HomeMy WebLinkAboutAppendix D Stormwater Design Report 04-16-2021
INTRODUCTION
The Palisade at 130 Village Crossing Way site plan consists of a multi-story residential building
with a footprint of approximately 33,500 sq. ft. and associated improvements located on Lot 5 of
Minor Subdivision 344 in Bozeman, Montana. A combination of site grading, curb and gutter, at-
grade retention ponds and underground Stormtech MC-3500 storage chambers will be used to
manage stormwater runoff for the development of the site. The proposed underground Stormtech
MC-3500 stormwater storage system and retention ponds were sized for the 10-year, 2-hour storm
and checked for the half-inch requirement. Supporting stormwater calculations are attached to this
report. Drainage Area Maps for pre and post-development are included in Appendix A.
Calculations for each individual drainage area are included in Appendix B. A Stormwater Facilities
Inspection and Maintenance Plan is included in Appendix C. Excerpts from the Parklands at the
Village Downtown Subdivision stormwater report are included in Appendix D.
POST-DEVELOPMENT DRAINAGE AREAS
Drainage Area 1
Drainage Area 1 consists of the south half of the parking lot and adjacent landscaping. Runoff
from this drainage area flows via curb and gutter to Retention Pond #1. The proposed retention
pond was sized for the 10-year, 2-hour storm and was checked for the half-inch requirement. It
was found that the 10-year, 2-hour storm governed the design and required 585 cubic feet of
storage. 620 cubic feet of storage is provided in Retention Pond #1.
Drainage Area 2
Drainage Area 2 consists of the north half of the parking lot and adjacent landscaping. Runoff from
this drainage area flows via curb and gutter to Retention Pond #2. The proposed retention pond
was sized for the 10-year, 2-hour storm and was checked for the half-inch requirement. It was
found that the 10-year, 2-hour storm governed the design and required 582 cubic feet of storage.
614 cubic feet of storage is provided in Retention Pond #2.
Drainage Area 3
Drainage Area 3 consists of the entire building and courtyard. Runoff from this drainage area flows
via a system of downspouts and pipes designed by others to the proposed Stormtech MC-3500
infiltration chambers located to the east of the building above the steep slope. The chambers are
designed to retain stormwater runoff using the arch-shaped chambers and void space in the
surrounding washed rock while the runoff infiltrates into the ground. The chambers were sized for
the 10-year, 2-hour storm and was checked for the half-inch requirement. It was found that the 10-
year, 2-hour storm governed the design and required 2,130 cubic feet of storage. 2,382 cubic feet
of storage is provided in the Underground Stormwater System including the surrounding washed
rock using a stone porosity of 40%. The system is equipped with an overflow pipe that daylights
to the adjacent hillside to the east. This overflow is set to the top of the chambers so it only
overflows in the unlikely event that the system is full.
Drainage Area 4
Drainage Area 4 consists of the landscaped and concrete areas located between the building and
existing Right of Ways (ROW) of Village Crossing Way and Village Downtown Blvd. Runoff
from this drainage area flows into said ROWs and subsequently into an existing detention pond at
the end of Village Downtown Blvd. Said pond was recently re-designed and re-shaped for the new
Parklands Subdivision. The pond was designed with a volume of 7,726 cubic feet, when only 7,522
cubic feet was required. An excess of 204 cubic feet of storage exists in said pond. DA #4
contributes 229 cubic feet of stormwater during the design storm event (10-yr, 2-hr). Given the
approximate nature of the Rational Method and the relatively small excess stormwater volume of
25 cubic feet it is deemed negligible. Therefore, it is acceptable not to provide any stormwater
improvements for DA #4 and to allow this area to naturally drain into said ROWs.
Drainage Area 5
Drainage Area 5 consists primarily of the area of the site that is undisturbed. Runoff from this
drainage area flows to the adjacent lots to the east. Historically, a large portion of the lot’s runoff
has flowed in a similar fashion. See Drainage Area Map – Pre-Development in Appendix A for a
visual reference. With the development of the lot, the runoff leaving the property is reduced from
1,205 cubic feet pre-development to 1,066 cubic feet post-development. Therefore, it is acceptable
not to provide any stormwater improvements for DA #5 and to allow this area to naturally drain
into adjacent lots to the east as it has done historically.
DEPTH TO GROUNDWATER
Groundwater monitoring has not been conducted on the subject property. Given that the wetland
area on the far east end of the lot is approximately 15 feet lower in elevation than the bottom of
the Stormtech chambers gravel retention volume, it is assumed that the underlying groundwater
table will not interfere with the function of the subsurface stormwater system. The developer is
planning to dig test pits on site on April 16, 2021 and will install groundwater monitoring wells to
verify this assumption. If our assumption regarding groundwater is incorrect, we will submit a
MOD application to rectify the issue.
G:\C&H\20\201192\Design Reports\Storm\201192_Stormwater Design Report.Docx
APPENDIX A
DRAINAGE AREA MAPS
1235758596061ADAADA
APPENDIX B
DRAINAGE AREA,
INFILTRATION/RETENTION SYSTEM
CALCULATIONS
DRAINAGE AREA #1
RETENTION POND #1
1. Calculate Area and Weighted C Factor
Contributing Area DA #C Area (ft 2 )C * Area
Hardscape 1 0.95 7012 6661
Landscape 1 0.20 10118 2024
Total 17130 8685
A = Area (acres)0.39
C = Weighted C Factor 0.51
2. Calculate Required Volume
Q = CIA
V=7200Q
C = Weighted C Factor 0.51
I = intensity (in/hr) 0.41 (10 yr, 2hr storm)
A = Area (acres)0.39
Q = runoff (cfs)0.08
V = REQUIRED VOL (ft3)585
Check the half inch requirement (per DSSP II.A.4)
1. Determine Area of Hardscape within Drainage Area #1
Contributing Area Area (ft 2 )
Hardscape 7012
2. Calculate 1/2" runoff volume over hardscape
(aka Runoff Reduction Volume [RRV] as calculated in Montana Post-
Construction Storwater BMP Manual - Equation 3-1)
RRV = [P*Rv*A]/12
P = Water quality rainfall depth 0.50 inches
Rv = Dimensionless runoff coefficient 0.42 0.05 + 0.9*I
I = Percent impervious cover (decimal)0.41 decimal
A = Entire drainage area 0.39 acres
RRV = Runoff Reduction Volume 0.007 acre-ft
RRV = Runoff Reduction Volume 299 cubic feet
Because the runoff volume from the 10-yr, 2-hr storm (for flood control) is
greater than the runoff volume produced by the half inch rainfall (for water quality)
the proposed retention pond #1 is sized to handle the larger volume (585 cf).
DRAINAGE AREA #2
RETENTION POND #2
1. Calculate Area and Weighted C Factor
Contributing Area DA #C Area (ft 2 )C * Area
Hardscape 2 0.95 8279 7865
Landscape 2 0.20 3821 764
Total 12100 8630
A = Area (acres)0.28
C = Weighted C Factor 0.71
2. Calculate Required Volume
Q = CIA
V=7200Q
C = Weighted C Factor 0.71
I = intensity (in/hr) 0.41 (10 yr, 2hr storm)
A = Area (acres)0.28
Q = runoff (cfs)0.08
V = REQUIRED VOL (ft3)582
Check the half inch requirement (per DSSP II.A.4)
1. Determine Area of Hardscape within Drainage Area #2
Contributing Area Area (ft 2 )
Hardscape 8279
2. Calculate 1/2" runoff volume over hardscape
(aka Runoff Reduction Volume [RRV] as calculated in Montana Post-
Construction Storwater BMP Manual - Equation 3-1)
RRV = [P*Rv*A]/12
P = Water quality rainfall depth 0.50 inches
Rv = Dimensionless runoff coefficient 0.67 0.05 + 0.9*I
I = Percent impervious cover (decimal)0.68 decimal
A = Entire drainage area 0.28 acres
RRV = Runoff Reduction Volume 0.008 acre-ft
RRV = Runoff Reduction Volume 336 cubic feet
Because the runoff volume from the 10-yr, 2-hr storm (for flood control) is
greater than the runoff volume produced by the half inch rainfall (for water quality)
the proposed retention pond #1 is sized to handle the larger volume (582 cf).
DRAINAGE AREA #3
UNDERGROUND STORMWATER SYSTEM
1. Calculate Area and Weighted C Factor
Contributing Area DA #C Area (ft 2 )C * Area
Hardscape 3 0.95 33254 31591
Landscape 3 0.20 0 0
Total 33254 31591
A = Area (acres)0.76
C = Weighted C Factor 0.95
2. Calculate Required Volume
Q = CIA
V=7200Q
C = Weighted C Factor 0.95
I = intensity (in/hr) 0.41 (10 yr, 2hr storm)
A = Area (acres)0.76
Q = runoff (cfs)0.30
V = REQUIRED VOL (ft3)2130
Check the half inch requirement (per DSSP II.A.4)
1. Determine Area of Hardscape within Drainage Area #3
Contributing Area Area (ft 2 )
Hardscape 33254
2. Calculate 1/2" runoff volume over hardscape
(aka Runoff Reduction Volume [RRV] as calculated in Montana Post-
Construction Storwater BMP Manual - Equation 3-1)
RRV = [P*Rv*A]/12
P = Water quality rainfall depth 0.50 inches
Rv = Dimensionless runoff coefficient 0.95 0.05 + 0.9*I
I = Percent impervious cover (decimal)1.00 decimal
A = Entire drainage area 0.76 acres
RRV = Runoff Reduction Volume 0.030 acre-ft
RRV = Runoff Reduction Volume 1316 cubic feet
Because the runoff volume from the 10-yr, 2-hr storm (for flood control) is greater than
the runoff volume produced by the half inch rainfall (for water quality) the proposed
Underground Stormwater System is sized to handle the larger volume (2,130 cf).
DRAINAGE AREA #3
ROOF DOWNSPOUT PIPE ROUTED TO STORMTECH AND OVERFLOW PIPE
1. Summary of Roof Area and C Factor
Contributing Area DA #C Area (ft2 )C * Area
Hardscape 3 0.95 33254 31591
Total 33254 31591
A = Area (acres)0.76
C = Weighted C Factor 0.95
2. Calculate Tc (Time to Concentration)
Tc Overland Flow (on roof with pitch of 1/4" to 12")
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%)2.1%Return (yrs)CfC = Rational Method Runoff Coefficient 0.95 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)70 26 to 50 1.251 to 100 1.25
Tc Overland Flow (minutes)1.2
Tc Total =5.0 (5 minute minimum)
3. Calculate Flow (Rational Formula)Q = CIA
C = Weighted C Factor 0.95 (calculated above)
I = 0.78 Tc-0.64 (in/hr)3.83 (25-yr storm)
A = area (acres)0.76 (calculated above)
Q 25-yr Flow Rate (cfs)=2.77
MANNING'S EQUATION FOR PIPE FLOW (PROVIDED CAPACITY)Pipe: 1 Location:Roof Downspout pipe
INPUT
D=12 inchesd=11.26 inchesMannings Formula n=0.013 mannings
θ=57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S=0.01 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter V=(1.49/n)Rh2/3S1/2
S=slope of channel Q=V x A
n=Manning's roughness coefficient
Solution to Mannings Equation
Area,ft2 Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
0.77 2.64 0.29 5.21 3.99 PE (<9"dia)0.015
PE (>12"dia)0.02
PE(9-12"dia)0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
θ
D
User Inputs
Chamber Model: MC-3500
Outlet Control Structure: No
Project Name: Lot 5 - Palisade
Engineer: Tim Staub
Project Location:
Measurement Type: Imperial
Required Storage Volume: 2127 cubic ft.
Stone Porosity: 40%
Stone Foundation Depth: 48 in.
Stone Above Chambers: 12 in.
Average Cover Over Chambers: 48 in.
Design Constraint Dimensions:(25 ft. x 40 ft.)
Results
System Volume and Bed Size
Installed Storage Volume: 2381.85 cubic ft.
Storage Volume Per Chamber: 109.90 cubic ft.
Number Of Chambers Required: 7
Number Of End Caps Required: 4
Chamber Rows: 2
Maximum Length:38.35 ft.
Maximum Width: 15.33 ft.
Approx. Bed Size Required: 538.43 square ft.
System Components
Amount Of Stone Required: 143.79 cubic yards
Volume Of Excavation (Not Including
Fill):
174.49 cubic yards
DRAINAGE AREA #4
EXISTING SUBDIVISION POND
1. Calculate Area and Weighted C Factor
Contributing Area DA #C Area (ft2)C * Area
Hardscape 4 0.95 2391 2271
Landscape 4 0.20 5628 1126Total80203397
A = Area (acres)0.18
C = Weighted C Factor 0.42
2. Calculate Required Volume
Q = CIA
V=7200Q
C = Weighted C Factor 0.42
I = intensity (in/hr) 0.41 (10 yr, 2hr storm)A = Area (acres)0.18
Q = runoff (cfs)0.03
V = REQUIRED VOL (ft3)229
Check the half inch requirement (per DSSP II.A.4)
1. Determine Area of Hardscape within Drainage Area #3
Contributing Area Area (ft 2 )
Hardscape 2391
2. Calculate 1/2" runoff volume over hardscape
(aka Runoff Reduction Volume [RRV] as calculated in Montana Post-
Construction Storwater BMP Manual - Equation 3-1)
RRV = [P*Rv*A]/12
P = Water quality rainfall depth 0.50 inches
Rv = Dimensionless runoff coefficient 0.32 0.05 + 0.9*I
I = Percent impervious cover (decimal)0.30 decimal
A = Entire drainage area 0.18 acres
RRV = Runoff Reduction Volume 0.002 acre-ft
RRV = Runoff Reduction Volume 106 cubic feet
Because the runoff volume from the 10-yr, 2-hr storm (for flood control) is greater thanthe runoff volume produced by the half inch rainfall (for water quality) the capacity
of the existing subdivision pond was checked for the larger volume (229 cf).
The capacity of the existing subdivision detention pond located at the end of the
Village Downtown Blvd (and recently redesigned for the Parklands Subdivision) is
7,522 cf. The pond was designed with a volume of 7,726 cf leaving a remainder of
204 cf. Given the approximate nature of the Rational Method and the relatively small
excess stormwater volume of 25 cf it is deemed negligible. Therefore, it is acceptable
not to provide any stormwater improvements for DA #4 and to allow this area to
naturally drain into the ROW of Village Crossing Way and Village Downtown Blvd.
DRAINAGE AREA #5
VERIFY RUNOFF TO ADJACENT PROPERTIES DOES NOT EXCEED HISTORICAL
1. Calculate Area and Weighted C Factor
Contributing Area DA #C Area (ft 2 )C * Area
Hardscape 5 0.95 272 258
Landscape 5 0.20 77734 15547Total7800615805
A = Area (acres)1.79
C = Weighted C Factor 0.203
2. Calculate Required Volume
Q = CIA
V=7200Q
C = Weighted C Factor 0.20
I = intensity (in/hr) 0.41 (10 yr, 2hr storm)A = Area (acres)1.79
Q = runoff (cfs)0.15
V = REQUIRED VOL (ft3)1066
Check the half inch requirement (per DSSP II.A.4)
1. Determine Area of Hardscape within Drainage Area #3
Contributing Area Area (ft 2 )
Hardscape 272
2. Calculate 1/2" runoff volume over hardscape
(aka Runoff Reduction Volume [RRV] as calculated in Montana Post-
Construction Storwater BMP Manual - Equation 3-1)
RRV = [P*Rv*A]/12
P = Water quality rainfall depth 0.50 inches
Rv = Dimensionless runoff coefficient 0.05 0.05 + 0.9*I
I = Percent impervious cover (decimal)0.00 decimal
A = Entire drainage area 1.79 acres
RRV = Runoff Reduction Volume 0.004 acre-ft
RRV = Runoff Reduction Volume 173 cubic feet
Because the runoff volume from the 10-yr, 2-hr storm (for flood control) is greater thanthe runoff volume produced by the half inch rainfall (for water quality) the historical
lot drainage was checked for the larger volume (1066 cf).
The existing lot's historical drainage pattern is delineated on the
'Drainage Area Map - Pre Development' located in Appendix A. Said map shows
that the existing lot naturally drains to adjacent parcels to the east and the Village
Downtown Blvd ROW due to the existing grade. A volume of 1,295 cf is produced
during the 10-yr, 2-hr storm and flows off site to adjacent lots to the east. After the lot
is developed the runoff to the adjacent lots is reduced to 1,066 cf; therefore, no
stormwater improvements are proposed within DA #5.
APPENDIX C
STORMWATER FACILITIES INSPECTION
AND MAINTENANCE PLAN
INSPECTION AND MAINTENANCE FOR
STORMWATER MANAGEMENT FACILITIES
The owner shall be responsible for the maintenance of the stormwater drainage facilities within The
Palisade at 130 Village Crossing Way development on Lot 5, Minor Subdivision No. 344.
Storm Water Facilities:
1. Underground Stormtech MC-3500 Infiltration System collect storm water runoff and
store the water until it infiltrates into the ground.
2. Retention Ponds collect storm water runoff and store the water until it evaporates and/or
infiltrates into the ground.
3. Pipe Networks convey storm water to different discharge locations underground.
Post Construction Inspection:
1. Use the attached Stormtech Isolator Row Operation & Maintenance manual to determine if
maintenance is required on the system after construction is completed.
2. Observe drain time in retention ponds for a storm event after completion of the facility to confirm
that the desired drain time has been obtained. If excessively slow infiltration rates are observed
then excavate a minimum 5 ft by 5 ft drain to native gravels (or native well-draining material) and
backfill with well-draining material (pit-run).
Semi-Annual Inspection:
1. Use the attached Stormtech Isolator Row Operation & Maintenance manual to determine if
maintenance is required on the system semi-annually.
2. Check for grass clippings, litter, and debris in retention ponds. Flush and/or vacuum storm water
pipes if excessive material is observed in the facilities.
Standard Maintenance:
1. Inspect and remove debris from catch basins. Use a trailer-mounter Vermeer VX50-800
vacuum excavator or similar (see Figure 1 below) to clean Stormtech pre-treatment manhole
with sump. To accomplish the vacuuming procedure, the trailer-mounted vac system should
be pulled into the parking garage to access the pre-treatment manhole with sump. There will
need to be coordination with the building management to ensure no cars are parked in the
parking spaces on the east wall of the parking garage to allow for the trailer-mounted vac
system and truck to pull into the area to access said manhole.
2. Inspect for the following issues: differential accumulation of sediment, drain time, signs of
petroleum hydrocarbon contamination (odors, oil sheen in pond water), standing water, trash
and debris.
3. Monitor health of vegetation and revegetate as necessary to maintain full vegetative cover.
4. Check retention ponds three days following a storm event exceeding ¼ inch of precipitation. Failure
for water to percolate within this time period indicates clogging or poor-draining soils.
Figure 1 Trailer-mounted Vermeer VX50-800 vacuum excavator.
Sediment accumulation:
In most cases, sediment in a catch basin or a retention system does not contain toxins at levels posing
a hazardous concern. However, sediments should be tested for toxicants in compliance with current
disposal requirements and if land uses in the drainage area include commercial or industrial zones, or
if visual or olfactory indications of pollution are noticed. Sediments containing high levels of
pollutants should be disposed of in accordance with applicable regulations and the potential sources of
contamination should be investigated and contamination practices terminated.
An company
2
THE MOST ADVANCED NAME IN WATER MANAGEMENT SOLUTIONS TM
ECCENTRICHEADER
MANHOLEWITHOVERFLOWWEIR
STORMTECHISOLATOR ROW
OPTIONAL PRE-TREATMENT
OPTIONAL ACCESS STORMTECH CHAMBERS
)(
APPENDIX D
EXCERPTS FROM PARKLANDS
SUBDIVISION STORMWATER REPORT
DETENTION POND #1
REQUIRED VOLUME
1. Calculate Weighted C Factor for Right-of-Way
Component Width C
ROW Hardscape 64 0.95
ROW Landscape 16 0.2
Weighted C Factor = 0.80
2. Calculate Area and Weighted C Factor (Post-Development)
Contributing Area C Area (ft 2 )C * Area
Composite ROW 0.80 186132 148906
OS 0.2 8601 1720
Low-Med Residential 0.35 7888 2761
Dense Residential 0.5 52799 26400
Total 255421 179787
A = Area (acres) 5.8637
C = Weighted C Factor 0.70
3. Calculate Tc (Pre-Development)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%) 3.50% Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.2 2 to 10 1
Cf = Frequency Adjustment Factor 1 11 to 25 1.1
D = Length of Basin (ft) 532 26 to 50 1.2
51 to 100 1.25
Tc (Pre-Development) (minutes) 26
4. Calculate Rainfall Intensity (Duration = Pre-Development Tc)
i = 0.64x-0.65 (10-yr Storm, Fig. I-3, COB Design Standards)
x = storm duration (hrs) 0.43 (Tc Pre-Development)
i = rainfall intensity (in./hr.) 1.11
5. Calculate Runoff Rate (Pre-Development)
Q = CiA
C = Rational Method Runoff Coefficient 0.2 (open land)
i = rainfall intensity (in./hr.) 1.11 (calculated above)
A = Area (acres) 5.86 (calculated above)
Q = Runoff Rate (Pre-Development) (cfs) 1.31
6. Calculate Required Pond Volume
Total Area (acres) = 5.86 acres
Weighted C = 0.70
Discharge Rate (cfs) = 1.31 cfs (Equal to Pre-Development Runoff Rate)
Duration(min) Duration(hrs)
Intensity
(in/hr)Qin (cfs)Runoff
Volume
Release
Volume
Required
Storage (ft3)
30 0.50 1.00 4.14 7461 0 7461
30.5 0.51 0.99 4.10 7504 0 7504
31 0.52 0.98 4.06 7547 39 7508
32 0.53 0.96 3.97 7631 118 7514
33 0.55 0.94 3.90 7714 196 7518
34 0.57 0.93 3.82 7795 274 7521
35 0.58 0.91 3.75 7875 353 7522
36 0.60 0.89 3.68 7953 431 7521
37 0.62 0.88 3.62 8029 510 7520
38 0.63 0.86 3.55 8104 588 7516
OUTLET STRUCTURE SLOT
Q=CLH3/2
Q = Discharge (cfs) 1.31 (calculated above)
C = Weir Coefficient 3.33 (per COB Design Standards)
H = Head (ft) 1
L = Horizontal Length (ft) 0.39
L = Slot Width (inches) 4.7