From:Luke, Edward <Edward.Luke@charter.com>
Sent:Monday, May 17, 2021 2:12 PM
To:Drew Kirsch; Self, Ed L
Cc:Steve Mcgough
Subject:RE: Westland Loft Phase 2 Rear Utility Easement
Drew,
Charter will not need the rear easement after all. We will feed the project from the north and south along with
Northwestern Energy when the trenching is started.
Thanks
Ed Luke | Construction Coordinator | C: 406.595.6002| F: 406.586.6381|
201 Evergreen Dr Suite B | Bozeman, MT, 59715
From: Drew Kirsch <dkirsch@chengineers.com>
Sent: Monday, May 10, 2021 4:44 PM
To: Luke, Edward <Edward.Luke@charter.com>; Self, Ed L <Ed.Self@charter.com>
Cc: Steve Mcgough <mcgoughconstruction@yahoo.com>
Subject: [EXTERNAL] RE: Westland Loft Phase 2 Rear Utility Easement
CAUTION: The e‐mail below is from an external source. Please exercise caution before opening attachments, clicking links, or
following guidance.
Thank you for getting back to me!
If we provided utility culverts under the patios and fences would it be possible to keep the patios and fences in the
easement?
Thanks,
Drew
From: Luke, Edward <Edward.Luke@charter.com>
Sent: Monday, May 10, 2021 4:28 PM
To: Drew Kirsch <dkirsch@chengineers.com>; Self, Ed L <Ed.Self@charter.com>
Cc: Steve Mcgough <mcgoughconstruction@yahoo.com>
Subject: RE: Westland Loft Phase 2 Rear Utility Easement
Drew,
2
We are planning on feeding phase 2 from the south through the easement. The pedestals placed in the easement will
need to be accesable.
Ed Luke | Construction Coordinator | C: 406.595.6002| F: 406.586.6381|
201 Evergreen Dr Suite B | Bozeman, MT, 59715
Thanks
From: Drew Kirsch <dkirsch@chengineers.com>
Sent: Monday, May 10, 2021 1:17 PM
To: Luke, Edward <Edward.Luke@charter.com>; Self, Ed L <Ed.Self@charter.com>
Cc: Steve Mcgough <mcgoughconstruction@yahoo.com>
Subject: [EXTERNAL] RE: Westland Loft Phase 2 Rear Utility Easement
CAUTION: The e‐mail below is from an external source. Please exercise caution before opening attachments, clicking links, or
following guidance.
Good Afternoon,
Have you had a chance to review the easement below? I have also attached an updated site plan set.
Thanks,
Drew
From: Drew Kirsch
Sent: Friday, April 02, 2021 9:58 AM
To: Edward.luke@charter.com; ed.self@charter.com
Cc: Steve Mcgough <mcgoughconstruction@yahoo.com>
Subject: RE: Westland Loft Phase 2 Rear Utility Easement
Ed,
To Clarify, the proposed project is near the intersection Kimberwicke and Gallatin Green, the lot below is highlighted in
yellow. Let me know if that helps. Thanks!
3
From: Drew Kirsch
Sent: Thursday, April 01, 2021 5:22 PM
To: Edward.luke@charter.com; ed.self@charter.com
Cc: Steve Mcgough <mcgoughconstruction@yahoo.com>
Subject: FW: Westland Loft Phase 2 Rear Utility Easement
Good afternoon,
NWE has agreed that they do not need the existing easement below for Lot 5, Block 14 of Baxter Meadows Subdivision
Phase 6. The owner, Steve Mcgough, would like to install concrete patios and fences within this easement.
Would it be possible to get Charter’s agreement that the easement could be reconveyed? Or at the least that the patios
and fences will no be an issue, as long as the owner is aware that they have the burden of replacing them? I think an
email acknowledging this would suffice.
We appreciate your help in this manner,
Thanks!
Drew Kirsch, E.I.
www.chengineers.com
4
"This message and/or attachment contains confidential information. Distribution of this
information must be only to those of C&H Engineering and Surveying, Inc employees or
individuals contractually approved to receive this information. If you are not the
addressee and/or are not authorized to receive this for the addressee, you must not use,
copy, disclose,forward, print or take any action based on this message or any information
herein. If you have received this message in error, please advise the sender immediately
by reply e-mail and delete this message."
From: Wussow, Daniel <Daniel.Wussow@northwestern.com>
Sent: Monday, March 22, 2021 3:47 PM
To: Drew Kirsch <dkirsch@chengineers.com>
Cc: Swanson, Dylan <Dylan.Swanson@northwestern.com>; Workman, Dustin <Dustin.Workman@northwestern.com>
Subject: RE: Westland Loft Phase 2 Rear Utility Easement
Drew,
I just discussed the easement release and reconveyance with our construction Manager, Dustin Workman. He is
attached to this email.
Northwestern Energy releases the rear 10’ utility easement behind building C on Lot 5, Block14 for Westland Lofts Phase
2, Baxter Meadows Subdivision, as indicated by the blue area in the drawing below:
5
The release and reconveyance is to accommodate the rear patios and fences for Buildings C in the Westland Lofts Phase
2 site plan.
Northwestern Energy will be providing utility services to the building from the north and south and will not need to run
utilities to the east of building C.
Please let me know if this will work for DRC. If you have any questions please let me know.
Thanks,
Daniel Wussow
From: Drew Kirsch <dkirsch@chengineers.com>
Sent: Monday, March 15, 2021 4:39 PM
To: Wussow, Daniel <Daniel.Wussow@northwestern.com>
Cc: Steve Mcgough <mcgoughconstruction@yahoo.com>
Subject: [EXTERNAL] Westland Loft Phase 2 Rear Utility Easement
6
CAUTION: This Email is from an EXTERNAL source outside of NorthWestern Energy.
The Original Sender of this email is dkirsch@chengineers.com.
Are you expecting the message? Is this different from the message sender displayed above?
Do not click on links or open attachments unless you are sure you recognize the sender and
you know the contents are safe.
If you believe the email to be malicious and/or phishing email, please use the Report Phish button.
Hi Daniel,
We don’t not have standard letter form for utility release and reconveyance. Emails have sufficed in the past. The
proposed easement release and reconveyance for Westland Lofts phase 2 would include the rear 10’ utility easement on
Lot 5, Block14, Baxter Meadows Subdivision, Phase 2. The release and reconveyance is requested to accommodate the
rear patios and fences for Buildings C in the Westland Lofts Phase 2 site plan. Please see the area highlighted below. It
would be great if you could respond providing your approval via email as proof for the City. Thanks!
Thanks,
Drew Kirsch, E.I.
Upcoming Out of Office – March 22nd-March 26th, 2021
7
www.chengineers.com
"This message and/or attachment contains confidential information. Distribution of this
information must be only to those of C&H Engineering and Surveying, Inc employees or
individuals contractually approved to receive this information. If you are not the
addressee and/or are not authorized to receive this for the addressee, you must not use,
copy, disclose,forward, print or take any action based on this message or any information
herein. If you have received this message in error, please advise the sender immediately
by reply e-mail and delete this message."
This message is for the named person's use only. It may contain confidential, proprietary or legally privileged
information. No confidentiality or privilege is waived or lost by any mistransmission. If you receive this message in error,
please immediately delete it and all copies of it from your system, destroy any hard copies of it and notify the sender.
You must not, directly or indirectly, use, disclose, distribute, print, or copy any part of this message if you are not the
intended recipient. NorthWestern Corporation and its subsidiaries each reserve the right to monitor all e‐mail
communications through its network.
The contents of this e‐mail message and
any attachments are intended solely for the
addressee(s) and may contain confidential
and/or legally privileged information. If you
are not the intended recipient of this message
or if this message has been addressed to you
in error, please immediately alert the sender
by reply e‐mail and then delete this message
and any attachments. If you are not the
intended recipient, you are notified that
any use, dissemination, distribution, copying,
or storage of this message or any attachment
is strictly prohibited.
The contents of this e‐mail message and
any attachments are intended solely for the
addressee(s) and may contain confidential
and/or legally privileged information. If you
are not the intended recipient of this message
or if this message has been addressed to you
in error, please immediately alert the sender
by reply e‐mail and then delete this message
and any attachments. If you are not the
intended recipient, you are notified that
any use, dissemination, distribution, copying,
or storage of this message or any attachment
is strictly prohibited.