HomeMy WebLinkAbout21- Contract Extension - Sourdough Fuels Stage 1 September 24, 2021    Davy Sheets  DS Jr. Trucking, Inc.  189 Howie Rd  Big Timber, MT  59011       SENT VIA EMAIL: sheetstrucking@hotmail.com    RE:  Contract Extension    Phase 1 Sourdough Fuels Reduction Project    Dear Davy,    As you know, the Phase 1 Sourdough fuels project contract terminates on September 30, 2021.   Contract term extensions are allowable under Section I.E of the contract.  This letter addresses  the specific circumstances underscoring the need for an extension and requirements of the  contract that must be met to allow for an extension.    The contract states that extensions shall be of last resort.  This is due to grant funding deadlines  faced by the City, and that the Phase 2 Sourdough fuels contract cannot be completed as bid  without Phase 1 having been completed first.  The Phase 2 contract was signed by R&R Conner  Aviation on September 21, 2021.    The City hereby determines that an extension of the Phase 1 contract is in its best interests.   Montana experienced exceptional drought conditions this year that began early and persisted  late, leading to an early and prolonged fire season.  Existing fuel loads in Sourdough watershed  create a hazardous situation that puts the City’s drinking water supply at risk.  The Phase 1 and  Phase 2 fuels projects help protect the City’s Sourdough Creek municipal water supply by the  removal of hazardous fuels.  The City notifies you that a contract extension for Phase 1 is  required to allow for Phase 2 of the fuels project to be completed this operating season.      In early July, soon after the Phase 1 contract was executed, you mobilized roadbuilding  equipment to the project area.  Just one day after equipment arrived it was dispatched to the  Alder Fire at Wise River.  The Alder Fire was designated the highest priority fire in Montana  while you were on it.  On September 7, you made a request for contract extension via personal  text communication to the City.  This extension was not based on poor log and/or market  conditions, but rather your assignment to the Alder Fire.  Soon thereafter, you were released by  incident command from the Alder Fire and shifted your road building resources to the Phase 1  contract.  As of the date of this letter, the roadwork is complete and timber removal is soon to  follow.  The City recognizes your return to the Phase 1 contract, completion of the road, and  pending start of timber removal as a good faith effort to complete the project.  We understand  that the delay in returning to the project and the related extension request resulted from  matters beyond your control.  DocuSign Envelope ID: 5ECEB333-9459-4757-A139-65F69A1C3E83   The City hereby waives the contract requirement for the extension request to be made in  writing at least 30 days prior to the September 30, 2021 termination date.  The City will hold the  $2,000 cash performance bond provided for the contract through the extension date.  As you  will recall, we agreed to hold the $2,000 cash bid security provided for the contract as your  performance bond.    The City will allow a contract extension date of October 31, 2021.  This extension is formalized in  the Contract Modification that accompanies this letter.  The contract extension is not effective  until the contract modification is fully executed.  Please sign and remit to me at the P.O Box  below.    Sincerely,      Brian Heaston, PE  Senior Engineer  DocuSign Envelope ID: 5ECEB333-9459-4757-A139-65F69A1C3E83 30thSeptemberDocuSign Envelope ID: 5ECEB333-9459-4757-A139-65F69A1C3E83