HomeMy WebLinkAbout01 SW KOHD Drainage Report 05062021-JUNEDESIGN REPORT
STORMWATER MANAGEMENT
KOHD BUILDING
LOT 16, BLOCK 4
NELSON MEADOWS SUBDIVISION
Prepared for:
Plum Design Lab
3141 Foxtail Street
Bozeman, MT 59718
Prepared by:
C&H Engineering and Surveying, Inc.
1091 Stoneridge Drive, Bozeman, MT 59718
(406) 587-1115
Project Number:201196
June 2021
INTRODUCTION
The Kaufmann’s Overhead Door (KOHD)site plan consists of a 5,964 sq. ft.building and
associated improvements located on Lot 16, Block 4 of Nelson Meadows Subdivision in Bozeman,
Montana. A combination of site grading, curb and gutter,curb inlet,and a retention pond will be
used to manage stormwater runoff for the development of the site.The proposed stormwater
features were sized for the 10-year, 2-hour storm and checked for the half inch requirement.The
proposed development consists of six (6) Drainage Areas, which are shown on the Drainage Area
Map included herein.Supporting stormwater calculations are attached to this report.A Drainage
Area Map is included in Appendix A.Calculations for each individual drainage area are included
in Appendix B.Groundwater depth information is included in Appendix C.Excerpts from the
original Nelson Meadows Subdivision Stormwater Report are included in Appendix D.A
Stormwater Facilities Inspection and Maintenance Plan is included in Appendix E.
NELSON MEADOWS SUBDIVISION –STORMWATER BACKGROUND
INFORMATION
Nelson Meadows Subdivision included the construction of regional retention basins that handle
the subdivision runoff by curb and gutter and underground stormwater infrastructure designed by
Morrison Maierle, Inc.This Nelson Meadows Subdivision Stormwater Design Report did not
account for the future development of the lots within the subdivision.Instead, the subdivision
stormwater infrastructure was sized for the R.O.W.’s and portions of the existing un-developed
lots that naturally drain into the R.O.Ws.A C coefficient for existing pasture land of 0.23 was
used in the original calculations for the portions of the lots that naturally drain into the R.O.W.s.
It was determined using AutoCAD that the approximate area of Lot 16, Block 4 that was accounted
for as existing pasture land was 1.00 acres. Using 1.00 acres and a C coefficient of 0.23, the
runoff for the 10-year 2-hour storm was calculated to be 679 cubic feet. Therefore, it is acceptable
to allow 679 cubic feet of stormwater runoff to discharge off site.The remaining stormwater
generated from this development will be retained on site.
A C coefficient of 0.95 was applied to all hardscaped areas including the paved drive aisles,
parking area, sidewalks, curbing and the building. The remaining area is landscaped with wither
proposed landscaping improvements around the buildable area as well as retaining the native
vegetation (or pasture land) located outside of the buildable area. A C coefficient of 0.20 was
applied to all landscaped areas. The hardscaped and landscaped areas for each drainage area were
determined using AutoCAD Civil 3D area calculations.Each surface type is depicted with
hatching as shown on the civil site plans.It should be noted that the eastern portion of the property
beyond the 50-foot watercourse setback was not included in the drainage areas because this area
will remain unimproved.
DRAINAGE AREAS
Drainage Area 1
Drainage Area 1 consists of the northwest portion of the site including the west portion of the
parking lot,landscaping,and roof drainage footprint of the proposed building, as shown on the
Drainage Area Exhibit included herein. Runoff from this drainage area both sheet flows and flows
via curb and gutter to a proposed drywell located in the northwest portion of the site.The drywell
was sized by applying an infiltration rate for native gravel subgrades and compared to the 10-year
2-hour storm event to determine the required volume. It was found that the 10-year, 2-hour storm
governed the design and required 637 cubic feet of storage.680 cubic feet of storage is provided
in Drywell #1 including the surrounding washed rock using a void ratio of 0.3.
Drainage Area 2
Drainage Area 2 consists of the portion of the parking lot and landscaping south and southwest of
the proposed building.Runoff from this drainage area flows via curb and gutter to proposed
Retention Pond #1 located on the eastern portion of the property.A proposed curb cut allows the
water to flow into the retention pond.It was found that the 10-year, 2-hour storm governed the
design and required 1,175 cubic feet of storage.1,624 cubic feet of storage is provided in Retention
Pond #1.
Drainage Area 3
Drainage Area 3 consists of the proposed loading dock area.Runoff from this drainage area flows
from the loading dock ramps and collects within a proposed “Durslot” trench drain.The
stormwater discharges into a french drain, which consists on a subsurface 8-in perforated PVC
pipe surrounded with washed rock. Details for the Durslot drain and french drain are shown on
civil sheet, C3.2. It was found that the 10-year, 2-hour storm governed the design and required
165 cubic feet of storage. 187 cubic feet of storage is provided in this french drain system.
Drainage Areas 4
Drainage Area 4 consists of the northern portion of the proposed building.It was found that the
10-year, 2-hour storm resulted in 451 cubic feet for Drainage Areas 4.This area is allowed to
drain to Prince Lane based on the 679 cubic feet of runoff that is allowed to be discharged off site.
Drainage Area 5
Drainage Area 5 consists of the undeveloped area on the southern and southeastern portions of the
property.Runoff from this drainage area sheet flows eastward toward the existing drainage ditch
located along the eastern property boundary.It was found that the 10-year, 2-hour storm resulted
in 611 cubic feet for Drainage Area 6.Drainage Area 6 will fully contain landscaping with no
increase of impervious area. Therefore, the existing drainage pattern of the pasture land into the
existing drainage ditch will be maintained.
DEPTH TO GROUNDWATER
Groundwater monitoring was performed by Morrison Maierle in 2018 for Nelson Meadows
Subdivision. The monitoring wells nearest to Lot 16, Block 4 were used to verify that the proposed
stormwater infrastructure for is above the high groundwater table.Monitoring Well (MW)#9 had
a measured high groundwater recording of approximately 6.5 feet below ground surface in April
2018.
The existing surface at the location of the proposed drywell is about 4,595 feet, while the drywell
rim elevation is about 4594 feet. Therefore, the seasonal high groundwater will be about 5.5 feet
below the rim elevation. The profile of the proposed drywell is shown on civil sheet, C3.0 and
depicts that the structure, including the surrounding washed rock, is about 5 feet deep.As such,
the proposed underground stormwater storage systems would not be negatively impacted by
groundwater.See Appendix C for more groundwater depth information.
OFF-SITE RUN-ON CONSIDERATIONS
Stormwater run-on from adjacent properties is not expected to adversely impact this development.
The surrounding properties have a slight downgradient slope to the north and, as a result, the only
run-on would be from the adjacent properties to the south, which are currently an undeveloped
vegetated pasture. As such, the current conditions would not result is a measurable amount of
run-on to this property. Any future development of the adjacent property to the south would be
required to contain stormwater runoff within their property and not be allowed to discharge
stormwater onto this property per City code. Given the existing and potential future conditions
at adjacent properties, off-site run-on would have a negligible effect on this development.
APPENDIX A
DRAINAGE AREA MAP
APPENDIX B
DRAINAGE AREA
RETENTION SYSTEM CALCULATIONS
Lot 16, Block 4 - Nelson Meadows Subdivision
Stormwater Design Calculations
Calculate required volume Hardscape 31095Q = CiA Landscape 36596
V=7200Q Gravel 10230
Drainage Area Area (acre)C FACTOR
Hardscape 0.71 0.95
Landscape 0.84 0.20
Gravel 0.23 0.5
Total 1.79
Weighted C=0.54
***Note - The area of the 25-foot trail easement per plat (along the eastern property boundary) has been excluded from the toal site area for the purposes of the stormwater calculations.
ALL STORMWATER GENERATED ON SITETotal Area =1.79 acres
Weighted C =0.54
Rainfall intensity =0.41 in./hr.(C.O.B Design Standards 10-yr, 2-hr storm)
Runoff, Q =0.40 cfs
Volume, V =2845 ft3
Proportion of allowable C directed towards sub-division
0.23 C Factor from Morrison Maierle Stormwater Report (March 2019)
VOLUME OF STORMWATER ALLOWED TO BE DISCARGED OFF SITE INTO NELSON MEADOWS SUBDIVISION
Total Area =1.00 acres
Weighted C =0.23Rainfall intensity =0.41 in./hr.(C.O.B Design Standards 10-yr, 2-hr storm)
Runoff, Q =0.09 cfs
Volume, V =679 ft3
TOTAL VOLUME TO BE RETAINED ON SITE 2166 ft3
DRAINAGE AREA # 2
RETENTION POND 1
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft2)C * Area
Hardscape 0.95 17262 16399
Landscape 0.20 5117 1023
Total 22379 17422
A = Area (acres) 0.5138
C = Weighted C Factor 0.78
2. Calculate Required Volume
Q=CIA
V=7200Q
C = Weighted C Factor 0.78
I = Intensity (in/hr) 0.41 (10 yr, 2hr storm)
A = Area (acres) 0.51
Q = Runoff (cfs) 0.16
V = REQUIRED VOL (ft3) 1175
3. Calculate Retention Pond Volume
Modeled In AutoCAD Civil 3D 1624 (ft3)
Provided Volume Inc. Perc. (ft3)1,624
Check the half inch requirement (per DSSP II.A.4)
1. Determine Area of Hardscape within Drainage Area #2
Contributing Area Area (ft2)
Hardscape 17262
2. Calculate 1/2" runoff volume over hardscape
(aka Runoff Reduction Volume [RRV] as calculated in Montana Post-
Construction Storwater BMP Manual - Equation 3-1)
RRV = [P*Rv*A]/12
P = Water quality rainfall depth 0.50 inches
Rv = Dimensionless runoff coefficient 0.74 0.05 + 0.9*I
I = Percent impervious cover (decimal)0.77 decimal
A = Entire drainage area 0.51 acres
RRV = Runoff Reduction Volume 0.0159 acre-ft
RRV = Runoff Reduction Volume 694 cubic feet
Because the runoff volume from the 10‐yr, 2‐hr storm (for flood control) is
greater than the runoff volume produced by the half inch rainfall (for water quality)
the larger runoff volume is used (1175 cf).
DRAINAGE AREA # 4
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
Hardscape 0.95 5355 5087
Landscape 0.20 8021 1604
Total 13376 6691
A = Area (acres) 0.3071
C = Weighted C Factor 0.50
2. Calculate Required Volume
Q=CIA
V=7200Q
C = Weighted C Factor 0.50
I = Intensity (in/hr) 0.41 (10 yr, 2hr storm)
A = Area (acres) 0.31
Q = Runoff (cfs) 0.06
V = REQUIRED VOL (ft3) 451
VOLUME OF STORMWATER ALLOWED TO BE DISCARGED
OFF SITE INTO NELSON MEADOWS SUBDIVISION
Check the half inch requirement (per DSSP II.A.4)
1. Determine Area of Hardscape within Drainage Area #4
Contributing Area Area (ft 2 )
Hardscape 5355
2. Calculate 1/2" runoff volume over hardscape
(aka Runoff Reduction Volume [RRV] as calculated in Montana Post-
Construction Storwater BMP Manual - Equation 3-1)
RRV = [P*Rv*A]/12
P = Water quality rainfall depth 0.50 inches
Rv = Dimensionless runoff coefficient 0.41 0.05 + 0.9*I
I = Percent impervious cover (decimal)0.40 decimal
A = Entire drainage area 0.31 acres
RRV = Runoff Reduction Volume 0.0052 acre-ft
RRV = Runoff Reduction Volume 229 cubic feet
Because the runoff volume from the 10‐yr, 2‐hr storm (for flood control) is
greater than the runoff volume produced by the half inch rainfall (for water quality)
the larger runoff volume is used (451 cf).
DRAINAGE AREA # 1
DRYWELL 1
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft2 )C * Area
Hardscape 0.95 9861 9368
Landscape 0.20 384 77
Total 10245 9445
A = Area (acres) 0.2352
C = Weighted C Factor 0.92
2. Calculate Required Volume
Q=CIA
V=7200Q
C = Weighted C Factor 0.92
I = Intensity (in/hr) 0.41 (10 yr, 2hr storm)
A = Area (acres) 0.24
Q = Runoff (cfs) 0.09
V = REQUIRED VOL (ft3) 637
3. Calculate Drywell Volume
Void Ratio of Media 30.00%
Gravel Offset Dist. From Drywell (ft) 10.5
Gravel Void Volume
Gravel Bed Depth (below MH) 0.00
Gravel Volume (ft3)2022.75
Gravel Storage Volume (ft3)606.82
Manhole Volume
Manhole Depth (ft) 4.00
Manhole Volume (ft3)73.29
Provided Volume (ft3)680
Check the half inch requirement (per DSSP II.A.4)
1. Determine Area of Hardscape within Drainage Area #1
Contributing Area Area (ft 2)
Hardscape 9861
2. Calculate 1/2" runoff volume over hardscape
(aka Runoff Reduction Volume [RRV] as calculated in Montana Post-
Construction Storwater BMP Manual - Equation 3-1)
RRV = [P*Rv*A]/12
P = Water quality rainfall depth 0.50 inches
Rv = Dimensionless runoff coefficient 0.92 0.05 + 0.9*I
I = Percent impervious cover (decimal)0.96 decimal
A = Entire drainage area 0.24 acres
RRV = Runoff Reduction Volume 0.0090 acre-ft
RRV = Runoff Reduction Volume 391 cubic feet
Because the runoff volume from the 10‐yr, 2‐hr storm (for flood control) is
greater than the runoff volume produced by the half inch rainfall (for water quality)
the larger runoff volume is used (637 cf).
DRAINAGE AREA # 3
FRENCH DRAIN 1
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2)C * Area
Hardscape 0.95 2570 2442
Landscape 0.20 0 0
Total 2570 2442
A = Area (acres) 0.0590
C = Weighted C Factor 0.95
2. Calculate Required Volume
Q=CIA
V=7200Q
C = Weighted C Factor 0.95
I = Intensity (in/hr) 0.41 (10 yr, 2hr storm)
A = Area (acres) 0.06
Q = Runoff (cfs) 0.02
V = REQUIRED VOL (ft3) 165
3. Calculate French Drain Volume
Porous Media in French Drain Gravel
Void Ratio of Media 30.00%
Gravel Offset Dist. From French Drain (ft) 6
Length of Media 26
Depth of Media 4
Gravel Void Volume
Gravel Volume (ft3)624
Gravel Storage Volume (ft3)187
Provided Volume (ft3)187
Check the half inch requirement (per DSSP II.A.4)
1. Determine Area of Hardscape within Drainage Area #3
Contributing Area Area (ft2 )
Hardscape 2570
2. Calculate 1/2" runoff volume over hardscape
(aka Runoff Reduction Volume [RRV] as calculated in Montana Post-
Construction Storwater BMP Manual - Equation 3-1)
RRV = [P*Rv*A]/12
P = Water quality rainfall depth 0.50 inches
Rv = Dimensionless runoff coefficient 0.95 0.05 + 0.9*I
I = Percent impervious cover (decimal)1.00 decimal
A = Entire drainage area 0.06 acres
RRV = Runoff Reduction Volume 0.0023 acre-ft
RRV = Runoff Reduction Volume 102 cubic feet
Because the runoff volume from the 10‐yr, 2‐hr storm (for flood control) is
greater than the runoff volume produced by the half inch rainfall (for water quality)
the larger runoff volume is used (165 cf).
DRAINAGE AREA # 5
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
Hardscape 0.95 0 0
Landscape 0.20 19736 3947
Gravel 0.50 10230 5115
Total 29966 9062
A = Area (acres) 0.6879
C = Weighted C Factor 0.30
2. Calculate Required Volume
Q=CIA
V=7200Q
C = Weighted C Factor 0.30
I = Intensity (in/hr) 0.41 (10 yr, 2hr storm)
A = Area (acres) 0.69
Q = Runoff (cfs) 0.08
V = REQUIRED VOL (ft3) 611
VOLUME OF STORMWATER ALLOWED TO BE DISCARGED
OFF SITE INTO NELSON MEADOWS SUBDIVISION
Check the half inch requirement (per DSSP II.A.4)
1. Determine Area of Hardscape within Drainage Area #5
Contributing Area Area (ft 2 )
Hardscape 10230
2. Calculate 1/2" runoff volume over hardscape
(aka Runoff Reduction Volume [RRV] as calculated in Montana Post-
Construction Storwater BMP Manual - Equation 3-1)
RRV = [P*Rv*A]/12
P = Water quality rainfall depth 0.50 inches
Rv = Dimensionless runoff coefficient 0.36 0.05 + 0.9*I
I = Percent impervious cover (decimal)0.34 decimal
A = Entire drainage area 0.69 acres
RRV = Runoff Reduction Volume 0.0102 acre-ft
RRV = Runoff Reduction Volume 446 cubic feet
Because the runoff volume from the 10‐yr, 2‐hr storm (for flood control) is
greater than the runoff volume produced by the half inch rainfall (for water quality)
the larger runoff volume is used (611 cf).
APPENDIX C
GROUNDWATER DEPTH INFORMATION
APPENDIX D
EXCERPTS FROM NELSON MEADOWS
SUBDIVISION STORMWATER DESIGN
REPORT (2019)
APPENDIX E
STORMWATER FACILITIES INSPECTION
AND MAINTENANCE PLAN
INSPECTION AND MAINTENANCE FOR
STORMWATER MANAGEMENT FACILITIES
The Property Owner shall be responsible for the maintenance of the stormwater drainage
facilities within the Lot 16, Block 4 Nelson Meadows development.
Storm Water Facilities:
1.Drainage swales slope toward retention and detention ponds to collect storm water
runoff and channel it to the retention or detention pond.
2.Retention Ponds collect storm water runoff and store the water until it evaporates and/or
infiltrates into the ground.
3.Detention ponds collect storm water runoff while allowing some water to drain to
another location.
4.Culverts are pipes which channel storm water from ditches or swales under roads.
5.Pipe Networks convey storm water to different discharge locations underground.
6.Inlets are facilities where storm water runoff enters a pipe network. Inlets include storm
water manholes and drains.
7.Catch Basins are sumps typically located directly below storm water inlets and allow
sediment to settle before storm water enters the pipe network.
8.Outlets are points where storm water exits a pipe network.
9.Drywells are underground storm water collection facilities that collect and temporarily
store runoff from roof tops and landscaped areas before allowing storm water to infiltrate
into the ground.
Post Construction Inspection:
1.Observe drain time in retention ponds for a storm event after completion of the facility to
confirm that the desired drain time has been obtained. If excessively slow infiltration
rates are observed then excavate a minimum 5 ft by 5 ft drain to native gravels (or native
well-draining material) and backfill with well-draining material (pit-run).
2.Observe that drywells,catch basins, and outlet structures are clear of any material or
obstructions in the drainage slots. Inspect these structures to insure proper drainage
following a storm event. Immediately identify and remove objects responsible for
clogging if not draining properly.
Semi-Annual Inspection:
1.Check retention ponds and dry wells three days following a storm event exceeding ¼
inch of precipitation. Failure for water to percolate within this time period indicates
clogging or poor-draining soils.Clear any clogs and replace any poor-draining soils with
well-draining gravely soils.
2.Check for grass clippings, litter, and debris in drainage swales, catch basins, dry wells,
culverts and retention ponds.Flush and/or vacuum drywells or storm water pipes if
excessive material is observed in the facilities.
Standard Maintenance:
1.Remove sediment and oil/grease from retention ponds and detention ponds.
2.Inspect and remove debris from drainage swales, catch basins, dry wells,and retention
ponds.Use a vacuum truck to clean catch basins and dry wells.
3.Monitor health of vegetation and revegetate as necessary to maintain full vegetative
cover.
4.Inspect for the following issues: differential accumulation of sediment, drain time, signs of
petroleum hydrocarbon contamination (odors, oil sheen in pond water), standing water,
trash and debris.
Sediment accumulation:
In most cases, sediment from a retention pond does not contain toxins at levels posing a hazardous
concern. However, sediments should be tested for toxicants in compliance with current disposal
requirements and if land uses in the drainage area include commercial or industrial zones, or if
visual or olfactory indications of pollution are noticed. Sediments containing high levels of
pollutants should be disposed of in accordance with applicable regulations and the potential
sources of contamination should be investigated and contamination practices terminated.
Equipment Type/Access:
All drywells will be cleaned using vacuum trucks. All vacuum trucks will access the site through
the proposed alley and parking lot.
Cost Estimate:
Depending on the amount of rainfall in the given year, the cost to maintain the stormwater
infrastructure will vary. It is estimated that the drywells will need to be vacuumed out once per
year, with an estimated cost of $1,500 to do so. The applicant will be responsible for financing the
maintenance of the stormwater infrastructure.