HomeMy WebLinkAboutVillage Downtown Lot 5 Narrative 04-16-2021
PALISADE AT 130 VILLAGE CROSSING WAY
MODIFICATION NARRATIVE
RC#1 (21-076)
Palisade at 130 Village Crossing Way
MOD Application – RC#1 (21-073)
April 2021
Page 2 of 17
Table of Contents
Updated documents in blue.
NARRATIVE
I. MOD Application Information
II. Response to Plan Modification/Amendment Checklist
III. Deviation Criteria
IV. Response to City Comments
APPENDICES
Appendix A: Vicinity Map
Appendix B: Zoning Map
Appendix C: Previously Approved Plans
Appendix D: Stormwater Design Report
Appendix E: Sanitary Sewer
Appendix F: Water & Mechanical Details
Appendix G: Village Boulevard Subdivision Final Plat
Appendix H: Wetlands Report
Appendix I: Draft Waiver of SID
Appendix J: CILWR Calculations
PLANS:
ARCHITECTURE
COVER SHEET
A0.00 PROJECT MATRIX AND PERSPECTIVES
A0.01 PERSPECTIVES
A0.10 ARCH SITE PLAN
A2.00 LEVEL 0 GARAGE PLAN
A2.01 ENLARGED PLANS AND DETAILS
A2.02 LEVEL 1 FLOOR PLAN
A2.03 LEVEL 2 FLOOR PLAN
A2.04 LEVEL 3 FLOOR PLAN
Palisade at 130 Village Crossing Way
MOD Application – RC#1 (21-073)
April 2021
Page 3 of 17
A3.00 EXTERIOR ELEVATIONS
A3.01 EXTERIOR ELEVATIONS
A4.00 MATERIALS / PRODUCT DATA
CIVIL
C1.0 COVER SHEET
C2.0 CIVL SITE PLAN
C3.0 CIVIL UTILITY PLAN
C4.0 SITE GRADING & DRAINAGE PLAN
C5.0 CIVIL DETAILS
C5.1 CIVIL DETAILS
C5.2 CIVIL DETAILS
EXISTING CONDITIONS SURVEY
ELECTRICAL
ES1.0 GARAGE SITE PLAN
ES1.1 MAIN LEVEL SITE PLAN
ES1.2 PHOTOMETRIC SITE PLAN
ES1.3 ELEVATION PHOTOMETRICS
ES1.4 LIGHTING CUT SHEETS
ES1.5 LIGHTING CUT SHEET
LANDSCAPE
L 000 SITE PLAN
L 003 OVERALL LANDSCAPE PLAN
L 200 NOTES AND SCHEDULES
L 300 ROOF DECK HARDSCAPE PLAN
L 301 LANDSCAPE PLAN ENLARGEMENT
L 302 LANDSCAPE PLAN ENLARGEMENT
L 500 LANDSCAPE DETAILS
L 501 LANDSCAPE DETAILS
L 502 IRRIGATION PLAN
L 700 IRRIGATION DETAILS
L 701 IRRIGATION DETAILS
Palisade at 130 Village Crossing Way
MOD Application – RC#1 (21-073)
April 2021
Page 4 of 17
Palisade at 130 Village Crossing Way
MOD Application – RC#1 (21-073)
April 2021
Page 5 of 17
View of Project Site facing Northwest
1. MOD Application Information – RC#1
This RC is submitted in response to City Comments provided for File #21-073. The narrative
below remains largely unchanged from the Modification submittal; however, the applicant
has responded to these comments within the pages that follow.
APPLICANT Northeast Bozeman Venture, LLC
503 South Willson Avenue
Bozeman, MT 59715
p. 949-842-4499
Palisade at 130 Village Crossing Way
MOD Application – RC#1 (21-073)
April 2021
Page 6 of 17
PROJECT CONSULTANTS:
ARCHITECT SMA Architects
109 E. Oak Street, Suite 2E
Bozeman, MT 59715
ENGINEER C&H Engineering and Surveying, Inc.
1091 Stoneridge Drive
Bozeman, MT 59718
PLANNING Intrinsik Architecture, Inc.
111 N. Tracy Avenue,
Bozeman, MT 59715
p. 406.582.8988
LANDSCAPE
ARCHITECT Design 5
37 E. Main Street
Bozeman, MT 59715
p: 406.587.4873
Palisade at 130 Village Crossing Way
MOD Application – RC#1 (21-073)
April 2021
Page 7 of 17
2. Response to Plan Modification/Amendment Checklist
1. Plan Modification/Amendment Checklist:
Project narrative providing a thorough description of what is being proposed including a list
of all alterations/changes proposed to the plan.
The applicant is proposing to modify the approved Site Plan application for this site through
this application (See Response #2 for additional project history). The Applicant is proposing
to construct a four-story, 92-unit residential condominium apartment building (unit
breakdown on Sheet A0.00) on Lot 5 within the Village Downtown Subdivision and Planned
Unit Development. The Architectural Plans portray the applicant’s vision for a building
suited for the neighborhood, and designed with thoughtfulness of the residents who will
call it home. This includes proposing a shorter building than is currently approved with a
smaller footprint, less impervious surface, additional onsite amenities, and no intrusion into
watercourse setbacks or wetlands.
As the project represents a new layout and design from the site plan approved with the
PUD in 2005, this project represents an improved site development vision from that
approved plan, and therefore the list of all changes includes all components of the
previously approved project design. The narrative below outlines the vision for this
development as well as provides context on previous approvals. The previously approved
plans have been included as Appendix C for reference.
Lot 5 lies within the Broadway Boulevard Minor Subdivision No. 344 created in 2004
(Appendix G), and the property is addressed as 130 Village Crossing Way. The parcel lies
within S07, T02 S, R06 E, P.M.M., Gallatin County, Montana. The project site is 3.408 acres
in size and is currently undeveloped. Lot 5 is zoned R-4 (Medium-density Residential), and
lies within the Urban Neighborhood Growth Policy/Future Land Use Map (FLUM)
designation area.
This intent of this infill project is to develop Lot 5 by modifying the approved Site Plan to
conform to expectations established by the previously authorized Site Plan Extension (05-
101) and Modification (20-172) applications (additional details below). Deliberate attention
has gone into the site design to allow for all site development work to avoid sensitive areas,
wetlands, and watercourse setbacks located on or adjacent to the project site (see also
Appendix H). The proposed residential condominium apartment building is the same use as
what was previously approved in 2005. Furthermore, the changes proposed for the site
Palisade at 130 Village Crossing Way
MOD Application – RC#1 (21-073)
April 2021
Page 8 of 17
decrease the lot coverage by impervious surfaces by approximately five percent (5%). The
City approval in Summer 2020 of the Minor PUD Modification (20-172) increased total
number of units approved for the site by less than five percent (5%); however, the parking
requirements for the project and the traffic impacts have not changed from the original
PUD approval (i.e. 122 parking spaces are proposed with this project). The Site remains
undeveloped and the development is not proposing to continue any unsafe or hazardous
conditions through the development of this project.
While the UDC has undergone several updates since the initial Site Plan approval, the
project is prepared the meet the current standards save for those related to the
transparency requirements for northern aspect of the underground parking structure,
standards that were not established at the time of the original Site Plan approval. This
expectation was discussed during the Concept Plan submittal and the City was amenable to
this project not being subject to that standard.
2. Project file number associate with plan to be modified.
File #05-101. Additional details on the previous approvals and conditions of these approvals
was included in the Concept application (File #20-393). Please reference that submittal for
complete details on the history of this project. Project history of relevance has been
included herein.
In 2005, the following relaxations were approved for the Village Lofts PUD (current UDC
Section numbers shown in brackets) and remain impactful on the current proposal:
1. Section 18.16.050, Yards [now Sec. 38.320.030.C] to encroach three (3) feet into the 5-
foot side yard setback along the northern property line (adjacent to the railroad right-
of-way);
2. File No. 20-172 additions are underlined] Section 18.16.060, Building Height [now Sec.
38.320.030.C] to increase the maximum building height in the underlying R-4 zoning
district for a building with a roof pitch of less than 3:12, from 34 feet to 75-feet for the
undeveloped areas of Lot 5; and for other lands within the R-4 zone of the PUD;
3. Section 18.42.170.A, Trash and Garbage Enclosures [now 38.520.070.] are allowed to be
located in the required front yard;
4. Section 18.44.060.D, Level of Service Standards [now 38.400.060.B.4] to allow the East
Main Street and North Broadway Avenue intersection to operate at a level of service
less than “D”;
5. Section 18.44.090.C.2.b, Drive Access Requirements [now 38.400.090] to increase the
maximum commercial drive access width from 35-feet to 46.5-feet; and
Palisade at 130 Village Crossing Way
MOD Application – RC#1 (21-073)
April 2021
Page 9 of 17
6. Section 18.46.040, Number of Parking Spaces Required [now 38.540.050] to decrease
the minimum number of required off-street parking spaces from 164 per lot to 122 per
lot, a 26% reduction.
The Final Site Plan for Lot 5 has also received extensions as follows (additional details on the
2020 Extension are included below):
• 2007 - Two (2) administrative extensions, issued by the Planning Director, granted
for six (6)months each.
• June, 2008 - City Commission approval of an additional two (2) year extension,
expiration May 3, 2010 (File No. Z-04265).
• March 22, 2010 - City Commission approval of a five (5) year extension, expiration
May 3, 2015 (File No. Z-04265A).
• February 9, 2015 - City Commission approval of a five (5) year extension, expiration
May 3, 2020 (File No. Z-14390).
• March 4, 2020 - Administrative extension issued by the Planning Director, expiration
May 3, 2021 (File No. 05-101)
2020 Site Plan Extension (File No. 05-101)
A one-year extension was administratively granted by City of Bozeman Staff on March 4,
2020. As was discussed in that approval, the current application is being submitted with a
Concurrent Extension request to allow for two-year window for Building Permit approval.
This Modification is in conformance with the current UDC requirements for weather
protection (Sec. 38.510.030.C), façade modulation (Sec. 38.530.040.E), bike parking (Sec.
38.540.050.A.5), and blank building end walls (Sec. 38.530.070). Additional changes to the
UDC since the original approval were addressed in the Conceptual application (File #20-393)
and City Staff did raise additional concerns during that review.
2020 PUD Modification (File No. 05-101)
The City of Bozeman Staff approved a minor amendment to the Planned Unit Development
on August 24, 2020. This approval, as related to this project, authorized the 92 total units as
is proposed through this Modification application. No additional changes to the approved
plans for Lot 5 were approved with this 2020 submittal, and the conditions of that approval
have been met. No further requirements associated with that approval were identified by
City staff during the Concept review.
3. Site plan of existing conditions with north arrow, property dimensions, setbacks,
existing easements, access points, vehicular and pedestrian circulation, buildings, natural
features and topography.
The existing conditions plan has been included as Civil Site Survey plan.
Palisade at 130 Village Crossing Way
MOD Application – RC#1 (21-073)
April 2021
Page 10 of 17
4. Site plan of proposed changes with north arrow, property dimensions, location of
buildings, parking, driveways/access points, landscaping, setbacks, easement locations,
vehicular and pedestrian circulation, natural features and topography.
Proposed changes noted on Civil Site Plan Sheet C1.0-C5.2 and the Architectural Site Plan
A0.10.
5. Front, rear and side elevations of all buildings, structures, fences and walls with height
dimensions and roof pitches if new construction or changes to elevations are proposed.
Show existing and proposed changes.
The previously approved elevations have been included as Appendix C, while the proposed
elevations are noted on sheets A3.00 and A3.01. Levels and roof pitch are also noted in
these sheets.
6. Building elevations shall include proposed exterior building materials, windows and
doors including a color and building material palette for all proposed features keyed to
the building elevations if material changes are proposed.
The proposed exterior building materials and façade treatments are detailed on
Architecture Plan Sheets A3.00 and A3.01. All proposed materials, window manufacturer,
sliding door, and lighting cutout sheets are shown on A4.00.
7. For minor changes, include pictures, specifications and other information that will
clearly express the proposed changes or alterations to the approved plan.
This item is not applicable to this project.
8. Cutsheets for proposed windows, doors, exterior lighting or other detailed
modifications if building elevations are not detailed enough to depict features accurately.
All proposed materials, window manufacturer, sliding doors, and lighting cut sheets are
shown on A4.00.
9. Floor plans showing floor layout including square footage and proposed use for each
room and area. Suggested scale is 1/4:1 foot.
The floor plans have been included as Architectural Drawings A2.00 - A2.04. The scale
appropriate for this project has been included in these sheets.
10. Parking plan and calculations for all uses if proposed changes to the approved plan
require review of parking requirements.
The parking is set by the effective PUD for this site, which requires 122 parking spaces for
this project as shown on the Architectural Plans. No changes to the PUD approved parking
Palisade at 130 Village Crossing Way
MOD Application – RC#1 (21-073)
April 2021
Page 11 of 17
are requested, and 122 onsite parking spaces have been included for this project split
between surface and structured parking as shown on the proposed plans.
11. Photometric plan, exterior lighting cutsheets and specification if proposed
modification to approved lighting plans.
The photometric plan has been included on Sheets ES1.0 - ES1.3. Lighting cutsheets are
shown on ES1.4 and ES1.5.
12. Landscape plan if proposed modification to approved landscaping.
The Landscape Plans have been included in this submittal. The previously approved
Landscaping plans are included as Appendix C.3.
13. Other information as applicable to assist the City in a decision on the proposed
modification.
Response to the City’s Concept review comments have been included below.
Palisade at 130 Village Crossing Way
MOD Application – RC#1 (21-073)
April 2021
Page 12 of 17
RESPONSE TO CITY COMMENTS
Replying to the DRC comments provided by City Staff on March 24, 2021, the following responses are
included in this RC submittal. The Table of Contents also provides additional direction to relevant
response materials.
No. Comment Review Entity Response/Comments
1 The applicant is advised that unmet code provisions,
or code provisions that are not specifically listed as
conditions of approval, does not, in any way, create
a waiver or other relaxation of the lawful
requirements of the Bozeman Municipal Code or
state law.
Conditions of
Approval
Understood.
1 2018 IECC Code required Building
Division
Understood.
2 A1147.1-2009 Accessible and IBC Code for Type A
and Type B requirements
Building
Division
Understood.
3 Egress issues in the garage on the north east stair
well exiting into a non-rated hallway. Appears to be
open to garage on the south west corner of the
Stairwell
Building
Division
Understood, will be addressed
at Building Permit.
4 South west stairs require gate at first floor to prevent
occupants to egress out the first floor and not the
garage.
Building
Division
Understood, will be addressed
at Building Permit.
1 Landscape design plan indicating the total
landscaped area (ft2) and landscaped area of each
hydrozone (ft2) - designated by grouping plants with
similar water needs.
Water
Conservation
Division
Addressed within the updated
Landscape Plans.
2 Reduce the use of Kentucky bluegrass within areas
surrounded by pavement and/or parking spaces and
install native seed mix and/or drought tolerant
plants/shrubs in these areas.
Water
Conservation
Division
Addressed within the updated
Landscape Plans.
3 Install an adaptor to the irrigation controller (12C-
800-PL) that will give it Wi-Fi capabilities and remote
scheduling access. This additional device will make
the irrigation controller a ‘smart’ weather-based
irrigation controller that will have automatic
scheduling adjustment capabilities corresponding to
changes in local weather conditions.
Water
Conservation
Division
Addressed in the updated
Landscape Plans.
Palisade at 130 Village Crossing Way
MOD Application – RC#1 (21-073)
April 2021
Page 13 of 17
4 Please specify the proper installation and
adjustment of overhead irrigation (rotors and
sprays) to minimize overthrow onto the pavement
within each zone.
Water
Conservation
Division
Correction shown on updated
Landscape Plans.
5 Multi-spray, multi-trajectory (rotary) nozzles can
reduce water loss from evaporation and wind drift
by up to 50%. Specify the installation of water
efficient sprinkler nozzles (multi-spray, multi-
trajectory nozzles or ‘rotary nozzles’) if overhead
irrigation is to be used within turf grass lawn areas.
To save money and water - check out the City’s
sprinkler nozzle rebates for new construction!
Water
Conservation
Division
Understood.
1 See comments from 9-30-2020 DRC comments.
Following are updated comments that may not have
been in the previous comments.
NWE All previous and current
comments have been
addressed.
2 When there are multiple units with multiple meters
NWE requires that the meters have a permanent
placard for each meter. For multiple metering each
location or premise must have its address and unit
numbers permanently attached by means of a
placard to the meter bases and the individual
apartment/unit breaker boxes before the meter is
set. These identifying placards must match the unit
information as displayed on the unit’s entry door.
NWE Understood.
3 Applicant is using a screening wall to screen the
meters. Following are some items that need to be
met before NWE can install the needed services.
NWE Understood.
4 Screening Walls.
a. Screening must meet the clear zone
requirement of NWE Electric Service
Requirements which typically for
commercial application is 48” from the
face of the electric meter to the screening
wall.
b. Gas meter cannot be located in recessed
location where it is not open atmosphere
above the meter without approval from
NWE.
c. Screening cannot consist of rolling doors or
other devices that are required to be open
to access the meters.
NWE Plans demonstrate
compliance with standards.
5 With the latest response and drawings submitted
from the applicant there doesn’t seem to be any
concerns with NWE providing the needed utilities to
the proposed meter location. Continue to work
with NWE project engineer Kory Graham on gas and
electric utilities. To save money and water - check
NWE Understood.
Palisade at 130 Village Crossing Way
MOD Application – RC#1 (21-073)
April 2021
Page 14 of 17
out the City’s sprinkler nozzle rebates for new
construction!
1 Per previous conversations with project engineer
and verified at today’s DRC meeting, the exterior
South end surface parking lot seems to not have
retained the internal circulation thus making an over
150 foot dead end, requiring a turnaround for
emergency apparatus. Overall the widths of road are
acceptable but internal looping would be required.
Probably requiring the elimination of West end
parking spots to loop the access.
Fire
Department
During a meeting between the
design team and Scott Mueller
on April 2, 2021 it was
determined that this
comment would be removed.
We are providing a 26’ wide
access lane from the Right of
Way to the back (east end) of
the parking lot. We have also
added fire lane curb paint and
signage to Sheet C2.0 to the
north-south drive aisle.
1 Building management will be responsible for moving
refuse container to the heated tip pad.
Solid Waste Understood.
1 BMC 38.410.080- The applicant must demonstrate
how drainage is addressed for the entire lot
in the drainage report.
Stormwater See updated Stormwater
management design report
(Appendix D).
2 BMC 38.410.080- The applicant must include the
area of the stormwater basins in the drainage
calculations.
Stormwater
See updated Stormwater
Management design report
(Appendix D).
3 BMC 38.410.080- The applicant must demonstrate
that maintenance adequate access is
provided for equipment maintaining the stormwater
facilities. A clear maintenance access is not shown
for the Stormtech facility.
Stormwater
See Appendix C of updated
Stormwater management
design report (Appendix D).
Also, see updated civil Sheet
C4.0 for the new
access/maintenance manhole
with 24” sump which has been
moved inside the parking
garage to allow for a trailer-
mounted vac assembly to
perform maintenance. Said
maintenance will require
coordination with building
management to ensure
parked cars along the east wall
of the garage are moved prior
to the scheduled day of
maintenance.
Palisade at 130 Village Crossing Way
MOD Application – RC#1 (21-073)
April 2021
Page 15 of 17
4 BMC 38.410.080- The seasonal high groundwater
elevation must be determined and the
engineer responsible for the design drainage must
certify that the proposed infrastructure can
meet or exceed the City’s drainage requirements
during the seasonal high groundwater.
Stormwater
Based on conversation with
Cody Flammond on April 6,
2021, approval of the design
can occur without
groundwater monitoring. See
stormwater management
design report. An assumption
has been made regarding the
groundwater elevation being
relatively deep in the location
of the stormwater system
because this portion of the lot
is 15 to 20 feet higher than the
adjacent wetland.
Groundwater monitoring
wells will be installed April 16,
2021. If the results of the
monitoring prove the
assumption to be incorrect, a
MOD application will be
submitted to correct the
problem.
1 BMC 38.410.130 (A) (1) Water rights - The applicant
must contact Griffin Nielsen with the City
Engineering Department to obtain a determination
of cash-in-lieu of water rights (CILWR).
CILWR must be paid prior to site plan modification
approval.
Water Rights See CILWR calculations
included with this resubmittal
(Appendix J).
1 DSSP V.D.1- A minimum of ten feet of separation
must be maintained between the water
services, sewer services, and the proposed fire
hydrant on Village Downtown Boulevard.
Water &
Wastewater
See updated Civil plan sheet
C3.0.
2 The applicant must submit the design for the fire
hydrant with the Modification package
resubmittal. The applicant must work with the City
on all pre-construction submittals and
permitting.
Water &
Wastewater
Based on conversation
between C&H and Cody
Flammond on April 6, 2021,
the requirement of hydrant
plan set is being lifted for
MOD approval and will be
required in the same
submittal with the future fire
line plan.
Palisade at 130 Village Crossing Way
MOD Application – RC#1 (21-073)
April 2021
Page 16 of 17
1 BMC 38.400.010 (A) (5) Streets, General - The
proposed parking lot on the south side of the site
is considered a dead-end and must comply with City
design specifications and standards, and
with any city-adopted International Fire Code. No
dead-ends longer than 150 feet are permitted
without an approved turn-around. The applicant
must provide an engineering approved turn
around for emergency vehicles.
Transportation During a meeting between the
design team and Scott Mueller
on April 2, 2021 it was
determined that this
comment would be removed.
We are providing a 26’ wide
access lane from the Right of
Way to the back (east end) of
the parking lot. We have also
added fire lane curb paint and
signage to Sheet C2.0 to the
north-south drive aisle.
City of Bozeman Resolution 5076, Policy 1 - The
applicant must provide and file with the County
Clerk and Recorder's office executed Waivers of
Right to Protest Creation of Special
Improvement Districts (SID’s) on City standard form
for the following: Street improvements to Village
Downtown Boulevard including lighting,
signalization,
paving, curb/gutter, sidewalk, and storm drainage.
Street improvements to Village Crossing Way
including lighting, signalization, paving,
curb/gutter, sidewalk, and storm drainage.
Street improvements to Broadway Avenue between
Village Downtown Boulevard and
Main Street including lighting, signalization, paving,
curb/gutter, sidewalk, and storm
drainage.
Intersection improvements at Village Crossing Way
and Village Downtown Boulevard
including lighting, signalization/channelization,
paving, curb/gutter, sidewalk, and storm
drainage.
Intersection improvements at Village Downtown
Boulevard and Broadway Avenue
including lighting, signalization/channelization,
paving, curb/gutter, sidewalk, and storm
drainage.
Intersection improvements at Mendenhall Street
and Broadway Avenue including
lighting, signalization/channelization, paving,
curb/gutter, sidewalk, and storm drainage.
Intersection improvements at Broadway Avenue and
Main Street including lighting,
signalization/channelization, paving, curb/gutter,
sidewalk, and storm drainage.
Conditions of
Approval
See attached draft of Waiver
of Right to protest SID. Once
deemed acceptable it will be
executed and filed (Appendix
I).
Palisade at 130 Village Crossing Way
MOD Application – RC#1 (21-073)
April 2021
Page 17 of 17
1 DSSP Fire Service Line Standard - The applicant must
prepare plans and specifications for any fire
service line in accordance with the City’s Fire Service
Line Policy. The plans must be prepared by
a Professional Engineer and be provided to and
approved by the City Engineer prior to initiation
of construction of the fire service or fire protection
system. The applicant must also provide
Professional Engineering services for construction
inspection, post-construction certification and
preparation of mylar record drawings. Fire service
plans, and domestic services 4” or larger, must
be a standalone submittal, separate from the
modification submittal. City of Bozeman
applications for service must be completed by the
applicant.
Engineering
Advisory
Comments
Understood.