HomeMy WebLinkAboutSPRCommentResponses_04142021
MEMORANDUM
----------------------------------------------------------------------------------------------------------
FROM: DANIELLE GARBER, ASSOCIATE PLANNER
DEVELOPMENT REVIEW COMMITTEE
RE: ONE 11 2.0 SITE PLAN, APPLICATION 20456
DATE: MARCH 17, 2021
----------------------------------------------------------------------------------------------------------
Project Description: An addition to the constructed One 11 building for 67 new units
with a shared lobby, bike/ski storage, structured parking that will connect to One 11
1.0, and share a common open space courtyard on level 2. Additional surface parking
is also proposed in the adjacent lot to the southwest with access, landscaping, striping
and other improvements. The project site is zoned B-3, Downtown District.
Project Location: Southwest of the corner of W. Beall St. and N. Willson Ave. and is
legally described as Tracy’s 3rd Add, S07, T02 S, R06 E, Block B, Lot A, Plat J-198
Recommendation: Staff has found that the application does not comply with the
requirements of Chapter 38 of the Bozeman Municipal Code (BMC) and is deeming
the application inadequate for further review.
Section 2 – Conditions of Approval
Please note that these conditions are in addition to any required code provisions
identified in this report. The following conditions are specific to the development:
1. The applicant is advised that unmet code provisions, or code provisions that
are not specifically listed as conditions of approval, does not, in any way,
create a waiver or other relaxation of the lawful requirements of the
Bozeman Municipal Code or state law. Acknowledged.
Section 3 – Required Code Corrections
PLANNING COMMENTS:
1. Process –
a. Provide an application fee payment for the 1 departure requested
from Section 38.510.030. If additional departures are requested with
resubmittal provide fee payment for the total number of departures.
Payment has been made.
b. A lot aggregation, as proposed by the applicant, is supported by staff
and will simplify review and entitlement of the project. This can be
submitted and reviewed concurrently with the site plan application.
The amended plat must be approved and recorded prior to final
approval of this application. This can be listed as a condition of
approval. Acknowledged.
c. The master site plan must be approved prior to final approval of this
application. This can be listed as a condition of approval.
Acknowledged.
d. Design Review Board (DRB) review is required. This meeting will be
scheduled once the project reaches adequacy and public notice can be
scheduled. Acknowledged.
2. Comments for new lots added – Preliminary drawings to add the lots to the
southwest of the project area were received 3/2/21. If moving forward with
the addition of this area to the site plan submittal staff recommends the
following:
a. Provide revised documents, studies, calculations, and drawings across
the entire submittal showing the added project area. These will be
provided.
b. A demolition application is required to be added to this submittal to
remove the current non-eligible office building. Records indicate this
structure was constructed in 1955. An updated Montana historic
property record inventory was completed in 2014 and can be found
on our website. The property record has been located and a
demolition application will be submitted with the site plan RC
submittal.
c. The addition of this new area adds additional block frontage and
building design requirements for the existing building, new building,
and new parking lot. Provide a response to these review criteria in the
revised submittal including but not limited to parking location
(possible departure request) and blank wall requirements. An
additional narrative has been crafted to address these requirements.
d. Provide a calculation for the addition of compact spaces to the site
(25% max). These have been identified in the plan and added to the
project matrix.
e. Provide a landscaping plan showing appropriate parking lot
screening, and landscaping within the new parking area. An updated
landscape plan has been provided.
f. Will an entrance to the building be added from the new parking area?
Yes, an additional door was added giving residents utilizing the
surface parking lot access to the One 11-2.0 parking garage. See the
updated architectural level 1 plan.
g. Discuss plans to preserve any existing trees on the site. This intent
will be indicated in the annotations at the landscape plan and
demolition exhibit.
3. Overlay District Standards – BMC 38.340.050.D.
a. Section J in the narrative mentions site furnishings as guest bike
parking and benches, is that referring to site amenities at the 1.0 site?
No details were found in the landscaping sheets. The language in
Section J has been updated to reflect the correct intent for site
furniture.
b. Section G in the narrative states that planting strips will be
maintained to keep with the existing design of the streetscape.
Forestry does not support the use of steel planter boxes in the right of
way (see below). Staff recommends ground level planting strips
adjacent to street trees along W. Beall Street. A revised design has
been provided for the streetscape landscaping and approval has been
given from Forestry to support the use of steel planter boxes. See
detail 10 on sheet L500.
4. Mixed – Storefront Block Frontage Standards – BMC 38.510.030.B. Façade
Transparency – Physical glazing samples or photos of physical glazing
samples demonstrating transparency are required for all window types that
contribute to the transparency calculation. A photo of the physical glazing
sample has been provided in the RC submittal documents.
5. Mixed - Landscaped Block Frontage Standards – BMC 38.510.030.D.
a. Building Placement – Staff supports the departure from the 10-foot
setback following the Special Residential transition elements detailed
in 38.510.030.J.1 – Raised deck or porch option. Acknowledged.
b. Façade Transparency – Residential buildings at least 15% of the
entire façade facing the street. Revise the transparency calculations
provided on the elevation sheets to reflect the 15% standard for
residential buildings for the Mixed-Landscaped portion of the façade.
An additional row has been added to calculate the transparency
calculations on the mixed-landscape portion of the façade.
6. Open Space – BMC 38.520.060.B.4.b. Indoor recreational areas used to meet
open space must meet the following: The space must be designed specifically
to serve interior recreational functions and not merely be leftover unrentable
area used to meet the open space requirement. Such space must include
amenities and design elements that will encourage use by residents. Provide
more details for the bike/ski storage and workshop to confirm usability as an
open space area. Additional details have been provided in the architectural
drawings to show how the bike workshop supports the definition of Indoor
Recreation spaces to comply with open space requirements.
7. Building Materials – BMC 38.530.060. Provide a manufacturers detail or
cutsheet specifying gauge of corrugated metal siding. Cutsheet has been
provided in the documents portion of the submittal.
8. Parking – BMC 38.540.050. Remove reductions not being utilized but still
listed in the parking calculation matrix. Provide bicycle storage and rack
details in the interior bicycle/ski shop room and parking garage showing the
22 bicycle parking spaces stated in the calculation. These details have been
provided in the architectural sheets.
9. Landscaping – BMC 38.550.050. Numbers 3 and 6 in the code summary on
sheet L000 will need to be updated with resubmittal. Number 3 refers to
surface parking (if adding the surface parking area), and number 6 refers to
utility meter screening. See Northwestern Energy Comments below.
Note 3 was updated to include the parking lot information.
Note 6 refers to utility screening which will be accomplished within the building.
The gas service will utilize the existing One 11 meter located on Willson which is
already screened.
10. Signs – BMC 38.560.060. The non-conforming projecting sign present on the
One 11 1.0 building will need to be removed. This can be a condition of
approval. Acknowledged.
11. Lighting – BMC 38.570.060.G.7. The photometric plans for the building
accent lighting on the elevations do not show any light output (all 0.0), please
provide clarification. The electrical sheets have been updated to address this
comment. The photometrics on the elevations display 0.0 on the upper levels
is that the only light fixtures higher than the main level are residential units.
Since these are controlled by the tenants we have excluded all of the
residential tenant lights from the calculation. All fixtures comply with dark
sky requirements.
Advisory Comments:
1. See attached comments from Water Conservation Technician Chelsey
Trevino, ctrevino@bozeman.net. All responses have been addressed with
those comments.
ENGINEERING COMMENTS, Karl Johnson, kajohnson@bozeman.net:
2. See Attached Memo All responses have been addressed with those
comments.
SOLID WASTE, Russ Ward, rward@bozeman.net:
1. If using trash room it will need to be written into covenants that it is building
management’s responsibility to move refuse container to the designated
trash tipping area. Acknowledged.
2. Pad for tipping refuse containers will need to be heated. This has been shown
and annotated at the architectural site plan.
3. Tipping pad will need to be at street level with no curbs to drive over.
Acknowledged.
BUILDING, Ben Abbey, babbey@bozeman.net:
1. 2% of all dwellings to be Type A units in accordance with the IBC & ICC
A117.1-2009. This has been provided and will be included in the code plans
and review submitted with the Building permit drawings.
2. All remaining dwellings will be required to be Type B units in accordance
with the IBC & ICC A117.1-2009. This has been provided and will be included
in the code plans and review submitted with the Building permit drawings.
3. Parking garage will require Ventilation Per the IMC Acknowledged.
4. Structural, Plumbing, Electrical, and Mechanical drawings to be prepared by
specific engineer with seal. Acknowledged.
5. Sprinklers and alarms system. Will be provided and detailed via a
performance spec as connecting to the 1.0 facility.
6. Grease interceptor per business if multiple restaurants are built in the TI
space. Confirmed, no restaurants are currently proposed at the TI space.
FIRE DEPARTMENT, Scott Mueller, smueller@bozeman.net
1. Fire generally supports as proposed. Acknowledged.
2. Fire sprinklers, fire alarms, and fire standpipes are required. These will be
provided.
3. Fire hydrant shall be within 100 feet of FDC for standpipes. See civil sheets at
building permit submission for fire hydrant locations.
4. Emergency generator is required.
According to IBC 2018, 1009.2.1, exception 1 – the elevator is not required as
an accessible means of egress because the building is providing a horizontal
exit, and therefore an emergency generator is not required. In lieu of
providing emergency/standby power to the elevator, a 2 hr fire barrier
horizontal exit is provided on floors 2-5.
5. Enclosed parking garages will need to meet all venting and air monitoring
requirements. Acknowledged.
FORESTRY, Alex Nordquest, anordquest@bozeman.net
1. Raised steel planter beds are not acceptable for boulevard trees. 4’ x 4’ tree
pits at grade, including cast iron grates and trunk collars, are standard for
non-turf boulevards.
The raised planters are 6” concrete curbed landscape beds. See detail
10/L500. These were approved by Alex Nordquest after the intent and
design of the planters was clarified.
PARKS AND RECREATION, Addi Jadin, ajadin@bozeman.net
1. Parks comments pending. CIL Parkland comments have been confirmed by
Addi Jaden and the confirmation email has been included in the RC
submission.
NORTHWESTERN ENERGY COMMENTS, Tom Stewart, District Engineer,
thomas.stewart@northwestern.com, 406-582-0573:
20456 One 11 - 2.0 SP, NWE Project Engineer Kory Graham
Kory.Graham@northwestern.com
• Continue to work with NWE project engineer Kory Graham on gas and
electric utilities. If relocating utilities from overhead to underground,
building over-dig, near all proposed utility locations, is a concern.
• Per comment response for item #10 under Planning Division comments your
response was;
A utility gate will be utilized at the Grand façade to permit access to the utility area.
The design of this gate has been provided in the exterior elevation sheets.
Per screening utility meters the following applies to such screening;
If using a screening wall a drawing of the screening wall need to be reviewed and
approved by NWE for underground utility installation under the wall and access for
operation and maintenance lines and equipment. The meters at this project are
being screened by the building walls, but openings are provided to keep the area
“open-air”. The utility gate details have been provided in the architectural drawing
sheets included in this submission.
Screening Walls.
o Gas service cannot penetrate foundation walls that are attached to the
building foundation per the International Fuel Code. Gas riser need to
penetrate the building above ground. However, if the foundation is not
attached to the building i.e. the foundation wall is isolated from the building
for just supporting the wall, this is acceptable.
o If this is a free standing foundation wall, a knock-out must be provided that is
a min of 2’x2’ but may be required that the knockout be larger on the electric
service depending on the meter base amperage. Consult NWE for proper
sizing of knock-out
o Contact NWE for placement of knock-out to insure that it lines up properly
with the termination location to prevent bends in the service
o Screening must meet the clear zone requirement of NWE Electric Service
Requirements which typically for commercial application is 48” from the face
of the electric meter.
o Gas meter cannot be located in recessed location where it is not open
atmosphere above the meter without approval from NWE.
o Screening cannot consist of rolling doors or other devices that are required
to be open to access the meters.
Future Impact Fees - Please note that future building permit applications will require
payment of the required transportation, water, sewer and fire impact fees according
to the City of Bozeman adopted impact fee schedule in place at the time of building
permit issuance. If you desire an estimate of the required impact fees according to
current rates please contact the Department of Community Development and/or visit
www.bozeman.net.
Note: With this memo, Staff has found the application to be inadequate for
continued review. During review of subsequent revisions, additional
conditions of approval may be recommended based on comments and
recommendations provided by other applicable review agencies involved with
the review of the project.
MEMORANDUM
------------------------------------------------------------------------------------------------------------
TO: Danielle Garber, Associate Planner
FROM: Karl Johnson, Engineer I
RE: APPLICATION NO 20456 – One 11 2.0 Site Plan
DATE: March 19, 2021
-----------------------------------------------------------------------------------------------------------
ENGINEERING COMMENTS:
Easements
1. BMC 38.410.060 Easements - Front setback utility easements must be ten feet wide, and must
always be provided unless written confirmation is submitted to the community development
department from all utility companies providing service indicating that front setback easements
are not needed.
The applicant is working with Northwestern Energy to relocate the existing overhead power and
communication lines underground along Beall. Once this is resolved written confirmation of the
solution will be provided to the City regarding required easements. Based on recent discussions
Northwestern Energy is requesting a 12’ utility easement along the Grand Avenue frontage for
new underground utilities required to serve the One 11 2.0 building, and a 3.5’ easement along
the Beall Street frontage for the relocation of existing overhead utilities to underground.
2. DSSP V.D - Permanent structures or significant landscaping may not encroach on utility
easements or be within 10 feet of utility mains and services.
Once the final location of the relocated underground power and communication lines
this issue will be addressed. If trees will not be allowed to be within 10’ of the
relocated utility lines, the proposed planting bed will contain only shallow rooted
plantings. Like other street boulevard landscaping, planting beds will be maintained
by the adjacent landowner.
Water Rights
1. BMC 38.410.130 (A) (1) Water rights - The applicant must contact Griffin Nielsen with the City
Engineering Department to obtain a determination of cash-in-lieu of water rights (CILWR).
CILWR must be paid prior to respective site plan approvals.
This has been completed, see attached email from Griffin. The engineering report has
been revised to display the City approved values.
Stormwater
1. Montana Post-Construction Storm Water BMP Design Guidance Manual The applicant must
demonstrate that seasonal high groundwater will not impact the function or maintenance of the
proposed facilities. Industry guidance recommends a three-foot minimum separation from the
bottom of the proposed facility to the underlying groundwater table. The applicant must
provide local seasonal high groundwater elevations to support the proposed design.
Groundwater monitoring was conducted by the geotechnical engineer in 2018 and 2019. The
groundwater monitoring results are provided in the geotechnical report included with this
submittal. The measured seasonal high groundwater for Borehole #3 (adjacent to One 11 2.0) is
12’ below ground surface. The bottom of the stormwater chambers are approximately 5’ below
ground surface or 7’ above seasonal high groundwater.
2. DSSP II.B. Storm Drainage Plan - The existing stormwater flow patterns are being changed from
the historic patterns in the area:
a. One 11 2.0 Building stormwater is being redirected into Beall Street storm drain that
was previously flowing north on Grand.
The building stormwater has been revised to overflow to the curb inlet in Grand
Avenue to maintain existing flow patterns.
b. The applicant has indicated permeable pavers will be used in public road ROW.
Stormwater management systems are not allowed within public ROW.
The permeable pavers at One 11 2.0 are meant to provide the same function
as a grassed boulevard, but with an all-weather walking surface that provides
a more functional urban streetscape. The only stormwater management
provided by the pavers is that of a grassed boulevard, which is infiltration of
sidewalk runoff and snowmelt from within the public road ROW. On-site
runoff is mitigated by the subsurface retention system.
The permeable pavers are only providing stormwater management for the
public ROW and thus are completely appropriate within the ROW.
c. The applicant must provide a map identifying square foot coverage of the various
ground surfaces.
The storm drainage calculations have been revised to include the added surface
parking lot. The drainage basins are separated into a building drainage basin and
surface parking lot drainage basin. Both of these drainage basins are dominated
by large impervious areas (building and parking lot). The stormwater systems
are designed to retain approximately 1” storm events, well above City
requirements. Detailed mapping of pervious areas that do not significantly
contribute to storm runoff is superfluous.
d. Proposed maintenance of proposed permeable pavers does not allow stockpiling of
snow on the pavers which the applicant has indicated they intend to utilize for snow
storage.
The permeable pavers are intended to allow infiltration of snowmelt like a grassed
boulevard. The stormwater maintenance plan has been updated to correct this
obvious error.
The applicant must provide a detailed analysis evaluating impacts of changing flow patterns in
the area to downstream infrastructure and discharge receiving bodies.
The building stormwater has been revised to overflow to the curb inlet in Grand
Avenue to maintain existing flow patterns.
3. BMC 38.540.020 – Snowmelt must not drain offsite. Confirm snow storage runoff will be
retained and treated onsite.
The snow storage areas shown are for the snow removed from the off-site public ROW.
On-site snow will remain on the building rooftop and snowmelt will be captured by the
on-site system. Awning downspouts will also be piped to the on-site system. This
feature has been added to the plans.
Additional on-site snow storage areas for the surface parking lot are shown in the
revised plans. The parking lot snow storage areas include drainage inlets to capture
snow melt and infiltrate it on-site.
4. Sand/oil separators must be utilized in all parking structures.
A sand/oil separator has been added to the plans for the parking structure for the garage floor
drains. Due to higher flow rates, a Vortechs separator is proposed for pretreatment of the runoff
from the surface parking lot.
Water and Wastewater
1. DSSP V.A.6.a – A waterline serving more than one building is or facility is considered a water
main
a. The water service to One 11 does not meet the requirements of a water main therefor
would not be allowed to be used for multiple buildings. The applicant must make a
separate water service connection to the proposed building.
One 11 2.0 is an addition to the existing One 11 building, not a separate building.
Accordingly, use of the existing service for One 11 is an acceptable option.
2. 38.410.070. and DSSP.V.A and B – Prior to a determination of adequacy the applicant must
provide an estimate of the peak-hour sanitary sewer demand as well as the average and max
day demands of domestic water usage for the proposed site development. The estimates must
be certified by a professional engineer.
a. Sewer demand calculations must use 65 gallons-per-capita-per-day and 2.17 people per
dwelling unit which equals 141.85 gpd/dwelling unit. Development is using an
estimated 50gpd/unit based on Black Olive development which does not follow COB
design standards.
The Engineering Report has been revised to use the above values for estimating peak
hour sanitary sewer demand. However, the applicant will continue to measure water
use from similar buildings in order to demonstrate the water conservation anticipated
from this type of urban development.
3. DSSP Section (V.A) Main Size - A water design report must be prepared by a professional
engineer for the proposed project. The water distribution system must be designed to meet the
maximum day demand plus fire flow and the peak hour demand.
a. The water section of the report must be updated to describe the change in water
service configuration required with comment #1 of this section.
As stated previously, One 11 2.0 is an addition to the existing One 11 building, not a separate
building. Accordingly, use of the existing service for One 11 is an acceptable option. The
City’s Water Facility Plan fire flow test data shows that fire flow can be met with the
additional building demand of 30 gpm added to the system.
4. DSSP V.A.8 Hydrants - Two fire hydrants are shown on the master site plan application at the
intersections of Beal and Wilson and Tracy and Villard. Only one hydrant is required at each
intersection. Confirm if existing hydrants are to be abandoned.
Though only one fire hydrant is required by the DSSP at each intersection, it has been our
experience that the Fire Department typically desires to have additional hydrants for areas
with large buildings, a common fire code requirement. This was recently a requirement for
the Merin building at the intersection of Bozeman and Lamme. This Master Plan element
may be revised after the fire department has reviewed buildings near these intersections.
Transportation
1. BMC 38.400.090 Access – To grant the requested access deviation for One 11. 2.0 parking
garage access on to Grand the applicant must submit a standalone memo specifically addressing
each item if BMC 38.400.090.H
A stand-alone memo addressing access deviations for surface parking accesses onto Grand
Avenue was provided to the Engineering Department on March 12, 2021. An additional stand-
alone memo for the parking garage exit is provided with this response.
2. 38.220.080 Site Plan Submittal Requirements – Traffic Impact Study (TIS):
a. The TIS must analyze the existing condition and future impacts on the North Wilson
Avenue corridor.
A TIS for the entire North Central Master Plan was provided with that master site
plan application. The TIS analyzes impacts at several intersections including the
North Willson Avenue Corridor. If the additional analysis desired can be more
concisely defined, additional information can be provided.
5. The TIS must show trip distribution on to adjacent and nearby local streets and analyze the local
intersections to determine if additional traffic control devices will be necessary.
See response above.
6. Dry utilities are not allowed in the public right of way boulevard. The applicant must work with
the city engineering department and Northwest Energy to achieve proper location of dry
utilities.
The applicant is working with Northwestern Energy and the City to determine the final
location of the relocated existing dry utilities. These existing utilities are currently located in
the public ROW. A 3.5’ easement is shown along the Beall Street frontage to provide
additional space for placing the existing overhead utilities underground. All new utilities
required to serve the One 11 2.0 addition are located outside of the public ROW in a proposed
12’ utility easement along the Grand Avenue frontage.
ENGINEERING ADVISORY COMMENTS:
Water and Wastewater
1. The applicant may be required to televise the sewer main pipe to verify the condition prior to
connection. Engineering is currently following up on maintenance activity performed due to the
age and material (vitrified clay) of the existing pipe.
Acknowledged. A similar sewer service was recently installed on this line to serve the original
One 11 building. Nothing unusual was encountered.
4. A cleanout in the landscaped right-of-way shall be provided to allow proper maintenance for
storm lines with bends.
Acknowledged. The site plan has been updated to show a clean-out on the stormwater
service just outside of the building.
5. DSSP V.A.6.h Services - Existing water services or stubs that are not utilized for service upon
development of the lot must be properly abandoned at the water main.
Acknowledged. This requirement has been added to the demolition notes on the Existing
Conditions plan since it applies to the water and sewer lines serving the MCC building.
Water Conservation DRC Comments
Chelsey Trevino – ctrevino@bozeman.net
Water Conservation Technician
March 4, 2021
One 11- 2.0 – Site Landscape and Irrigation Plan Advisory Comments
The Water Conservation Division appreciates the use of drought tolerant plant species within the development
landscape plan. The following recommendation to the One 11 – 2.0 project plan is provided to maximize landscape
health and resiliency while minimizing outdoor water consumption.
1. On sheet L600, indicate the total landscaped area (ft 2) and landscaped area of each hydrozone (ft 2) -
designated by grouping plants with similar water needs.
Notes on the area of each hydrozone were added to sheet L600. Notes to specify MSMT nozzles and to
adjust heads to minimize over-spray were also added.