March 12, 2021
Community First Griffin Place
Site Plan Application
Planning
1. 38.510.020. C and 38.510.030.H Block Frontage. The Site has no Block Frontage
designation; therefore the “default” Block Frontage designation in industrial zones is
“Other” per 38.510.020.C. That section defers to section 38.510.030.H which defers to
Table 38.320. 050 which requires a 20-feet front setback with landscaping therein. It
appears that the North building is setback 24-feet from the north property line; please
confirm. The planting area between the sidewalk and the building and parking areas
must be at least 20-feet in depth; please label this. When architectural drawings are
submitted, they will be measured by the standards of Table 38.510.030.C for Mixed
Block Frontage sites and not the storefront standards.
A 20-foot landscaped setback is noted on the drawings. Thank you for clarifying the
“No Frontage” > “Other” > “Mixed” > “Landscaped” block frontage designation along
Griffin Drive.
2. 2. 38.520.060. B.1, Open space. The North building non-residential uses would not
require open space. The South building uses, as principally-transitional housing and
services to those clients, would require the same open space as required for group
housing at 37 square feet per person/bed.
The design team has applied the principals of “Trauma-Informed Design” throughout
the site and building designs and there are several different programmed open spaces
strategically located throughout the site. The code requires a minimum of 37 sf per
bed. With 170 beds proposed, 6,290 sf of open space is required. This requirement will
be met by the landscaped areas south of the south building as detailed on Sheets A1.2
and L306.
3. 3. 38.540.050, Parking. Parking is required for each of the various uses, depending upon
the net square footage of each use (85% of the gross) [38.540.010.A.1] or you may
calculate the parking requirement by the more detailed process described in
38.540.010.A.1.a.
See parking calculations on Sheet A.01 “Cover Sheet.” Based on the unique uses of the
buildings, the owner has elected to pursue the more detailed process allowed by
Section 38.540.010.A.1.a.
4. 38.360.135. C.5, Parkland Dedication. Per this Section, the emergency housing
component is exempt from parkland dedication.
Understood.
5. Please provide a lighting plan with the site plan submittal.
Please see the ES Sheets in the Drawing folder for details.
6. Please remember to submit an application for Concurrent Construction of infrastructure
with the site plan submittal.
A concurrent construction plan has been submitted. See Section 06 in the Documents
folder.
Engineering - Legal
1. Bozeman Municipal Code (BMC) 38.400.090. - Griffin Drive is classified as a minor
arterial as such requires 100 feet of right-of-way (ROW). Conservatively the applicant
should plan that 50 feet of right-of-way will be required along the property frontage
from the center line, however, with the design of Griffin underway the City is reviewing
the necessary ROW required to support the reconstruction of the street. Preliminary
review of the design indicates that a reduced ROW section maybe acceptable. The
required ROW must be provided prior to site plan approval, City will accept either ROW
dedication or a street easement dedication using the City’s standard language.
The design team and owner have been coordinating with the City of Bozeman
Engineering Division and Sanderson Stewart, the firm designing the Griffin Drive
transportation project.
2. BMC 38.410.060.B.2.a. - Ten foot utility easement are required along the frontage for all
streets for the extension of dry utilities unless an alternative location is approved of in
writing by all appropriate utility companies and the City. This easement must be provide
beyond any additional ROW required for Griffin Drive.
A 10-foot utility easement is shown along the Griffin Drive frontage. See Sheet C1.0 in
the Drawings folder.
3. BMC 38.410.060. - The public water and sewer easement supporting the onsite
extension of mains must be prior using the City’s standard language. Please contact the
Engineering Department (Griffin Nielsen) to receive a copy of the standard language.
A standard easement is planned for the main extensions.
Engineering - Transportation
1. BMC 38.400.010. – Griffin Drive adjacent to the development does not meet the City
minimum standard for a minor arterial street, the street must be upgraded in order for
the development to receive approval. As discussed above, the City is planning the street
upgrade of Griffin Drive in Fiscal Year 2021 (CIP No. SIF 113). The applicant is responsible
for the property owners local cost share of the street improvements. Payment for the
local share must be made according to the City’s cash-in-lieu of infrastructure code
section, Bozeman Municipal Code (BMC) 38.270.070 and must pay the full cash-in-lieu
of infrastructure amount prior to site plan approval.
The property owner understands this condition.
2. BMC 38.400.090. - The accesses on to Griffin Drive do not meet the City’s separation
require. The applicant may request a relaxation to this standard per 38.400.090.H. The
applicant will need justify that relaxation for the proposed development is safe as
proposed or if additional infrastructure would be need to ensure safety. A relaxation
request will need to account for the present of the adjacent transit stop.
The accesses on Griffin Drive have been discussed with the Engineering Division and
Sanderson Stewart, the City’s consultant for the road design. These accesses line up
with the existing accesses across Griffin Drive and allow for safe movement to and
from the site. Please see Section 07 “Transportation Impact Summary” from
Sanderson Stewart which includes the access deviation request.
3. BMC 38.230.100.A.6. - Please provide a transportation summary of for impacts for the
development which includes estimate for the peak hour trips, muti-modal trip
distribution breakdown (included pedestrian and bike users), atypical vehicles which
may access the site and any additional infrastructure that maybe needed to support the
health and safety of the public and site user and mitigate the impacts the transportation
system.
Please see Section 07 “Transportation Impact Summary” from Sanderson Stewart.
4. BMC 38.410.120. - The proposed transit stop will need to be coordinated with the
design of Griffin Drive and Streamline. The applicant is advised to review section 7 from
the City’s 2007 Transportation Master Plan when designing the site with the adjacent
transit stop.
The design team has been in contact with the City, Sanderson Stewart and Streamline
to determine the best location for the bus stop which is shown in the drawing set.
5. BMC 38.400.010. – The project falls along a Montana Department of Transportation
(MDT) Urban Route, as such must be submitted to the MDT Systems Impact Review
Committee and make necessary update/changes to the future site plan to address any
comments provided by the committee.
Please see Section 07 “Transportation Impact Summary” from Sanderson Stewart.
Sanderson Stewart is the Engineer on the Griffin Transportation project and has been
coordinating with MDT and the City.
Engineering - Water and Wastewater
1. BMC 38.410.070. - The applicant must coordinate water and sanitary sewer main
extension with the design of Griffin Drive improvements. Please contact the City
Engineering Division (Taylor Lonsdale). The main extension must be installed either
before the reconstruction or concurrently. Pavement cuts into Griffin Drive will not be
allowed once the project is completed.
The design team is coordinating the construction schedule with the City and the City’s
consultant, Sanderson Stewart.
2. BMC 38.410.070. – Please provide an estimate of the peak-hour sanitary sewer demand
certified by a professional engineer for the proposed project. The City will analyze and
determine if sewer capacity is available to accommodate the project.
See attached Preliminary Engineering Sewer Report in Section 12 in the Documents
folder.
3. BMC 38.410.070. - The proposed project resides in an area that is known to experience
high groundwater and increased rates of corrosion due to clay soils. The applicant must
provide a corrosion analysis with the infrastructure design report. If the corrosion report
verifies corrosive soils, the applicant must provide sufficient corrosion protection of the
ductile iron water mains.
See attached Preliminary Engineering Water Report in Section 11 in the Documents
folder.
4. BMC 38.410.130. - Water rights and/or payment of cash-in-lieu of water right is
required prior site plan approval. The applicant is advised to contact Brian Heaston with
the Engineering Department for additional questions on the requirements of
38.410.130.
A preliminary cash-in-lieu of water right calculation is included in Section 1.1.5 of the
Preliminary Water Report in Section 11; however, we would like to discuss this
calculation with the City due to the unique nature of the proposed uses.
Engineering - Stormwater:
1. BMC 38.410.080. - The applicant must include a drainage plan with post-construction
storm water management controls that are designed to infiltrate, evapotranspire,
and/or capture for reuse the post-construction runoff generated from the first 0.5
inches of rainfall from a 24-hour storm preceded by 48 hours of no measurable
precipitation. For projects that cannot meet 100% of the runoff reduction requirement,
the remainder of the runoff from the first 0.5 inches of rainfall must be either: a.
Treated onsite using post-construction storm water management control(s) expected to
remove 80 percent total suspended solids (TSS); b. Managed offsite within the same
sub-watershed using post-construction storm water management control(s) that are
designed to infiltrate, evapotranspire, and/or capture for reuse; or c. Treated offsite
within the same subwatershed using post-construction storm water management
control(s) expected to remove 80 percent TSS.
a. The existing site appears collected and provided storage for offsite drainage in the
northeast and northwest corner. The drainage design must account for this offsite
drainage and ensure that runoff is limited to predevelopment rates.
b. With the upgrade to Griffin Drive there maybe need to provide stormwater storage for
the increase in drainage from the expansion of the road along the property frontage.
The drainage design engineer should coordinated with City Engineering Division (Taylor
Lonsdale).
See attached Preliminary Engineering Stormwater Report in Section 13 in the
Documents folder.
2. BMC 38.410.080. - A stormwater maintenance plan must be provided and approved by
the City. The approved maintenance plan must be signed by the property owner or
incorporated into property owner association documents, if documents are to be
created prior to master site plan approval.
There are no property owner association documents for this project. See attached
draft stormwater maintenance plan in the Appendix of the Preliminary Engineering
Stormwater Report in Section 13 in the Documents folder.
3. Montana Post-Construction Storm Water BMP Design Guidance Manual Seasonal High
Groundwater - The proposed project is located in an area that is known to have
seasonally high groundwater. The season high groundwater elevation must be
confirmed and included as part of the drainage report. Groundwater may not impact the
function or maintenance of the proposed facilities. Industry guidance recommends a
three-foot minimum separation from the bottom of the proposed facility to the
underlying groundwater table. The applicant is advised to begin groundwater
measurements as soon as possible to obtain the necessary information for design.
See attached Geotechnical Report in Section 14 of the Documents folder.
Engineering – Recommended Conditions of Approval
1. Upon future development, the applicant must provide and file with the County Clerk
and Recorder's office executed Waivers of Right to Protest Creation of Special
Improvement Districts (SID’s) for the following:
a. Street improvements to Griffin Drive including lighting signalization paving,
curb/gutter, sidewalk, lighting and storm drainage
b. Intersection improvements to Griffin Drive and Manley Road
c. Intersection improvements to Griffin Drive and North 7th Ave.
d. Intersection improvements to Griffin Drive and Bridger Drive.
e. Intersection improvements to Griffin Drive and Rouse Ave.
The applicant may obtain a copy of the template SID waiver from the City Engineering
Department (Griffin Nielsen). The document filed must specify that in the event an SID
is not utilized for the completion of these improvements, the applicant agrees to
participate in an alternate financing method for the completion of said improvements
on a fair share, proportionate basis as determined by square footage of property,
taxable valuation of the property, traffic contribution from the development, or a
combination thereof. The applicant must provide a copy of the SID waiver filed with the
County Clerk and Recorder with and provided a copy of the recorded document prior to
site plan approval.
See attached draft waiver in Section 08 in the Documents folder. If this draft is
acceptable to the City, the owner will sign and record it.
Engineering - Advisory
1. The applicant must obtain approval from The Montana Department of Environmental
Quality for water and sanitary sewer infrastructure constructed with this project prior to
scheduling an infrastructure pre-construction meeting with the City.
The owner understands this condition.
2. The applicant must submit plans and specifications for water and sewer main
extensions, streets, and storm water improvements, prepared and signed by a
professional engineer (PE) registered in the State of Montana, which must be provided
to and approved by the City Engineer. Water and sewer plans must also be approved by
the Montana Department of Environmental Quality. The applicant must also provide
professional engineering services for construction inspection, post-construction
certification, and preparation of mylar record drawings. Construction shall not be
initiated on the public infrastructure improvements until the plans and specifications
have been approved and a preconstruction conference has been conducted. Building
permits will not be issued prior to City acceptance of the site infrastructure
improvements unless all provisions set forth in Section 38.270.030.C of the Bozeman
Municipal Code are met to allow for concurrent construction.
This application does include a request for Concurrent Construction. Please see
Section 06 in the Documents folder for details.
3. The applicant must prepare plans and specifications for any fire service line in
accordance with the City’s Fire Service Line Policy. The plans must be prepared by a
Professional Engineer and be provided to and approved by the City Engineer prior to
initiation of construction of the fire service or fire protection system. The applicant must
also provide Professional Engineering services for construction inspection, post-
construction certification and preparation of mylar record drawings. Fire service plans,
and domestic services 4” or larger, must be either a standalone submittal or included
with the water main extension infrastructure plans, separate from the site plan
submittal. City of Bozeman applications for service must be completed by the applicant.
The owner understands this condition.