March 12, 2021
City of Bozeman
Development Review Committee
RE: Community First Griffin Place
Concurrent Construction Request
Please accept this letter as a request for concurrent construction of site and building
improvements for the Community First Griffin Place Site Plan. The Design Team is
coordinating with the City’s engineer regarding the upcoming improvements to
Griffin Drive. While we anticipate that infrastructure will be largely completed prior
to the start of building construction for Phase 1, we would like to request concurrent
construction to allow for flexibility if needed. This request if supported by the
following standard conditions per UDC 38.270.030 C1 b and c for Site Developments.
The Community First Griffin Place meets the provisions outlined within the UDC in
sections 38.270.030.1.b., as the water and sewer mains will be located within a public
utility easement physically adjacent to the proposed buildings, with adequate
capacity.
It will also meet the requirements of 38.270.030.1.c (1-5) as the extended mains will
only serve one lot, will be subject of an irrevocable offer of dedication to the City upon
completion of the project, the development will be under the control of a single
developer (HRDC), under the supervision of a single general contractor, and will have
no subdivision of land.
The site can be serviced by existing Fire Hydrants #634 and 635, which are both
adjacent to the HRDC lot and supplied by the 12” water main in Griffin Drive. The site
also has two existing accesses off Griffin Drive.
Please see the attached schedule and construction plan and let us know if there are
any additional conditions required to enable concurrent construction.
Sincerely,
Heather Grenier, President & CEO
HRDC District IX, Inc.
GRIFFIN DRIVEPROJECT SITE5.24 ACRESNORTH BUILDING27,086 SF FOOTPRINT202 E. GRIFFIN DR.SOUTH BUILDING14,500 SF FOOTPRINT206 E. GRIFFIN DR.MONTANA RAIL LINKPHASE 1PHASE 2NOTE: THIS PLAN IS TO PROVIDE GENERALGUIDANCE OF SITE CONSTRUCTIONSEQUENCING CONSTRAINTS. THE GENERALCONTRACTOR SHALL PROVIDE MORE DETAILEDSEQUENCING/FACILITIES PLANS THAT FOLLOWTHIS GENERAL GUIDANCE.C0.3CONSTRUCTIONFACILITIES PLANPROFESSIONALENGINEERS &SURVEYORSCOMMUNITY FIRST
GRIFFIN PLACE STAHLYENGINEERING& ASSOCIATESHRDC
202 & 206 EAST GRIFFIN DR.
BOZEMAN, MTCONSTRUCTION ROUTE
COMMUNITY FIRST GRIFFIN PLACE03-12-2021PROJECT SCHEDULEWINTER SPRING SUMMERFALLWINTERENTITLEMENTPROCESSBUILDING DESIGNYEAR-ROUNDEMERGENCY SHELTER & RESOURCE HUBFOOD RESOURCE CENTERSPRING SUMMER20202021M A MD J FJ J A S O N D J F M A M J J ACONCEPT PUDMay 2018INF SITE PLANCITY REVIEW - SITE PLAN - estimated at 20 weeksCITY REVIEW INF Site Plan SITE PLANPRELIMINARY DESIGN DDSD BLDG PERMIT est. 8 weeks / 2 weeks for revisionsBUILDING CONSTRUCTIONestimated 12-18 monthsEarly 2023 construction startCDDDCDSD BLDG PERMIT est. 8 weeks / 2 weeks for revisionsBUILDING CONSTRUCTIONestimated 12-18 months Early 2022 construction startPROGRAM VERIFICATIONSITE DESIGN SITE CONSTRUCTIONFall 2021 construction startPRELIMINARY DESIGNCITY AND STATE ENGINEERING REVIEW OF SITESITE LANDSCAPINGCIVIL DESIGNLAND-SCAPINGCIVIL DESIGNGRIFFIN DRIVE IMPROVEMENTSGRIFFIN DRIVE CONSTRUCTIONGRIFFIN DRIVE IMPROVEMENTS - design by Sanderson Stewart