HomeMy WebLinkAboutResolution 3287 Authorize City Manager to sign CO#1 for 1998 sewer improvements
COMMISSION RESOLUTION NO. 3287
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF BOZEMAN,
MONTANA, APPROVING ALTERATION/MODIFICATION OF CONTRACT
WITH PLANNED AND ENGINEERED CONSTRUCTION (PEC), INC., HELENA,
MONTANA.
WHEREAS, the City Commission did, on the 6th day of July 1998, authorize award
of the bid for 1998 sanitary sewer improvements to Planned and Engineered Construction
(PEC), Inc., Helena, Montana; and
WHEREAS, Section 7-5-4308, Montana Code Annotated, provides that any such
alterations or modifications of the specifications and/or plans of the contract be made by
resolution; and
WHEREAS, it has become necessary in the prosecution of the work to make
alterations or modifications to the specifications and/or plans of the contract.
NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of
Bozeman, Montana, that the proposed modifications and/or alterations to the contract
between the City of Bozeman, a municipal corporation, and Planned and Engineered
Construction (PEC), Inc., as contained in Change Order No.1, attached hereto, be and the
same are hereby approved; and the City Manager is hereby authorized and directed to
execute the contract change orders for and on behalf of the City; and the Clerk of the
Commission is authorized and directed to attest such signature.
PASSED AND ADOPTED by the City Commission of the City of Bozeman, Montana,
at a regular session thereof held on the 3rd day of May 1999.
~/m~
ALFR M. STIFF, Mayor
ATTEST:
~ ;!d/~~
ROBIN L. SULLIVAN
Clerk of the Commission
RECEIVED iljAH
3 " 'i88S
CHANGE ORDER
ORDER NO. 1
DATE 2/1/99
AGREEMENT DATE: August 18r 1998
NAME OF PROJECT 1998 Sanitary Sewer Improvements
OWNER City of Bozeman
CONTRACTOR P.E,C'r Inc.
The following changes are hereby made to the CONTRACT DOCUMENTS:
586 lineal feet of additional 8" lining work. 406 lineal feet of 10" lining work. Reinstate 62
service, internally.
Justification: Budget available to perform additional work
Attachments: Letter from City of Bozeman to TD&H, 8/18/98. Letter from P.E.C. to TD&H, 8/27/98.
Original CONTRACT PRICE: $ 111 r647.40
Current CONTRACT PRICE adjusted by previous CHANGE ORDER:$ 111 r647.40
The CONTRACT PRICE due to this CHANGE ORDER will be (increased) by:
$ 46r636.00
The new CONTRACT PRICE including this CHANGE ORDER will be $ 158r283.40
CHANGE of CONTRACT TIME: N/ A
The CONTRACT TIME will be (increased)(decreased)by N/ A calendar days.
The date for completion of all work will be unchanged from original .
R=mmendoo~~~l- ~;~~
Ordered by: t P. E,C) '). I i
Accepted by: \- -l
S _dVobs\B96-24\OITcDocs\Chageorl.wpd