HomeMy WebLinkAbout(32a) City Wetlland Report Bridger Meadows_Naiad_Review TQ Response 03-02-2021
Section 32a – Applicant Responses City Wetland Report NAIAD Review
Bridger Meadows Neighborhood Development
PUD Preliminary Plan Application 20350
Subdivision Preliminary Plat Application 20351
March 2, 2021
Sarah Rosenberg, Associate Planner
City of Bozeman
121 N Rouse Ave
Bozeman, Mt 59715
RE: Responses to City of Bozeman Review of Bridger Meadows Subdivision Sensitive Areas
_________________________________________________________________________________
Dear Sarah,
Responses (blue) to City of Bozeman (COB) review of Aquatic Sensitive Areas are below each
bulleted review point.
• Ms. Bacon notes that the subdivision’s original design had the road east of the lots, a design that would
impact about 0.74 acres of wetland and much of the setbacks. The site was redesigned, and the wetland
impacts were reduced to 0.078 acres. This current design is shown in Figure 1. Although I commend the
reduced impact in the redesigned project, simply juxtaposing the two designs does not adequately show
avoidance and minimization. We can assume that there are many problems with the first effort, besides
wetland impacts, that would make that design unreasonable (e.g., increase expense of grading and lot
values with open area adjacent -vs.- across the street). Avoidance and minimization can and should be an
iterative effort. There are five areas where the current design could be altered, and one or more would
provide additional avoidance and minimization of impacts to sensitive areas. Please refer to the circled
areas in Figure 1 (this figure has been placed at the end of this document).
Wetlands have been avoided and impacts minimized by redesigning the project into its
current configuration. Decreasing impacts from 0.74 acre to 0.091 acre qualifies as both
avoidance and minimization, to the maximum extent practicable.
• Area 1 – There is no description of the grading that extends into the setback area in this location. Nor is
it labeled on the are Grading and Drainage Plan. Without this explanation, it is difficult to know its
purpose or conceive a path to avoid and minimize impacts on the setback.
• The impacts in Area 1 are not in a sensitive area and do not impact any existing wetlands. The
proposed excavation is the removal of artificially placed fill (an old railroad bed). The fill is
being removed to increase the 100-year flood storage volume of the East Gallatin River, to
offset loss of flood storage volume in other areas of the site. The Applicant intends to
excavate Area 1 down to about the same elevation as the surrounding wetlands, then remove
wetland sod/seed mats from impacted wetlands and re-plant them in this area. Wetland plants
would very likely re-establish themselves in some or all of Area 1 due to the new conditions
(shallower groundwater), resulting in a new wetland area that is larger than the total area of
currently proposed wetlands impacts, even at a 50% reduction factor for replacement wetlands.
Bridger Meadows Neighborhood March 2, 2021
Applicant Responses City Wetland Report NAIAD Review
Page 2
• Area 2 – The grading necessary for the building pad of Lot 4 is the reason for the most extensive wetland
impacts, those on Wetland 3 (0.60 acres). Eliminating one lot and reconfiguring the others could avoid
this wetland altogether and minimize other impacts to the setback.
The Wetland 3 acreage of 0.60 acres is misquoted and is actually 0.060 acres. Area 2
(Wetland 3) impacts were reduced to the extent feasible (from 0.060 to 0.035 acres) by
adjusting the Lot 4 lot line. This change also reduced floodplain impacts.
Any further reduction of impacts in this area would compromise other goals of the project
and of the City, such as the desire for infill development. Removing Lot 4 to protect an
additional 1,500 sq. ft. of Wetland 3, which was farmed agricultural land as recently as
2011, is not feasible. Allowing the development to move forward in an economically viable
manner allows the Applicant to follow his intent and vision to permanently preserve and
enhance almost all of the naturally occurring wetlands on the site, while having
homeowners close by with a vested interest in monitoring and preventing the degradation
of wetlands and unique wildlife habitat that has occurred in the past on this site.
• Area 3 – it appears that moving this utility crossing approximately 50 feet to the SE would avoid 0.01
acres of impact to Wetland 4,
All Wetland 4 impacts will be within the 30-foot utility easement, so wetland delineation was
not completed beyond those limits. Impacts would be similar east and west of the
proposed location. The utilities and easement are located to align sewer with an existing
manhole in Boylan Road, so cannot be moved.
• Area 4 – By switching the location of the stormwater management with Lot 7, it appears that additional
setback impacts could be reduced.
The impacts in Area 4 are primarily in an upland area of historically agricultural use.
Impacts to existing vegetation extending toward the wetland is necessary to discharge
storm water from an underground detention facility. The stormwater facility’s location is set
by the low point in the road and cannot be moved west to the area of Lot 7 due to the rise
in road elevation. Moving the road’s low point to the west would not allow enough elevation
drop for collection, storage, and treatment of all street runoff.
• Lastly, Area 5 – The ‘Ground Water Discharge Pipe’ and proposed retention basin outfall could be
moved to the east to have the pipe discharge into the upland area, thereby avoiding the impact of 0.008
acres of impact.
The Area 5 (Wetland 1) impact, previously required for a groundwater discharge pipe, has
been removed from the project along with the pipe. This eliminates ground disturbance
within sensitive areas (existing wetlands and floodplain) in Area 5.
• Setback Impacts
• I do not see any setbacks on Wetland 3 in Exhibit C. It appears that Wetland 3 is connected
to the floodway, and its buffer should also extend.
Wetland 3 is not an immediately adjacent (i.e., fringe) wetland, therefore per the UDC is
not included in the watercourse setback. Whether it is connected to the floodway or not
is irrelevant. There is no wetland buffer for the same reason.
• Lot 7 has a setback impact but not included in the application.
A relaxation from the wetland buffer requirement has been requested with this
application. The proposed wetland buffer is shown on the revised Exhibit C and is
within the rear building setback area.
Bridger Meadows Neighborhood March 2, 2021
Applicant Responses City Wetland Report NAIAD Review
Page 3
• Grading setback impacts for the proposed retention basin in the SE corner near Wetland 1
are not in the application.
The groundwater pipe has been removed from the project, and all associated impacts
to the existing 100-year floodplain and existing wetlands have been eliminated. The
ground disturbance area for the retention pond is outside of the watercourse setback,
but within the wetland buffer which is acceptable.
• I do not see a total area of wetland setback impacts
Calculation of watercourse setback impact areas is not required in the UDC so was not
provided. There are no impacts within the proposed watercourse setback. This is also
true for non-compliant uses within the proposed wetland buffer.
• I do not see any plan for the mitigation of these impacts.
The proposed watercourse setback does not extend into any of the residential lots or
proposed improvements, except re-grading and re-vegetating to mitigate floodplain
impacts. The proposed wetland buffer does not extend beyond the rear setback line of
any residential lot. Landscaping and minor improvements are allowed within the rear
setback and wetland buffer.
• No functional assessment.
Given wetland impact was reduced through Avoidance and Minimization from 0.74 to
0.091 acre, decrease in wetland function is deemed not a concern by this TerraQuatic
Wetland Scientist. Functional Assessments will not be provided.
• Sec 38.610.080.A.3.d requires an assessment of cumulative impacts, but I did not see that in this
report.
No cumulative impacts assessment is provided; no other impacts have occurred as a result
from this property owner.
• There was a lot of discussion about the ‘defunct stormwater system’ north of the property. The
pond to the north is open water, and the relevance of its history may be a concern to the
USACOE, but I do not believe it is relevant to City.
The stormwater system north of the property is of concern because it is not functioning;
sediment has filled the basin and groundwater infiltration has increased downslope of the
facility, i.e. Wetland-3 has doubled in size in the last 5 years.
• Impacts on Wetland 4 and Wetland 1 are not mentioned in the report.
Do not know what this item means. In general impacts are not reviewed within an aquatic
resource delineation summary document.
• I am not convinced that the buildable area in Lot 4 cannot be reduced to a footprint similar to lot
2.
See response above regarding Figure 1, Area 2. Area 2 (Wetland 3) impacts were reduced
to the extent feasible (from 0.060 to 0.035 acres) by adjusting the Lot 4 lot line. Further
reduction to eliminate all impacts to Wetland 3 would reduce the depth to less than Lot 2.
Additionally, the front lot width is much less than Lot 2, so the resulting area within the
building setback lines, as well as its triangular shape, would result in a lot that is too small
for a typical home consistent with the project.
Bridger Meadows Neighborhood March 2, 2021
Applicant Responses City Wetland Report NAIAD Review
Page 4
• In Ms. Bacon’s response to 38.30.090.A.5, she states that “City of Bozeman watercourse 50-
foot wide setbacks along connected wetlands are greater than federal USACE restrictions.”
USACOE has no buffer requirements and leaves this to state and local governments to establish.
These are clearly stated in the City Code; therefore, I do not see this statement’s relevance.
The item asks if City restrictions are greater, simple answer: Yes. This was just an answer
to a question with no expectation regarding relaxation requests.
• There is a French drain that is mentioned several times, but I do not see it in the plan submitted
with the application.
There is an existing French Drain about 8 feet northeast of Bridger Meadows. The
previous submittal proposed connecting a new pipe through Bridger Meadows that would
discharge collected groundwater into the south end of the Bridger Meadows pond. This
new pipe has been deleted from the project. The existing French Drain collects a
significant amount of groundwater which discharges continuously into the Boylan Road
ditch and into the existing detention basin north of Bridger Meadows. Due to lack of
maintenance and/or design issues, the detention outfall path has migrated from its intended
discharge to the west and now flows toward and into Bridger Meadows, either creating or
greatly expanding Wetland 3 on land that was farmed agricultural land as recently as 2011.
The groundwater pipe was shown inaccurately on the previous submittal and has been
moved to match the location on the record drawing.
• In sec 38.41.130.3 in the review document, Ms. Bacon states that there is no mitigation required
for impacts below 0.10 acres. This may be allowable for the USACOE CWA permits; however,
I do not see a size limit in the City of Bozeman code.
When the USACE enters into the jurisdictional aquatic resources impact mitigation the City
does not require additional mitigation requirements. The City does require mitigation
‘negotiation’ for nonjurisdictional (NJ) aquatic resource impacts with the exception of most
(if not all) stormwater facilities and true irrigation ditch features. Mitigation quantities and
types for impacts to NJ features vary from project to project and depend on myriad aquatic
resource characteristics as affected by the proposed development during analysis by City
Aquatic Resource Subconsultants.
• The review material focuses on impacts in Wetland 3 but reports different numbers than those
in the Exhibit B impact table. The review material also reports other impact numbers for
Wetland 4 and does not report impacts to Wetland 1.
Please review enclosed revised Exhibit B impact map. This map has been submitted to the
USACE.
Sincerely,
Lynn Bacon, PWS
TerraQuatic, LLC
614 Lamme Street
Bozeman, MT 59715
lbacon@terraquaticllc.com
Bridger Meadows Neighborhood March 2, 2021
Applicant Responses City Wetland Report NAIAD Review
Page 5
Figure 1. Five specific areas of potential avoidance or minimization.