HomeMy WebLinkAbout0_CoverLetter_04162021
2304 N. 7TH AVENUE | SUITE L | BOZEMAN, MT 59715 | (406) 587-2781
Professional Consulting Engineers and Land Surveyors
Equal Opportunity Employer | www.hyaliteeng.com
April 16, 2021
City of Bozeman- Community Development Department
PO Box 1230
Bozeman, MT 59771
Attn: Sarah Rosenberg- Associate Planner
RE: Parkview Crossings Major Subdivision – Preliminary Plat Submittal
Lot 4 of Minor Subdivision 400, Bozeman, MT
Dear Sarah:
The purpose of this submittal is to provide you with a Subdivision Preliminary Plat Submittal for the above
referenced project. The Park View Crossings Subdivision is located at the intersection of Tschache Lane and
Vaquero Parkway on the existing Lot 4 of Minor Subdivision 400. The project consists of 44 residential lots:
nine 4-plex units, two 3-plex units, and one duplex unit. This development is consistent with the existing
Zoning, and Subdivision Regulations for this area. The existing and the nearby surrounding zoning is R-3. All
preliminary plat requirements have been met and are found within this submittal.
The development team for the project is as follows;
Owner/Developer- Campeche Shores Development Company, LLC (Ethan Stokes)
PO Box 3088
Galveston, Texas 77552
Architect- 45 Architecture, LLC (Martina Parrish)
1216 W Lincoln Street, Suite D
Bozeman, MT 59715
Civil Engineer- Hyalite Engineers, PLLC (Brett Megaard)
2304 N 7th Ave, Suite L
Bozeman, MT 59715
The following is in response to the City’s comment letter received on September 22, 2020 following the pre-
application submittal for this project:
Planning Comments:
1. The amount of lots have been decreased. The original application proposed 46 lots, whereas 44
lots are now proposed – varying from 4-plex to duplex units. The lots located internally on the
loop road will be alley loaded, with water and sewer being serviced from the alley. Each of the
units will have a garage facing the alley. The exterior lots (one 4-plex and two 3-plexes) will have
a drive approach directly onto the loop road.
2. The garage for each unit is four feet behind the front façade of the structure. The garages also do
not comprise of more than 50% of the width of the ground level façade.
3. There is no longer a park access easement, as the loop road is now bordered to the west by the
park.
4. Affordable housing is no longer a requirement per HB 259. Cash-in-lieu of affordable housing will
no longer be provided, as the requirement has been eliminated for inclusionary zoning.
5. Street trees will be provided along Vaquero Parkway, as well as the interior loop road.
Letter to City of Bozeman
Re: Park View Crossings- Preliminary Plat Application
Lot 4 of Minor Subdivision 400, Bozeman, MT
April 14, 2021
Page 2 of 3
L:\193211\_Preliminary Plat\_Letter CoB- Development Review.doc
Engineering Comments:
Stormwater
1. The subdivision storm sewer network will connect to existing storm sewer stubs located near
Vaquero Parkway. Phases 4G & 4H of the Crossing 2 at Baxter Meadows accounted for future
connection to the storm network. The stormwater runoff will then discharge into Pond 5B located
north of the development within the existing stormwater easement. As the exact density of the
proposed development was not known at the time, the existing pond will need to be extended in
order to effectively control the stormwater discharge.
2. The stormwater conveyance system is located above the seasonal high groundwater level. The
storm sewer piping is near the minimum practical bury depth.
Transportation
3. The proposed local street now meets all geometric requirements as per the City’s Design
Standards and Specifications Policy. Also proposed with the development is an alley within a 30’
public right of way that is designed to meet the standards of the Bozeman Municipal Code as well
as the intersection requirements found in the City of Bozeman Modifications to MPWSS.
4. Tschache Lane has been extended to the western property boundary with the loop Road. The
loop road then continues from the end of Tschache Lane to the north and connects back into
Vaquero Parkway. The entire N-S section of the loop road borders the Gallatin County Regional
Park.
5. Pursuant to conversations with the City of Bozeman Parks and Recreation Department, a shared
use pathway will be constructed within the Vaquero Parkway right-of-way along the property’s
eastern boundary. The pathway will provide park connections to the north and south of the
development, as well as continuing the PROST plan for overall City pedestrian connectivity.
Utilities
6. The development now includes an alley with the majority of the units being alley-loaded. The alley
is located within a 30’ public right-of-way with water and sewer mains following the alley
centerline. No services will be needed from Vaquero Parkway nor will street trees be located
within the alley boulevard.
7. The newly constructed/in-construction lift station north of Davis Lane/I-90 will help mitigate the
currently full allocation to the Baxter Meadows Lift Station, as well as the Norton Bypass line that
was a part of that project. Once the new lift station is up and running, the capacity of the Baxter
Meadows lift station will be drastically reduced, thus allowing the proposed subdivision to move
towards construction and/or Final Plat. We do understand that Final Plat cannot be granted until
that project is fully operational. See the included Engineering Report for the estimated
wastewater demands.
Parks Comments:
1. Noted, cash-in-lieu of parkland dedication is proposed with this subdivision, see the included
analysis.
2. Noted, cash-in-lieu of parkland dedication is proposed with this subdivision, see the included
analysis.
3. Noted, cash-in-lieu of parkland dedication is proposed with this subdivision, see the included
analysis to include the shared use path as part of the option.
4. N/A, no park elements are being included with the application.
5. Noted.
6. Noted and agreed, the open space areas are accounted for within the CILP analysis included.
Fire Comments:
· A fire hydrant has been provided at each end of the loop road (northern and southern
connections), as well as mid-block within the alley right-of-way.
Letter to City of Bozeman
Re: Park View Crossings- Preliminary Plat Application
Lot 4 of Minor Subdivision 400, Bozeman, MT
April 14, 2021
Page 3 of 3
L:\193211\_Preliminary Plat\_Letter CoB- Development Review.doc
Northwestern Energy Comments:
· A 10-foot utility easement is being provided along all lot frontages to the City street. Water
and sewer services will be located within the alley; thus, no utility easement has been
provided along alley frontage.
A water main exists on the north and south sides of this parcel, with existing main stubs for future expansion.
An existing sewer main stub is located on the North side of this parcel. All increased stormwater will be
captured and detained on-site. No phasing of the project will be needed and no future development is
expected. Primary access to this subdivision will be from the intersection of Vaquero Parkway and Tschache
Lane. The other entrance will be located approximately 600’ north of the Vaquero Parkway and Tschache
Lane intersection. Parkland dedication will be satisfied by cash-in-lieu. Parking will be provided with on street
parking and by individual driveways.
From a previous wetland study completed for phases 4G and 4H at The Crossing 2 at Baxter Meadows, this
subdivision will be exempt from for the need for Streambed, Streambank and Wetland Permits. That study
identified the wetland areas associated with this vicinity and the only areas found were associated with the 4G
& 4H phases, as well as the Vaquero Parkway extension. A ten-foot utility easement is proposed in front of
the lots for utilities as agreed to by Northwestern Energy.
This project will either fully comply with the city of Bozeman’s Affordable Housing ordinance, or the developer
may still elect to pursue the cash-in-lieu option to be able to meet the requirements, however they are still
trying to assess all their available options. Once a more detailed proposal path is identified, it will be brought
forth to the City for your review.
Currently with this project, no waivers are being sought or requested, as the project is intended to meet all
zoning and development standards.
I hope that the enclosed information allows you to provide comment on this project. If for any reason you
have any questions, or need any additional information during the review of this project, please feel free to
give me a call at 587-2781 or send an email to bmegaard@hyaliteeng.com.
Sincerely,
______________________________
Brett Megaard, PE
Project Manager
Cc: File: 193211
Owner