HomeMy WebLinkAboutLessthanOneAcreConstructionPermit_03-03-21 Stormwater Division
B O Z M A N MT Construction Stormwater Permit P.O.Box 1230
Sites Less than One(1)Acre Bozeman,Montana 59771
MarM1,2019 (406)582-2270
The City requires all multi-family, commercial, utility, demolition, and paving projects less than one acre to submit this
application and receive an approval letter before initiating construction activities pursuant to Chapter 40 Article 4 of the
Bozeman Municipal Code. The City's Stormwater Division reviews, inspects, and enforces all provided information. This
Permit is active once approved by the City and terminated upon the receipt of a Certificate of Occupancy.
Section 1—Applicant Information
1. Preparer:Derek Dennehy Company:Madison Engineering
Phone:406-586-0262 Email:derek@mad-eng.com
Address:895 Technology Blvd, Ste 203 City:Bozeman I State:MT Zip code:59718
2. Owner:Justin Tribitt Company:Four Fly Fellows LLC
Phone:406-539-1062 Email:justin@third-street.net
Address:4768 Victory St City:Bozeman State:MT Zip code:59718
3. Contractor:Nick Brunner Company:Cutbank Construction, LLC
Phone:406-579-6998 Email:brunedawgl2@gmail.com
Address:PO Box 10231 City:Bozeman State:MT Zip code:59719
Section 2—Project Information
Project Name:The Flats Total Land Disturbance (Square Feet):18,295
Project Address:3762 Galloway St. Bozeman, MT 59718 Project Type:Live-Work Development
Section 3—Project Schedule
Start Date:05/10/21 7Final Stabilization Date:06/06/22
Section 4—Site Map
1.Applicant must include a sitemap(s)showing each of the following:
• Project boundary
® Direction(s) of stormwater run on and runoff
• Public and private stormwater infrastructure on or adjacent to site
• Material storage and equipment staging area(s)
01 BMPs selected in Section 5
Natural Resources Areas (if applicable)
Section 5—Local Erosion and Sediment Control Requirements
**Please use the City of Bozeman's Best Management Practice(BMP) Manual to select controls.**
1. Control disturbed areas: Project boundaries require BMPs that control stormwater flowing from disturbed areas
pursuant to §40.04.360.B. BMC. **Low to grade is not an approved option** Approved options:
N Silt Fence
❑Foam or Straw Wattle
❑Other:
2. Mitigate tracking: Exit points require BMPs that mitigate the tracking of debris off-site onto the right-of-way
pursuant to §40.04.360.C. BMC.Approved options:
71 Cobble/Cattle Guard Hybrid Track Pad
Angular Rock Track Pad
El Proprietary Tracking Control Product
Other:
3. Control concrete waste,slurry,and other masonry wash waters:Concrete activities require BMPs that allow for the
capture and disposal of generated pollutants pursuant to§40.04.360.F. BMC. Approved options:
0 Reusable or Disposable Product
❑Prefabricated Roll-Off
❑Below or Above Ground Containment
❑Other:
4. Manage material stockpiles: Material stockpiles, not already contained within an existing perimeter control,
require perimeter BMPs that control stormwater flowing from disturbed areas or an erosion control BMP that
prevents displacement of loose material pursuant to §40.04.360.A. BMC. Approved options:
❑•Silt Fence
❑Foam or Straw Wattle
❑Cover/Tarp
❑Within Existing Perimeter Control BMP
❑Other:
i
5. Manage dewatering flows: Pumping activities that discharge into infrastructure or waterways are MDEQ
permitted activities and as such are required to meet the effluent limitations in the MDEQ General Permit for
Construction Dewatering pursuant to 40.04.360.B. BMC, Montana Clean Water Act, and Federal Clean Water Act.
Approved options:
❑Land Application
0 Well Point
❑Flocculent or Filter Treatment System
❑Other:
6. Stabilize disturbed areas: Disturbed areas require BMPs that prevent erosion of barren ground pursuant to
§40.04.360.A. BMC.Approved options:
❑Crimped Straw Mulch or Wood Mulch
N Hydroseed
❑Sod
❑Other:
7. Protect inlets: On-site inlets receiving site runoff require BMPs that filter stormwater before flowing into
underground infrastructure pursuant to§40.04.360.C. BMC. **Rock bags are not an approved option** Approved
options:
M Pre-Manufactured Drop Inlet Protection
Other:
Section 6—Administrative and Operational Controls
1. Check which of the following will be utilized:
N Street Sweeping: Frequency:Weekly
00 On-Street Parking
Eal Spill Kit, including absorbent material, cleanup tools,and covered waste container
section 7—Acknowledgment Certificate
I certify that I am the contractor/owner or an authorized agent. If acting as an authorized agent, I certify that I am
authorized to act as the contractor/owner agent regarding the property at the above-referenced address for the
purpose of filing applications for decisions, plans, or review under Chapter 40 Article 4 of the BMC and Ordinances
#1763 and #2002, and have full power and authority to perform on behalf of the contractor/owner all acts required to i
enable the City to process and review such applications. I certify that the information on this application is true, will be
implemented, and maintained throughout the life of the project.
0 By checking this box, I acknowledge that non-compliance with this Permit, aforementioned BMC, and City
Ordinances may result in a stop work order, city withholding a certificate of occupancy, or a lien filed against the
project for unpaid costs of abatement of violations.
Signature L gally Responsible Person Date
Printed Name Title
\ \ VAQUERO PARKWAY M
*STREET SWEEPING TO
SF r�� ���� INLET PROTECTION OCCUR ON A WEEKLY BASIS
j (TYP)
y SF
TDzE�
F_
0
PROPERTY r SF -
LINE i� Ln
I
SF / °°°° ■
— — — — — — — — SF
r = IP GROUNDWATER DEWATERING TO n�.,T II it s
BE PIPED TO ON—SITE
RETENTION SYSTEM i --
r Xr r
° -
LIMITS OF r
s SM r SM ° °°O S F SM SSM S
Sd 53�Sd` sy�. Sdn —//---- ---- --- J I U
DISTURBANCE £
SF ------ ; NT °° El El *2 VEHICLE TRACKING o
I CONTROL
15----r-
��
nP� Lt� / unLLinii _ niuiiiiii Co
Co
eN _ *DESIGNATED CONSTRUCTION
� I
ENTRANCE
r ❑❑ ❑❑
SF
-- --- --- -- — — -- -- --- ---
N
SIE S GA:�� —.GABS GAS GAS �—Gi SF —.GAS �SjA A- GASPGAS.
EXT'G PARKING LOT
V)
NOTES: THE FLATS: STflRMWATEE EROSION CONTROL LEGEND
1. CONTRACTOR SHALL MAKE ALL NECESSARY EFFORTS TO PREVENT CONSTRUCTION PLAN —SF— SILT FENCE 3
SEDIMENT FROM LEAVING THE SITE. 1. INSTALL EROSION CONTROL MEASURES AS NOTED ON —VB— VEGETATIVE BUFFER
2. EROSION CONTROL MEASURES SHALL REMAIN IN-PLACE UNTIL VEGETATION THIS SITE PLAN PRIOR TO PERFORMING ANY WORK.
HAS ESTABLISHED AND THERE IS NO RISK OF SEDIMENT RUN-OFF. LIMITS OF DISTURBANCE
2. CONSTRUCTION TRAFFIC TO ENTER FROM NORTH
3. THIS EROSION CONTROL PLAN SHALL BE USED IN CONJUNCTION WITH THE BOUNDARY OF PROJECT SITE USING DESIGNATEDCONSTRUCTION ENTRANCE. STREET SWEEPING SHOULD GRAVEL CONSTRUCTION ENTRANCE
STORM WATER POLLUTION PREVENTION PLAN FORM (SWPPP). BE COMPLETED ON ALL STREETS IMPACTED BY ` � 7
CONSTRUCTION.
4. GENERAL CONTRACTOR IS RESPONSIBLE FOR ASSURING EROSION CONTROL CURB INLET PROTECTION
0
MEASURES ARE IN CONFORMANCE WITH THE SWPPP. CLEAR COMMUNICATION N
BETWEEN THE CONTRACTOR AND SWPPP ADMINISTRATOR IS CRUCIAL FOR MATERIAL STORAGE AND STOCKPILE SCALD o
MAINTAINING COMPLIANCE WITH THE GENERAL PERMIT FOR STORMWATER `V
DISCHARGES ASSOCIATED WITH CONSTRUCTION ACTIVITY. UNANNOUNCED *2 CONCRETE WASHOUT 0 15, 30 60' o
VISITS BY THE AUTHORITY MAY OCCUR. o
R WATER FLOW DIRECTION Q
5. DO NOT ALLOW DISTURBANCE OUTSIDE OF THE LIMITS OF DISTURBANCE. 1 inch= 30 FEET j
6. SOIL STOCKPILE MUST BE TEMPORARILY STABILIZED IF INACTIVE FOR 14
DAYS. COVERING OR SURFACE ROUGHENING IS APPROPRIATE. THE FLATS FIGURE A
7. CONTRACTOR TO MAINTAIN GOOD HOUSEKEEPING PRACTICES INCLUDING �11� 11���f��y 1� l� ADISON ENGINEERING DRAWN BY: DAD
WORKER WASTE PICK UP. S Jl ®J[ M �Y�Y ATER SITE MAP 895 TECHNOLOGY BLVD.STE 203,BOZEMAN,MT 59718
B®ZEMAN MT PHONE(406)586-02621FAx(406)586-7357 DATE: 03/03/21
8. SPILL KIT TO BE KEPT ON SITE IN JOB/STORAGE TRAILER. 9 PROJECT# 20-113