Danielle Garber
From:Joshua Allen <Joshua@cpbuild.us>
Sent:Tuesday, November 2, 2021 1:57 PM
To:Danielle Garber; carl sanders
Cc:Diane Tolhurst; mcotterman@caddiseng.com; Greg Allen
Subject:RE: 21290 Gran Cielo Multi-Family Condos WEST SP Revision #1 - DRC Comments
Attachments:C1.0CoverSheet_102221.pdf; C2.0GeneralCivilUtilityPlan_102221.pdf;
C3.0Grading&DrainagePlan_102221.pdf; C4.0Site Plan_102221.pdf;
PM1PhotometricLightingPlan&Details_102221.pdf
Follow Up Flag:Follow up
Flag Status:Flagged
CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you recognize the
sender and know the content is safe.
Danielle,
See attached updated civil drawings that were included to address the setback issue. When we reviewed the drawings,
we discovered that only the two buildings on Graf on the east lot had patios that would hang into the setback. That was
resolved by pushing the buildings back the required distance to create a 6’ distance from front of building to the setback
line (the depth of the patio, per already submitted architectural drawings).
So, the architectural drawings have not changed, and the setback issue is resolved in these drawings that are attached.
2
Thank you,
Joshua Allen
Project Manager
Bozeman, Montana
Phone: 406.599.8417
Email: joshua@cpbuild.us
Website: www.cpbuild.us
From: Danielle Garber <DGarber@BOZEMAN.NET>
Sent: Tuesday, November 2, 2021 1:45 PM
To: carl sanders <carl@videredev.com>
Cc: Joshua Allen <Joshua@cpbuild.us>; Diane Tolhurst <dtolhurst@BOZEMAN.NET>; mcotterman@caddiseng.com; Greg
Allen <Greg@cadiuspartners.com>
Subject: RE: 21290 Gran Cielo Multi-Family Condos WEST SP Revision #1 - DRC Comments
Carl,
3
Comments are attached for the East and West Site Plans. There are 2 remaining planning corrections and 2
recommended conditions of approval. Correction 1 can be taken care of with the landscaping plans, correction 2 is
regarding the upper level patios encroaching into the front setback. I believe they recessed the upper level patios to take
of the encroachment, but I need an updated floor plans and update site plans showing where it overhangs.
Please let me know if you have any further questions. I will be available until 4pm if you would like to call.
Thank you,
Danielle Garber | Associate Planner, Community Development
City of Bozeman | 20 East Olive St. | P.O. Box 1230 | Bozeman, MT 59771
P: 406.582.2272 | E: dgarber@bozeman.net | W: www.bozeman.net
From: carl sanders < carl@videredev.com >
Sent: Tuesday, November 2, 2021 12:25 PM
To: Danielle Garber < DGarber@BOZEMAN.NET >
Cc: Joshua Allen < Joshua@cpbuild.us >; Diane Tolhurst < dtolhurst@BOZEMAN.NET >; mcotterman@caddiseng.com ; Greg
Allen < Greg@cadiuspartners.com >; Martin Matsen < MMatsen@BOZEMAN.NET >
Subject: Re: 21290 Gran Cielo Multi-Family Condos WEST SP Revision #1 - DRC Comments
CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you recognize the
sender and know the content is safe.
Diane or Danielle,
Thanks for the quick response Danielle. Can you call me this afternoon and let me know exactly which sheets
you want? I think we sent over everything that needed to be updated so I don’t know what you are looking for
at this point. Sorry for not understanding on my part.
Carl
On Nov 2, 2021, at 10:47 AM, Danielle Garber < DGarber@bozeman.net > wrote:
Hi Carl,
We typically don’t review by email. A revisions submittal through the front desk helps us keep a
schedule and loop in other departments if necessary.
However, since it looks like engineering comments have already been addressed I think we can switch
out the last few sheets by email. Please group together the new landscaping plans, and the floor and
setback plans to address comments #1 and #2 from the 10/6 DRC memo, and send them to Diane so
they can get placed in the file for Director and public review when we go to public notice. Once they are
in there I can check to see if these comments have been fully addressed, provide you an adequacy
memo, and get public notice scheduled. At that time you will be able to apply for concurrent review to
submit your building permits.
Please feel free to reach out with any questions.
Thank you,
4
Danielle Garber | Associate Planner, Community Development
City of Bozeman | 20 East Olive St. | P.O. Box 1230 | Bozeman, MT 59771
P: 406.582.2272 | E: dgarber@bozeman.net | W: www.bozeman.net
From: carl sanders < carl@videredev.com >
Sent: Tuesday, November 2, 2021 11:24 AM
To: Danielle Garber < DGarber@BOZEMAN.NET >
Cc: Joshua Allen < Joshua@cpbuild.us >; Diane Tolhurst < dtolhurst@BOZEMAN.NET >;
mcotterman@caddiseng.com ; Greg Allen < Greg@cadiuspartners.com >; Martin Matsen
<MMatsen@BOZEMAN.NET >
Subject: Re: 21290 Gran Cielo Multi-Family Condos WEST SP Revision #1 - DRC Comments
CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless
you recognize the sender and know the content is safe.
What else do you need to be submitted? I though I emailed everything?
On Nov 2, 2021, at 10:20 AM, Danielle Garber < DGarber@bozeman.net > wrote:
Hi Carl,
Sorry I missed your call. Landscaping looks good. Just need a revisions submittal of all
the changes for the file and we can move to next steps.
Thank you,
Danielle Garber | Associate Planner, Community Development
City of Bozeman | 20 East Olive St. | P.O. Box 1230 | Bozeman, MT 59771
P: 406.582.2272 | E: dgarber@bozeman.net | W: www.bozeman.net
From: carl sanders < carl@videredev.com >
Sent: Wednesday, October 27, 2021 1:24 PM
To: Danielle Garber < DGarber@BOZEMAN.NET >
Cc: Joshua Allen < Joshua@cpbuild.us >; Diane Tolhurst < dtolhurst@BOZEMAN.NET >;
mcotterman@caddiseng.com ; Greg Allen < Greg@cadiuspartners.com >; Martin Matsen
<MMatsen@BOZEMAN.NET >
Subject: Re: 21290 Gran Cielo Multi-Family Condos WEST SP Revision #1 - DRC
Comments
CAUTION: This email originated from outside of the organization. Do not click links or open
attachments unless you recognize the sender and know the content is safe.
Hi All,
Attached are the updated drawings to address the final comment. I believe we
have now addressed all of the comments. Can you confirm this? These drawings
are for both of the site plan reviews, if you need me to send separate emails or
something so they get routed correctly, please let me know.
5
We are trying very hard to get these units into production as quickly as possible,
especially the units at the corner of 27th and Graf which will really help provide
better access to the park by providing pedestrian connectivity. Is it possible to
submit for concurrent building permit review of those units and have all
departments review the building permit applications while we wait for the final
approval of the site plan? That way we would have the ability to pull building
permits as close to the site plan approval date as possible? We are already very
much behind schedule on these units and appreciate any assistance the City can
provide us in bringing them to completion.
Thank you for all of your help thus far.
Carl
On Oct 22, 2021, at 11:20 AM, Danielle Garber
<DGarber@BOZEMAN.NET > wrote:
Hi Josh,
That looks like it would work. Building in more flexibility to this section
was a thread of discussion at our meeting this morning and I appreciate
the feedback.
Thank you,
Danielle Garber | Associate Planner, Community Development
City of Bozeman | 20 East Olive St. | P.O. Box 1230 | Bozeman, MT 59771
P: 406.582.2272 | E: dgarber@bozeman.net | W: www.bozeman.net
From: Joshua Allen < Joshua@cpbuild.us >
Sent: Friday, October 22, 2021 11:59 AM
To: Danielle Garber < DGarber@BOZEMAN.NET >; carl sanders
<carl@videredev.com >
Cc: Diane Tolhurst
<dtolhurst@BOZEMAN.NET >; mcotterman@caddiseng.com ; Greg Allen
<Greg@cadiuspartners.com >; Martin Matsen
<MMatsen@BOZEMAN.NET >
Subject: RE: 21290 Gran Cielo Multi-Family Condos WEST SP Revision #1
- DRC Comments
CAUTION: This email originated from outside of the organization. Do not click
links or open attachments unless you recognize the sender and know the
content is safe.
Danielle,
6
It appears that the drawings Matt sent yesterday did not fully
incorporate the changes we discussed internally, but the plan is to shift
the buildings back so that the upper patios are all out of the setback. I
believe the only ones that currently have this issue are 2723 and 2715
Graf. The other ones all seem to be right on the line already. That will
resolve the patio issue.
In regard to the open space. Our consultants understanding was that if
the patios where a minimum of 6’ deep they could qualify as open space
and not require any fencing or hedge. However, it appears that the code
now has a minimum of 12’ x 12’ for townhouse rowhouse, so I guess we
are going to need a fence/hedge regardless. I want to make sure we get
this right on the resubmittal, so is what I’m showing below
representative of a solution that works:
<image007.jpg>
I appreciate your willingness to allow a hedge as an option. However, I
do want to reiterate that it doesn’t really make any sense in this
context. This duplex on 31 st will be the only duplex on a subdivision
street of 50 houses that has a front yard hedge. I appreciate that variety
is important in urban settings, but this is a neighborhood. I understand
you don’t have any more flexibility afforded to you, and that’s fine, we’ll
make it work. But I think this highlights why the site plan review process
is really not designed to handle these kinds of projects. It is designed for
large apartment projects and urban infill projects. It really doesn’t lead
to common sense solutions for small projects like this. The city
desperately needs a middle ground review process between sketch plan
and site plan review that allows a little more flexibility and common
sense.
Thank you again for your help. We do appreciate it and please
understand our frustration is with the code and not with you.
Thank you,
Joshua Allen
Project Manager
<image008.png>
Bozeman, Montana
Phone: 406.599.8417
Email: joshua@cpbuild.us
Website: www.cpbuild.us
From: Danielle Garber < DGarber@BOZEMAN.NET >
Sent: Friday, October 22, 2021 11:02 AM
To: Joshua Allen < Joshua@cpbuild.us >; carl sanders
<carl@videredev.com >
Cc: Diane Tolhurst
<dtolhurst@BOZEMAN.NET >; mcotterman@caddiseng.com ; Greg Allen
<Greg@cadiuspartners.com >; Martin Matsen
7
<MMatsen@BOZEMAN.NET >
Subject: RE: 21290 Gran Cielo Multi-Family Condos WEST SP Revision #1
- DRC Comments
Hi Josh,
Regarding porch/patio encroachments #4 below was added to allow
covered ground level entry porches to encroach into the front setback.
This has been reiterated by senior staff since the paragraph was added
to the code. It was never intended for upper level patios. The upper
level patios, appear to encroach around 2-feet into the front setback
and need to be moved out of the setback, and the site plan and
landscape plans need to be updated (see below snips from your
drawings).
<image009.jpg><image010.jpg>
Regarding the open space fencing, there are no departures from the
TH/RH open space section shown below. The open space must be
adjacent to and accessible from each dwelling unit. Must be a minimum
of 12-feet on all sides and must be fenced if in the front setback. Senior
staff suggested an alternative to a fence. The code below does
reference the fencing standards of Section 38.350.060 which is for
fences walls and hedges. A bit of separation is required, but not
necessarily a 4-foot fence, you could do a 30-inch fence or hedge. For
some of the units this is the south facing portion of the lot and will be
utilized by residents. I would add that variety doesn’t necessarily mean
“ugly” as stated below, theme and variation is a core urban planning
principal.
<image011.png>
Thank you,
Danielle Garber | Associate Planner, Community Development
City of Bozeman | 20 East Olive St. | P.O. Box 1230 | Bozeman, MT 59771
P: 406.582.2272 | E: dgarber@bozeman.net | W: www.bozeman.net
From: Joshua Allen < Joshua@cpbuild.us >
Sent: Thursday, October 7, 2021 10:42 AM
To: Danielle Garber < DGarber@BOZEMAN.NET >; carl sanders
<carl@videredev.com >
Cc: Diane Tolhurst
<dtolhurst@BOZEMAN.NET >; mcotterman@caddiseng.com ; Greg Allen
<Greg@cadiuspartners.com >; Martin Matsen
<MMatsen@BOZEMAN.NET >
Subject: RE: 21290 Gran Cielo Multi-Family Condos WEST SP Revision #1
- DRC Comments
CAUTION: This email originated from outside of the organization. Do not click
links or open attachments unless you recognize the sender and know the
content is safe.
Danielle,
8
On the fenced front patios, I understand that is technically what the
code requires for open space, but it will, without a doubt and without
much debate, lead to an uglier streetscape. This project consists of the
entirety of Graf Street in Gran Cielo. Ten buildings that are of this similar
design and were all on single lots approved via sketch plan review, all
utilizing front-yard open space, and none of them with fences. These
units will end up sticking out like a sore thumb, with no continuity to the
existing street scape.
In regard to the upper-level front porches. There appears to be two
code subsections that address this. One talks about not extending above
the ground floor level, the other does not. Also, how are you defining
ground-floor level? The structure tapers back to the easement line as it
extends past the upper-level patio, which is also acting as an entry roof.
3. Terraces and patios, uncovered decks and stoops or similar
features, provided that such features do not extend above the
height of the ground floor level of the principal structure nor
more than five feet into any required front or rear setback or
two feet into any required side setback;
4. Porches and entries on residential structures, except multi-
household developments featuring more than four attached
dwelling units, may project up to five feet into the front setback
area except where front setback utility easements prevent such
projects;
How are you differentiating what is defined as a “terrace or patio” in
subsection three below, versus what is defined as a “porch or entry” in
subsection four? Do we just need to remove the door out to the upper-
level patio and call that space an entry roof?
I understand that you are bound by the code, but it’s very unfortunate
when the code doesn’t produce a result that passes the test of common
sense.
<image012.jpg>
Thank you,
Joshua Allen
Project Manager
<image008.png>
Bozeman, Montana
Phone: 406.599.8417
Email: joshua@cpbuild.us
Website: www.cpbuild.us
From: Danielle Garber < DGarber@BOZEMAN.NET >
Sent: Wednesday, October 6, 2021 4:53 PM
To: carl sanders < carl@videredev.com >; Joshua Allen
9
<Joshua@cpbuild.us >
Cc: Diane Tolhurst
<dtolhurst@BOZEMAN.NET >; mcotterman@caddiseng.com ; Greg Allen
<Greg@cadiuspartners.com >; Martin Matsen
<MMatsen@BOZEMAN.NET >
Subject: RE: 21290 Gran Cielo Multi-Family Condos WEST SP Revision #1
- DRC Comments
Hi Carl, Josh and Greg,
The comments are regarding setbacks and open space design
requirements for TH/RH structures.
I am asking you to make the site plan drawings and the landscaping plan
drawings match what you are showing in the floor plans. The ground
level patios extending 6-feet from the front façade, as currently drawn
on the floor plans, will encroach into previously planned landscaping
beds shown on the site and landscaping plans. Additionally, this patio
open space is fine, and can encroach into the front setback provided a
4-foot fence is provided for privacy of the user as required by code.
The other comment is regarding upper level patios encroaching into the
front setback, it is detailed in the memos.
Yes, you are correct, Parks does not need any further information and
there is a parkland credit that applies to these lots so no further action
is needed for parkland.
The remaining condition of approval is listed at the top of both memos
regarding CILWR, I will remove the Parks condition for final review.
If we can get the above items fixed for the files, we can move to public
notice and staff report preparation.
Thank you,
Danielle Garber | Associate Planner, Community Development
City of Bozeman | 20 East Olive St. | P.O. Box 1230 | Bozeman, MT 59771
P: 406.582.2272 | E: dgarber@bozeman.net | W: www.bozeman.net
From: carl sanders < carl@videredev.com >
Sent: Wednesday, October 6, 2021 2:26 PM
To: Joshua Allen < Joshua@cpbuild.us >
Cc: Diane Tolhurst
<dtolhurst@BOZEMAN.NET >; mcotterman@caddiseng.com ; Greg Allen
<Greg@cadiuspartners.com >; Danielle Garber
<DGarber@BOZEMAN.NET >
Subject: Re: 21290 Gran Cielo Multi-Family Condos WEST SP Revision #1
- DRC Comments
10
CAUTION: This email originated from outside of the organization. Do not click
links or open attachments unless you recognize the sender and know the
content is safe.
Looked like something about setbacks too. I believe we cleared up the
parks comment today with Matthew.
On Oct 6, 2021, at 1:05 PM, Joshua Allen
<Joshua@cpbuild.us > wrote:
Diane,
Am I reading this correctly that the only item remaining
is the open space/patios, and then the CILWR payment
and updated parkland table?
Thank you,
Joshua Allen
Project Manager
<image001.png>
Bozeman, Montana
Phone: 406.599.8417
Email: joshua@cpbuild.us
Website: www.cpbuild.us
From: Diane Tolhurst <dtolhurst@BOZEMAN.NET >
Sent: Wednesday, October 6, 2021 1:08 PM
To: carl sanders < carl@videredev.com >; Joshua Allen
<Joshua@cpbuild.us >; mcotterman@caddiseng.com ;
Greg Allen < Greg@cadiuspartners.com >
Cc: Danielle Garber < DGarber@BOZEMAN.NET >
Subject: 21290 Gran Cielo Multi-Family Condos WEST
SP Revision #1 - DRC Comments
<image002.jpg>
October 6, 2021
Caddis Engineering & Land Surveying, P.C.
226 Timberline Dr.
Bozeman, MT 59718
RE: 21290 Gran Cielo Multi-family Condos WEST SP –
Revision #1
Dear Applicant,
The Department of Community Development deemed
your application for Gran Cielo Multi-family Condos
WEST SP Revision #1 (#21290) acceptable for initial
11
review on September 22, 2021. Community
Development Staff has reviewed the application in
accordance with the submittal checklists and Article
38.220 of the Unified Development Code and at this time
the application includes elements that are inadequate
for continued review. Therefore, the application has
been deemed inadequate for further review.
City staff have identified items that require correction
and/or additional information and can be found in the
document attached in this email.
Corrections and revisions are required for the application
to be adequate for continued review. Please submit
these revisions to the Planning Department digitally,
accompanied by a Revision and Corrections (RC) form .
The digital copy must include all application documents,
not only the updated documents.
To submit revisions, please contact our Community
Development Technicians
at planningtech@bozeman.net . They will provide you
with a cloud link to resubmit your revised application
packet. Once a revised application is received City staff
will again review the application for adequacy. They will
determine whether the application is adequate to
proceed in the development review process.
If you have any questions in regards to this review, please
contact both your Planner and Development Review
Coordinator.
Development Review Coordinator
Diane Tolhurst
dtolhurst@bozeman.net
406-285-2938
Planner
Danielle Garber
dgarber@bozeman.net
406-582-2272
Diane Tolhurst | Development Review Coordinator,
Community Development
City of Bozeman | 20 East Olive St. | P.O. Box 1230 |
Bozeman, MT 59771
P: 406.582.2938 | C: 406.451.6248 |
E: dtolhurst@bozeman.net | W: www.bozeman.net
City of Bozeman emails are subject to the Right to Know provisions of
Montana’s Constitution (Art. II, Sect. 9) and may be considered a “public
record” pursuant to Title 2, Chpt. 6, Montana Code Annotated. As such,
12
this email, its sender and receiver, and the contents may be available
for public disclosure and will be retained pursuant to the City’s record
retention policies. Emails that contain confidential information such as
information related to individual privacy may be protected from
disclosure under law.
City of Bozeman emails are subject to the Right to Know provisions of
Montana’s Constitution (Art. II, Sect. 9) and may be considered a “public
record” pursuant to Title 2, Chpt. 6, Montana Code Annotated. As such,
this email, its sender and receiver, and the contents may be available
for public disclosure and will be retained pursuant to the City’s record
retention policies. Emails that contain confidential information such as
information related to individual privacy may be protected from
disclosure under law.
City of Bozeman emails are subject to the Right to Know provisions of
Montana’s Constitution (Art. II, Sect. 9) and may be considered a “public
record” pursuant to Title 2, Chpt. 6, Montana Code Annotated. As such,
this email, its sender and receiver, and the contents may be available
for public disclosure and will be retained pursuant to the City’s record
retention policies. Emails that contain confidential information such as
information related to individual privacy may be protected from
disclosure under law.
City of Bozeman emails are subject to the Right to Know provisions of Montana’s
Constitution (Art. II, Sect. 9) and may be considered a “public record” pursuant to Title
2, Chpt. 6, Montana Code Annotated. As such, this email, its sender and receiver, and
the contents may be available for public disclosure and will be retained pursuant to the
City’s record retention policies. Emails that contain confidential information such as
information related to individual privacy may be protected from disclosure under law.
City of Bozeman emails are subject to the Right to Know provisions of Montana’s Constitution (Art. II,
Sect. 9) and may be considered a “public record” pursuant to Title 2, Chpt. 6, Montana Code Annotated.
As such, this email, its sender and receiver, and the contents may be available for public disclosure and
will be retained pursuant to the City’s record retention policies. Emails that contain confidential
information such as information related to individual privacy may be protected from disclosure under
law.
<01 21290 DRC Memo.pdf>
City of Bozeman emails are subject to the Right to Know provisions of Montana’s Constitution (Art. II, Sect. 9) and may
be considered a “public record” pursuant to Title 2, Chpt. 6, Montana Code Annotated. As such, this email, its sender
and receiver, and the contents may be available for public disclosure and will be retained pursuant to the City’s record
retention policies. Emails that contain confidential information such as information related to individual privacy may be
protected from disclosure under law.