INTRODUCTION
The Westland Lofts Mixed Use Master Site Plan proposes to develop Lot 5, Block 14 of the Baxter
Meadows Subdivision, Phase 6. The proposed layout consists of a parking area centrally located
on the lot with two approaches on the north and south side of the lot. Surrounding the parking lot
are four proposed buildings, three of which will be exclusively residential and the fourth will have
commercial and residential spaces. The property is located within the City of Bozeman limits and
is within the community business district (B-2) zoning. A combination of site grading, curb and
gutter, and underground infiltration chambers will be used to manage stormwater runoff on the
site. Supporting stormwater calculations are enclosed in Appendix A for reference.
BAXTER MEADOWS SUBDIVISION, PHASE 6 – STORMWATER BACKGROUND
INFORMATION
Baxter Meadows Subdivision included the construction of regional detention and retention ponds
that handle the runoff generated by the subdivision through a system of stormwater conveyance
structures and stormwater detention ponds. The pond that was constructed for Lot 5, Block 14 was
installed with the Phase 6 infrastructure improvements. Lot 5, Block 14 was assigned a Rational
Method Runoff Coefficient of 0.5 per Bozeman Design Standards and Specifications Policy
(DSSP) in the original design of the subdivision. The lot was intended to drain to Detention Pond
A. See Appendix C for the Phase 6 stormwater design report by TD&H Engineering. A Runoff
Coefficient of 0.5 does not provide adequate storm water detention for the proposed development
of this lot. The actual Runoff Coefficient for the proposed project on Lot 5, Block 14 is 0.80 (see
enclosed calculations). The original underestimation of the future development of this lot means
that the regional detention ponds for the subdivision are not adequate to handle the entire runoff
contribution from the proposed development.
LOT 5, BLOCK 14, STORMWATER DESIGN
The site was divided into 4 drainage areas as shown on the attached Drainage Area Map in
Appendix B. Using the design C value of 0.5 and the DSSP 10-year, 2-hour storm, the runoff
allocated for Lot 5 is 2,138 ft3 (see Appendix A for calculations). Drainage Areas 1 & 2 will be
retained in underground storage systems. Drainage Areas 3 & 4 and a majority of the landscaping
are anticipated to infiltrate into the respective landscaping beds.
The runoff coefficient for Drainage Area 1 is 0.86 over an area of 28,114 sf which translates to
1,642 cf of runoff. Runoff form Drainage Area 1 will drain to a catch basin located in the middle
curb island in the center of the parking lot. The runoff will then be conveyed and retained in
Contech Stormwater Infiltration Chambers beneath the open space located in the southeast corner
of the lot. The design will consist of a double manifold system with four rows of 26’ long, 36” dia.
perforated CMP. The system provides a storage capacity of 1,673 cf. Details for the Drainage Area
1 infiltration system are included in Appendix D.
Drainage Area 2 has a runoff coefficient of 0.90 over an area of 25,317 sf which translates to 1,549
ft3 of runoff. Similar to Drainage Area 1, Drainage Area 2 will drain to a catch basin at the north
end of the parking lot. The runoff will be conveyed to another Contech Stormwater Infiltration
Chamber System beneath the north row of parking stalls. The design will consist of a double
manifold system with four rows of 52’ long, 30” dia. perforated CMP. The system provides a
storage capacity of 1,559 cf. Details for the Drainage Area 2 infiltration system are included in
Appendix D.
Drainage Area 3 consists of the landscaping along the eastern edge and a small area of sidewalk.
Drainage Area 3 has a weighted C value of 0.30 over an area of 5,098 sf which translates to a
runoff volume of 102 cf. Drainage Area 4 has a weighted C value of 0.20 over an area of 2,611 sf
which translates to a runoff volume of 35 cf. Since nearly 95% of Drainage Area 3 and Drainage
Area 4 are landscaping it is anticipated that the small amount of runoff will infiltrate into the
landscape beds along the northern, eastern, and southern edges of the property.
SEASONAL HIGH GROUNDWATER
Three groundwater monitoring wells were installed on the property on April 12, 2019. Readings
were taken weekly from April 12 to June 21 to determine the seasonal high levels. Two of the
wells were installed directly where the underground retention chambers are proposed. The third
monitoring well was installed in the low point of the existing property. Monitoring Well 1 was
installed where the Drainage Area 1 system is proposed. The peak groundwater level was
measured at 6.42 feet below ground surface (bgs). The existing grade at Monitoring Well 1 is
4702.18’; which makes the seasonal high-water elevation 4695.76’. The underground retention
system for Drainage Area 1 has a bottom elevation of 4698.31’. Monitoring Well 3 was installed
where the Drainage Area 2 system is proposed. The peak groundwater level was measured at 6.55
feet below ground surface (bgs). The existing grade at Monitoring Well 3 is 4700.92’; which
makes the seasonal high-water elevation 4694.37’. The underground retention system for
Drainage Area 2 has a bottom elevation of 4696.42’. Based on this information, groundwater is not
anticipated to decrease the systems storage capacity. As an additional measure to promote
infiltration into the water table, the proposed design includes excavation to the native gravels layer
and backfilling with well-draining pit run. Monitoring well data is included in Appendix E of this
report.
APPENDIX A
STORMWATER CALCULATIONS
PRE-DEVELOPMENT RUNOFF VOLUME
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2)C * Area
Total 0.5 63090 31545
C=Weighted C Factor 0.50
2. Calculate Required Volume
Q = CIA
V=7200Q
C = Weighted C Factor 0.50
I = intensity (in/hr) 0.41 (10 yr, 2hr storm)
A = Area (acres) 1.45
Q = runoff (cfs) 0.30
V = RUNOFF VOL (ft3)2138
OVERALL SITE
REQUIRED VOLUME
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2)C * Area
Hardscape 0.95 50709 48174
Landscape 0.2 12381 2476
Total 63090 50650
C=Weighted C Factor 0.80
2. Calculate Required Volume
Q = CIA
V=7200Q
C = Weighted C Factor 0.80
I = intensity (in/hr) 0.41 (10 yr, 2hr storm)
A = Area (acres) 1.45
Q = runoff (cfs) 0.48
V = RUNOFF VOL TO SUBDIVISION (ft3)3432
DRAINAGE AREA 1
REQUIRED VOLUME
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2)C * Area
Hardscape 0.95 24814 23573
Landscape 0.2 3300 660
Total 28114 24233
C=Weighted C Factor 0.86
2. Calculate Required Volume
Q = CIA
V=7200Q
C = Weighted C Factor 0.86
I = intensity (in/hr) 0.41 (10 yr, 2hr storm)
A = Area (acres) 0.65
Q = runoff (cfs) 0.23
V = REQUIRED VOL (ft3)1642
DRAINAGE AREA 2
REQUIRED VOLUME
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2)C * Area
Hardscape 0.95 23718 22532
Landscape 0.2 1599 320
Total 25317 22852
C=Weighted C Factor 0.90
2. Calculate Required Volume
Q = CIA
V=7200Q
C = Weighted C Factor 0.90
I = intensity (in/hr) 0.41 (10 yr, 2hr storm)
A = Area (acres) 0.58
Q = runoff (cfs) 0.22
V = REQUIRED VOL (ft3)1549
DRAINAGE AREA 3
REQUIRED VOLUME
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2)C * Area
Hardscape 0.95 655 622
Landscape 0.2 4443 889
Total 5098 1511
C=Weighted C Factor 0.30
2. Calculate Required Volume
Q = CIA
V=7200Q
C = Weighted C Factor 0.30
I = intensity (in/hr) 0.41 (10 yr, 2hr storm)
A = Area (acres) 0.12
Q = runoff (cfs) 0.01
V = RUNOFF VOL. (ft3)102
DRAINAGE AREA 4
REQUIRED VOLUME
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2)C * Area
Hardscape 0.95 0 0
Landscape 0.2 2611 522
Total 2611 522
C=Weighted C Factor 0.20
2. Calculate Required Volume
Q = CIA
V=7200Q
C = Weighted C Factor 0.20
I = intensity (in/hr) 0.41 (10 yr, 2hr storm)
A = Area (acres) 0.06
Q = runoff (cfs) 0.00
V = RUNOFF VOL. (ft3)35
DRAINAGE AREA #1
INLET CAPACITY
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2)C * Area
Landscape 0.2 3300 660
Hardscape 0.95 24814 23573
Total 28114 24233
A = Area (acres) 0.6454
C = Weighted C Factor 0.86
2. Calculate Tc (Time to Concentration)
Tc Overland Flow (Roof and Parking Lot)
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%) 2.5 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.20 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft) 71 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)10.22
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb)
S = slope (%) 0.50%
L = length of gutter (ft) 81
V = mean velocity (ft/s) 2.12
Tc Gutter Flow (minutes) =0.64
Tc Total = 10.85
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.86 (calculated above)
I = 0.78 Tc-0.64 (in/hr)2.33 (25-yr storm)
A = area (acres) 0.65 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs) 1.30 (assuming no carry flow)
4. Calculate Inlet Capacity-Sag Location
Q=3.3P(h)1.5 (Modified Weir Eq.)from Neenah Foundry
P=Perimeter (ft) 5.9
1.03 (0.15' below top of curb)
Q= capacity of Inlet (cfs) 20.21
Q=0.6A(2gh)0.5 (Orifice Equation)from Neenah Foundry
A= Free Open Area of Grate (ft2) 2.10
1.03 (0.15' below top of curb)
Q= capacity of inlet (cfs) 10.24
Q=True Capacity (lesser of the two) 10.24
Number of Inlets Required 1.0
h=depth of flow from above (ft) +
(0.875in/12in for Depression of Grate)
h=depth of flow from above (ft) +
(0.875in/12in for Depression of Grate)
DRAINAGE AREA #2
INLET CAPACITY
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2 )C * Area
Landscape 0.2 1599 320
Hardscape 0.95 23718 22532
Total 25317 22852
A = Area (acres) 0.5812
C = Weighted C Factor 0.90
2. Calculate Tc (Time to Concentration)
Tc Overland Flow (Roof and Parking Lot)
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%) 2.5 Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.20 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft) 90 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)11.50
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb)
S = slope (%) 0.75%
L = length of gutter (ft) 139
V = mean velocity (ft/s) 2.60
Tc Gutter Flow (minutes) =0.89
Tc Total = 12.39
3. Calculate Flow (Rational Formula)
Q = CIA
C = Weighted C Factor 0.90 (calculated above)
I = 0.78 Tc-0.64 (in/hr)2.14 (25-yr storm)
A = area (acres) 0.58 (calculated above)
Q = REQUIRED GUTTER CAPACITY (cfs) 1.12 (assuming no carry flow)
4. Calculate Inlet Capacity-Sag Location
Q=3.3P(h)1.5 (Modified Weir Eq.)from Neenah Foundry
P=Perimeter (ft) 5.9
1.03 (0.15' below top of curb)
Q= capacity of Inlet (cfs) 20.21
Q=0.6A(2gh)0.5 (Orifice Equation)from Neenah Foundry
A= Free Open Area of Grate (ft2) 2.10
1.03 (0.15' below top of curb)
Q= capacity of inlet (cfs) 10.24
Q=True Capacity (lesser of the two) 10.24
Number of Inlets Required 1.0
h=depth of flow from above (ft) +
(0.875in/12in for Depression of Grate)
h=depth of flow from above (ft) +
(0.875in/12in for Depression of Grate)
MANNING'S EQUATION FOR PIPE FLOW (PROVIDED CAPACITY)
Pipe: CONTECH INLETS Location:ST MH 2 & ST MH 1
INPUT
D=12 inches
d=11.26 inches
Mannings Formula n=0.013 mannings
q=57.5 degrees
Q=(1.486/n)ARh2/3S1/2 S=0.005 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter V=(1.49/n)Rh2/3S1/2
S=slope of channel Q=V x A
n=Manning's roughness coefficient
Solution to Mannings Equation
Area,ft2 Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs
PVC 0.013
0.77 2.64 0.29 3.54 2.71 PE (<9"dia) 0.015
PE (>12"dia) 0.02
flow required (cfs) DA 1 1.30 PE(9-12"dia) 0.017
DA 2 1.12 CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
q
D
APPENDIX B
DRAINAGE AREA MAP
APPENDIX C
BAXTER MEADOWS ORIGINAL
STORMWATER DESIGN REPORT
APPENDIX D
CONTECH STORMWATER INFILTRATION
CHAMBERS DETAILS
Detention or Infiltration System Designer
Design - CMP
System Selection
Structural Backfill Detail
DYODS® #9302
System Description:Drainage Area 1
Project:Westland Lofts Master Site Plan
Application:Infiltration (Perforated CMP)
Created:11/01/2018
Modified:06/26/2019
Application:Infiltration
System:CMP - Perforated w/ Stone Backfill
Stone Porosity:40 %
Width At Ends:18 in
Above Pipe:6 in
Width At Sides:18 in
Below Pipe:6 in
Design Parameters
Pipe Detail
Storage Volume:1,642 cf
Limiting Length:40 ft
Limiting Width:25 ft
Pavement Type:No Pavement
Pavement Depth:0 in
Freeboard Depth:0 in
Invert Depth:5 ft
Material:Steel
Shape:Round
Size:36 in
Corrugation:2-2/3" x 1/2"
Gage:16
Pipe Spacing:18 in
Coating:Aluminized Steel Type 2 (ALT2)
Layout:Double Manifold
Calculations
Status:OK
Barrel Count:4
CMP Footprint (LxW):32 x 16.5 ft
Length Per Barrel:26 ft
Length Per Header:16.50 ft
Pipe Storage:968 cf
Structural Backfill Zone Storage:704 cf
Total Storage Provided:1,673 cf
Percent Of Required Storage:101.89 %
Total CMP Footage:137 ft
Approximate CMP Piece Count:10
Approximate Coupling Bands:12
Approximate Truckloads:1
Total Excavation:140 cy
Structural Backfill:65 cy
Pavement Volume:0 cy
Remaining Backfill To Pavement:38 cy
Draftboard
Detention or Infiltration System Designer
Design - CMP
System Selection
Structural Backfill Detail
DYODS® #9314
System Description:Drainage Area 2
Project:Westland Lofts Master Site Plan
Application:Infiltration (Perforated CMP)
Created:11/05/2018
Modified:06/26/2019
Application:Infiltration
System:CMP - Perforated w/ Stone Backfill
Stone Porosity:40 %
Width At Ends:15 in
Above Pipe:6 in
Width At Sides:15 in
Below Pipe:6 in
Design Parameters
Pipe Detail
Storage Volume:1,549 cf
Limiting Length:75 ft
Limiting Width:15 ft
Pavement Type:Flexible Pavement
Pavement Depth:3 in
Freeboard Depth:0 in
Invert Depth:4 ft
Material:Steel
Shape:Round
Size:30 in
Corrugation:2-2/3" x 1/2"
Gage:16
Pipe Spacing:15 in
Coating:Aluminized Steel Type 2 (ALT2)
Layout:Double Manifold
Calculations
Status:OK
Barrel Count:3
CMP Footprint (LxW):57 x 10 ft
Length Per Barrel:52 ft
Length Per Header:10 ft
Pipe Storage:863 cf
Structural Backfill Zone Storage:695 cf
Total Storage Provided:1,559 cf
Percent Of Required Storage:100.69 %
Total CMP Footage:176 ft
Approximate CMP Piece Count:11
Approximate Coupling Bands:12
Approximate Truckloads:1
Total Excavation:124 cy
Structural Backfill:64 cy
Pavement Volume:7 cy
Remaining Backfill To Pavement:20 cy
Draftboard
APPENDIX E
GROUNDWATER MONITORING WELL
DATA
Project Engineer:
Project:
Gallatin Green, Gallatin County, MT
Well Information:bgs = below ground surface ags = above ground surface
MW-1 MW-2 MW-3
2.00
Groundwater Information:
MW-1 MW-2 MW-3
7.22 3.05 7.40
6.42 2.25 6.55
6.72 2.58 6.83
6.85 2.70 6.98
7.11 3.00 7.26
7.29 3.17 7.45
7.27 3.16 7.42
7.36 3.21 7.49
7.59 3.46 7.75
7.30 3.29 7.46
7.21 3.23 7.45
Date
4.23.19
5.17.19
5.24.19
5.31.19
6.7.19
6.14.19
6.21.19
4.30.19
5.3.19
5.10.19
4.12.19
Project Number: 171281.1
Gallatin Green Groundwater Monitoring
Project Location:
Monitor Well Data
Well ID
Well Depth (feet-bgs)
Top of Well (feet-ags)
Ground Elevation
Depth to Ground Water (feet-bgs)