Suite 10
Bozeman, MT 59715
p. 406.587.4873
5 November 2021
Preliminary Plat MOD: Eastlake Professional Center
3. Narrative
Executive Summary
We are submitting a material modification to our approved preliminary plat application
to allow us to enter into an improvements agreement for the outstanding road
improvements as allowed under UDC Section 38.270.030.B.1.b.2. Completion of
Improvements. This request is coupled with a Concurrent Construction request to begin
construction on the Medical Eye Specialist Clinic on Lot 4 prior to the completion of
these remaining street improvements. This request to financially guarantee and request
concurrent construction was not available when we initially submitted our preliminary
plat and thus results in a material modification to the plat, which requires re -review by
the City Commission. For more information on our concurrent construction request
please see Section IV.
I. Project Overview
The Subdivision Preliminary Plat to subdivide 7.65 acres (333,321 SF) of undeveloped
land into four (4) commercial lots was approved on June 8,2021. Subsequently, a site
plan was submitted (currently on public notice) for a Medical Eye Clinic located on lot 4.
6 November 2021
Preliminary Plat MOD: Eastlake Professional Center
Due to unforeseen circumstances and timing, it became apparent that all of the
necessary subdivision improvements weren't able to be completed prior to the asphalt
plant closing, which will ultimately results in a significant time delay in the start of
construction for the important Medical Eye Specialists clinic. It is our intent to
financially guarantee all remaining street improvements to allow the concurrent
construction request to be granted. Because this item was not requested in our original
preliminary plat application it constitutes a material modification to a plat, which
ultimately requires a new
decision by the review
authority.
II. Project Details
Please refer to Appendix G
for all relevant information
on the previously approved
preliminary plat.
III. Phasing Timelines
This project is proposed to
be constructed in five (5)
phases. Phase 1 is to be the
first phase constructed.
While Phases 2 - 5 are
numbered numerically, and
subsequently to Phase 1,
phases are not necessarily
intended to be constructed
in their numerical order. It
is the applicants intention
that Phases 1 - 5 may be
constructed concurrently or
independently of one
another.
Please see Appendix C for
an updated phasing plan providing additional details on the extent of each proposed
phase. The applicant is seeking to financially guarantee the remaining on site road
improvements in Phase 1. The future phasing expectations will be further developed in
the subsequent Final Plat submittal.
IV. Concurrent Construction Request
1. The city will have an opportunity to review and approve future proposed
7 November 2021
Preliminary Plat MOD: Eastlake Professional Center
development through a site plan review or planned unit development;
Response: Understood. A site plan application for the Medical Eye Specialists is
currently on public notice and a building permit application has been
submitted. It is understood that all future development/sites will be required
to go through the site plan review process.
2. The property owner must enter into an improvements agreement to ensure the
installation of required infrastructure and other applicable improvements, to be
secured by any security or securities found in section 38.270.080. If a financial security
is used, the amount will be determined by the city and in an amount not less than 150
percent of the cost of the improvements verified against city publicly bid unit prices,
where such are available. If no publicly bid unit prices are available, any cost estimate
acceptable to the city may be used. The security must be in the name of the city and
must be at least six months longer than the time of performance required by the
improvements agreement;
Response: The property owner is prepared to enter into an improvement ’s
agreement with financial security for 150% of the cost of improvements
acceptable to the City. The security will be made in the name of the City and
extend a minimum of 6 months beyond the anticipated completion date.
3. Improvements must be complete within two years of the date of the improvements
agreement;
Response: Public infrastructure improvements are anticipated to be complete
by June of 2022.
4. Approval of the final engineering design, including location and grade, for any public
infrastructure must be obtained from the engineering department, and the Montana
Department of Environmental Quality when applicable, prior to issuance of any
building permit for the development;
Response: Infrastructure approval has been granted by the City of Bozeman,
and DEQ review is underway. We anticipate DEQ approval will be granted very
soon.
5. Building permits may be issued incrementally, dependent upon the status of
installation of the infrastructure improvements. All building construction within the
development must cease until required phases of infrastructure improvements as
described in the improvements agreement have been completed, and inspected and
accepted by the city;
Response: Incremental phases as deemed necessary by the City are
acknowledged and building construction will be phased in accordance with the
improvements agreement.
6. The developer must provide and maintain hazard and commercial general liability
insurance. Insurance policies must not be cancelled without at least 45 days prior
notice to the city. The commercial general liability policy must name the city as an
8 November 2021
Preliminary Plat MOD: Eastlake Professional Center
additional insured. The developer must furnish evidence, satisfactory to the city, of all
such policies and the effective dates thereof;
Response: The developer will provide the required insurance and name the City
as additional insured.
7. The developer must recognize, acknowledge and assume the increased risk of loss
because certain public services do not exist at the site;
Response: The developer acknowledges this risk.
8. If public funds or other third party funding will be used to fund all or part of the
installation of infrastructure, the improvements agreement between the developer and
the city must identify the type or types of predetermined infrastructure funding. Public
or third party funding may include, but is not limited to reimbursement, payment up
front, creation of a special improvements district, or grants;
Response: No public funds are anticipated for this project.
9. No occupancy of any structures or commencement of any use constructed or
proposed within the boundaries of the development will be allowed until required
infrastructure improvements have been completed, inspected, and accepted by the city,
and a certificate of occupancy has been issued;
a. No occupancy of structures or commencement of any use is allowed when such action
would constitute a safety hazard in the opinion of the city;
Response: The applicant understands that all necessary improvements must be
completed and reviewed by the City prior to a Certificate of Occupancy being
issued for the development.
10. The developer must enter into an agreement with the city to address the provision
of any services on an interim basis during construction, if deemed appropriate;
Response: If deemed appropriate by the City, the applicant is willing to enter
into an agreement with the City to address provision of services.
11. The developer must execute a hold harmless and indemnification agreement
indemnifying, defending and holding harmless the city, its employees, agents and
assigns from and against any and all liabilities, loss, claims, causes of action, judgments
and damages resulting from or arising out of the issuance of a building permit under
this section;
Response: The applicant is aware of the risks associated with the concurrent
build process, and is willing to hold harmless the City against any and all
liabilities.
12. The developer must pay for any extraordinary costs associated with the project
which the city may identify, including, but not limited to, additional staff hours to
oversee the planning, engineering and construction of the project and infrastructure
improvements, inspection of the infrastructure improvements and any extraordinary
administrative costs;
9 November 2021
Preliminary Plat MOD: Eastlake Professional Center
Response: Extraordinary costs are not anticipated for this project; however, the
developer agrees to cover costs if additional staff hours are deemed necessary
for inspection and project oversight.
13. The development must be under the control of a single developer and all work must
be under the supervision of a single general contractor. The developer and general
contractor must agree that there must be no third-party builders until required
infrastructure improvements have been completed, and inspected and accepted by the
city; and
Response: The development is under the control of a single developer, who will
maintain control of the project until all required infrastructure improvements
are complete, inspected, and accepted by the City. One general contractor will
supervise all work conducted on site.
14. Subsequent to preliminary plat or plan approval, a concurrent construction plan,
addressing all requirements of this section, must be submitted for review and approval
of the community development director in consultation with the city engineer and with
a recommendation from the development review committee.
Response: Acknowledged. A concurrent construction plan will be provided
subsequent to preliminary plat approval.
V. Response to the Conditions of approval
Please see Appendix E for response to the preliminary plat conditions of
approval.