Planned Unit Development Final PUDF Page 1 of 3 Revision Date 01-27-20
Required Forms: A1, SP1 Recommended Forms:
PUD FINAL PLAN REQUIRED MATERIALS
APPLICATION SETS
2 total sets are required that include 1 copy of every item below bound or folded into 8½ x 11 or 8½ x 14
sets.
Complete and signed development review application form A1.
Complete materials required by the SP1 checklist, except for traffic information required in item 67.
Materials and plans that include all the required items listed in the Final PUD plan checklist below.
Standard application sets
required plan sizes:
2 sets that include full size
24 x 36 inch plans 1 set that include 11 x 17 inch plans
2-digital versions of all materials (JPEG or PDF) on separate CD-ROM’s or USB drives. Individual files
must be provided at 5MB or less in size. Files shall be named according to naming protocol.
Notes:
All plans must be drawn to scale on paper not smaller than 8½ x 11 inches or larger than 24 x 36
inches. The name of the project must be shown on the cover sheet of the plans. If 3-ring binders
will be used, they must include a table of contents and tabbed dividers between sections. Plans
that are rolled or not bound into sets will not be accepted.
APPLICATION FEE
Base fee $1,407.00
If includes dwellings add: $45 per dwelling unit
If includes nonresidential
uses add: $140 per 1000 square feet of nonresidential building space.
PUD FINAL PLAN CHECKLIST
A Planned United Development (PUD) Final Plan review is the third and final step in the PUD entitlement
process. When a subdivision is proposed in conjunction with a zoning PUD the subdivision review shall be
coordinated with the zoning review and a subdivision final plat application may also be submitted
concurrent with this application. The purpose of the final plan is to revise all exhibits and documents to
comply with any conditions of approval and to present all documents in a final form.
1. A narrative stating how each of the conditions of preliminary approval and noted code provisions have
been satisfactorily addressed. This narrative shall be in sufficient detail to direct the reviewer to the
appropriate plat, plan, sheet, note, covenant, etc. in the submittal.
2. An executed and recorded copy of the PUD conditions of approval document provided by the City at
preliminary approval.
3. Final project narrative providing a thorough and extensive description of the overall project including
design intent, project goals, project timeframe, proposed uses, site improvements and buildings.
4. A complete list of the approved relaxations to the BMC listed by individual section and reason for the
relaxation.
5. Name, mailing address and full contact information for project team including: owner, developer,
architect, civil engineer, landscape architect/designer and electrical engineer.
6. A title report for subdivision or proposed subdivision guarantee with all current property ownership.
7. Data regarding site conditions, land characteristics, available community facilities and utilities and
other related general information about proposed uses, adjacent land uses and the uses of land within
one-half mile of the subject parcel of land both existing and proposed. This shall be in narrative and/or
$1,407 +($45*20)= $2,307
✔
✔
✔
✔
✔
Planned Unit Development Final PUDF Page 2 of 3 Revision Date 01-27-20
Required Forms: A1, SP1 Recommended Forms:
table formats. Provide the following supporting maps: existing land use map, community plan land use
designation map, city zoning map, neighborhood and entryway overlay map for property showing
conditions within 200 feet of the project boundaries.
8. Overall land use ratios for:
a. existing footprints of existing buildings and structures
b. proposed buildings and structures
c. driveways and parking areas
d. streets, roads and alleys with areas of rights of way identified separately
e. private open spaces for residential uses
f. landscape areas
g. city parkland
9. Overall project floor area ratio (FAR) and net residential density.
10. Final development Schedule. If phasing is proposed, provide narrative clearly describing project
phasing with the proposed phasing of all infrastructure, PUD open space, buildings, driveways and
parking and landscaping.
11. Final phasing Plan exhibit clearly showing all site and infrastructure improvements including PUD
open space or elements required for PUD performance point requirements with phase boundaries
including detailed limits of construction and approaches to mitigate any conflicts with phase
boundaries and site safety and function.
12 Final phasing table that shows phase area and data for each phase including: area in acres and square
feet, lot area in acres and square feet, building foot print square feet, building floor area, FAR, street
right of way, common opens space, landscaped area, PUD open space square feet and percentage of
total, PUD performance points by type and parking space requirements.
13. Table of proposed buildings include phase information, footprint, gross square footage, stories,
whether building exists or proposed and building use designations by building floor.
14. Colored aerial vicinity map within one-half mile of the site with project site and other significant
community facilities, streets, trails, watercourses, railways, highways and other applicable features
identified by name.
15. Overall site illustration in color showing all building foot prints, PUD open space, landscaped areas,
site circulation including vehicular, bike, and pedestrian facilities.
16. Statements of objectives and conformance to city policy and plans:
a. Statement of applicable City land use policies and objectives achieved by the proposed plan and how
it furthers the implementation of the Bozeman Community Plan, provide specific land use goals an
objectives in the Community Plan that are furthered by the proposed PUD;
b. Statement of proposed ownership of public and private open space areas and applicant’s intentions
with regard to future ownership of all or portions of the PUD;
c. Estimate of number of employees for business, commercial, and industrial uses;
d. Description of rational behind the assumptions and choices made by the applicant;
e. The applicant shall submit as evidence of successful completion of the applicable Community Design
objectives and Criteria of Section 38.20.090.E, documentation pursuant to these regulations
for each proposed use; the applicant shall submit written explanation for each of the applicable
objectives or criteria as to how the plan does or does not address the objective or criterion; the
Director may require, or the applicant may choose to submit, evidence that is beyond what is required
in that section; any variance from the criterion shall be described;
f. Detailed description of how conflicts between land uses are being avoided or mitigated;
g. Statements of design methods to reduce energy consumption, (e.g. - home/business, utilities,
transportation fuel, waste recycling);
Planned Unit Development Final PUDF Page 3 of 3 Revision Date 01-27-20
Required Forms: A1, SP1 Recommended Forms:
17. If not provided by subdivision application materials, physiographic data and summaries for:
landforms and geology and soils; hydrology; vegetation; noxious weeds; wildlife and view-sheds. If
the project is a brown field site, provide site history, data and copies of any environmental site
assessments that have been completed. An approved noxious weed management plan must be
submitted.
18. Narrative descriptions of site access and overall utilities including an overview, parking, existing and
proposed condition of the streets providing access to the site, proposed accesses to the site and
utilities including water, sewer, storm drainage, solid waste, gas, electric and shallow franchise
facilities.
19. Development and Design Guidelines per Section 38.20.070.D.2 BMC.
20. Comprehensive Signage Plan, if applicable.
21. Final drafts of supplementary documents per Section 38.38 of the BMC including property owners’
association documents, covenants, open space maintenance plan meeting the requirements of Section
38.38.030.
22. Stormwater facility maintenance plan.
CONTACT US
Alfred M. Stiff Professional Building
20 East Olive Street 59715 (FED EX and UPS Only)
PO Box 1230
Bozeman, MT 59771
phone 406-582-2260
fax 406-582-2263
planning@bozeman.net
www.bozeman.net