January 21, 2022
James Nickelson
PO Box 1113
Bozeman, MT 59771
RE: MSU AES BART Farm Water Service Building MOD, 21450
Dear applicant,
The Bozeman Department of Community Development is pleased to award approval of your modification
application for the project referenced above. The application requests approval for minor modifications to:
- Construct a utility building
Staff reviewed your application materials to ensure the proposal maintains the underlying continuity with the
approved site plan located at S14, T02 S, R05 E, C.O.S. 2729, Acres 41.173, East Por. Tract A in SD7C-08
(RGG62456 in SD 7R-41) and the requirements of the Unified Development Code. Following review, Staff
forwarded a recommendation to the Community Development Director who is responsible for the final decision.
Pursuant to section 38.230.150, BMC, amendments to approved plans must be reviewed and may be approved
by the community development director upon determining that the amended plan is in substantial compliance
with the originally approved plan.
Please be aware that as the applicant you must comply with all provisions of Chapter 38 of the Bozeman
Municipal Code that are applicable to this project, including but not limited to the following:
Code Provisions
Per Section 38.100.080 & 38.200.110, the proposed project shall be completed as approved and in this
application. Any modifications to the submitted and approved application materials shall invalidate the
project's legitimacy, unless the applicant submits the proposed modifications for review and approval
by the Department of Community Development prior to undertaking said modifications. The only
exception to this law is repair.
You have the right to appeal this decision of the Community Development Director pursuant to the provisions
of the Bozeman Municipal Code. Please note that this decision is subject to appeal by other aggrieved parties as
defined by Sec. 38.700.020 of the Bozeman Municipal Code. Such appeals must be filed pursuant to the
provisions of Sec. 38.250.030 of the Bozeman Municipal Code. An appeal must be filed within 10 working days
following the date of this decision. If a valid appeal is filed, no further action on the project may proceed until a
decision on the appeal is made by the City Commission, and the Community Development Department and
Building Division will not be able to approve any building permits or to perform any inspections related to this
application.
If you have any more questions, or if the Community Development Department can be of further assistance,
please do not hesitate to contact me at cmorrison@bozeman.net.
For office use only
DATE OF FINAL DECISION ______________________________