June 24, 2021
City of Bozeman Planning Dept.
Attn: Danielle Garber
20 E. Olive Street
P.O. Box 1230
Bozeman, MT 59771-1230
RE: Gran Cielo Subdivision, Phase 1, Multifamily Lots, Lot 9, Block 13 and Lot 4, Block
12, Site Plan Review Application No.19479 Response Letter to Planning Comments
Dear Danielle,
The following information addresses the planning comments from the original application review.
, Danielle Garber, dgarber@bozeman.net, 406-582-2272
1. Process-A Site Plan Application is required for entitlement. If the development phasing
is to extend for a period beyond two years than a master site plan is required.All phasing
plans must include a construction management plan. If the applicant is planning on
acquiring occupancy building by building, but not extending construction over 2-years,
then a construction management and phasing plan is still required with the site plan.
a. Site Plan may not be submitted until the final plat and associated agreements and
easements have been recorded at the Gallatin County Clerk and Recorder.
The final plat and associated agreements and easements have been recorded at
the Gallatin County Clerk & Recorder. The applicant plans to complete
construction on the individual sites covered under this site plan submittal in less
than 2-years.
2. Use- Section 38.360.240,townhouse rowhouse standards apply including:
a. Usable open space-Update the project cover sheets to show open space calculated
as 10% of the building area.
b. Building design.
The project is proposed to meet "Rowhouse" standards. Open Space
calculations found on Sheet C1.0 are based on 10%of the building area.
3. Parking- Section 38.540.020
a. Ensure stacked parking spaces in front of garages that are counted towards
provided parking stall counts meet the 9'x 18'surface parking standard.Delineate
the spaces on the site plan with annotated dimensions.
T: 406.581.4097 1 E: MCOTTERMAN@CADDISENG.COM PO BOX 11805,BOZEMAN, MT 597191 WWW.CADDISE-NC5.COM
Stacked parking spaces are delineated, dimensioned and enumerated on the site
plan.
b. Interior garage spaces not meeting the 22-foot space depth requirement interior
wall to interior wall.
Interiorgarage spaces meet the 22 foot depth requirement.
c. Snow removal storage areas must be provided sufficient to store snow
accumulation on site. Such areas may not cause unsafe ingress/egress to the
parking areas, may not cause snow to be deposited on public rights-of-way, may
not include areas provided for required parking access and spaces, and may not
be placed in such a manner as to damage landscaping. All snow removal storage
areas must be located and designed such that the resultant stormwater runoff is
directed into landscaped retention/detention and water quality improvement
facilities as required by the engineering department, or in compliance with the
storm drainage provisions of chapter 40 article 4, and/or best practices manual.
Adequate snow storage areas are depicted on the site plan.
4. Landscaping - Section 38.550 - The landscaping section of the UDC has been revised
and adopted by the City Commission with ordinance #2029. The changes, including
removing the performance points system,go into effect December 18,2019.Demonstrate
compliance with the formal submittal.
Compliance with the new landscaping section of the UDC is outlined in the included
Landscaping Plans.
5. Lighting-Section 38.570, demonstrate compliance with this article with any exterior
building mounted or parking area lighting.
Attached photometric lighting plans demonstrate compliance with UDC Section
38.570.
1. Buildings 19 and 20 (Duplexes) - no issues
As noted, and acknowledged, no issues.
2. Building 21, Lot 5,Block 6 (Triplex) -Fire sprinklers and fire alarm systems required due
to three units and stories,as acknowledged in the application.
It is our understanding the City changed its fire line policy since these comments
were received and fire sprinklers are now only required on four-plexes or greater.
3. The fire riser/domestic water service room should be sized to provide two-foot clearance
from pipe to exterior walls as specified by city standards.
See response to comment 2 above.
4. Road/alley ways designated, as 24-foot wide will be required fire lanes. Marking and
features shall be installed per Fire Code at points of ingress/egress and corners.
Alley and roadway markings were completed as a part of the Gran Cielo Subdivision
infrastructure.
5. Building addresses should be as building is fronted to Graf and S. 31st St.
Building addresses have been assigned by the City accordingly.
1. Park area requirement is to be provided as Improvements-in-lieu of Parkland in
accordance with the preliminarily approved Gran Cielo Master Park Plan. Provide a
spreadsheet showing itemized improvements to meet the base park requirements for the
Subdivision,additional improvements for the additional density of this lot up to 12 units
per acre,and improvements required for any other lots being reviewed concurrently.CIL
owed for subdivision requirements will be established at the time of Final Plat for Gran
Cielo Subdivision. Subsequent development must provide improvements based on the
appraisal value at the time of Site Plan completion(unless equivalent improvements have
been previously installed or guaranteed). Provide in the spreadsheet the cost per line
item to show compliance with the appraisal value established. Staff requests an editable
Excel spreadsheet to assist in future site inspections.
According to the final plat of Gran Cielo Subdivision Phase 1, an excess of parkland
was provided(improvements in-lieu were not proposed with Phase 1). As noted on
each Sheet C1.0 of our submittal "Parkland calculations on Sheet 5 of the Gran Cielo
Subdivision Phase 1 Final Plat show that a development density of 12 dwelling units
per acre was assumed for each of the 4 multi-unit lots associated with this project
Lot 9, Block 12, Lot 4, Block 12; Lot 3, Block 5 and Lot 5, Block 6 in aggregate were
assumed to contain a total of 28 dwelling units. This project proposes a total of 28
dwelling units on said lots. The assumed density and resulting subdivision
parkland dedication provides sufficient parkland to meet the requirements of the
Bozeman Municipal Code." Since improvements in lieu are not proposed/required
a cost per line-item spreadsheet calculation is not necessary.
Please don't hesitate to contact me if you have any questions or need any additional information
to complete your review of this project.
Sincerely,
Za n E., P.L.S.