ADDENDUM NO. 1
PROJECT NAME: Downtown Bozeman Streetscape Project 2021
PROJECT No. : B19-096
This addendum No. 1 forms part of the Contract Documents and modifies the original Bidding
Documents as noted below. All provisions of the Contract Documents not in conflict with this
Addendum shall remain in full force. Acknowledge receipt of this Addendum in the space
provided on the Bid Form and on the outside of the Bid Envelope. Failure to do so may
subject the Bidder to disqualification.
This addendum consists of two (2) pages and two (2) attachments.
1. CHANGES TO CONTRACT DOCUMENTS:
Bid Form – New Bid Form attached to this addendum.
Revise the following:
The allowed contract time shall be 30 45 calendar days total. These 30 45
days shall be consecutive days and can occur any time between June 14
July 1, 2021 and August 20 October 29, 2021.
Agreement Form – New Agreement Form attached to this addendum.
Revise the following:
The Work will be completed within 30 45 calendar days total after the date when
the contract time commences to run as provided in the General Conditions. These
30 45 days shall be consecutive days and can occur any time between June 14
July 1, 2021 and August 20 October 29, 2021. Final payment will be withheld until
final completion and acceptance of the Work, as stipulated in this Agreement.
I hereby certify that this Addendum was prepared by me or under my direct supervision, and
that I am duly registered as a Professional Engineer under the laws of the State of Montana.
Kyle Scarr, PE
Registration Number 16813 PE
6/7/2021
Page 2
Attachments: Revised Bid Form
Revised Agreement Form
END OF ADDENDUM NO. 1
BID FORM 1
BID FORM
DOWNTOWN BOZEMAN STREETSCAPE
CITY OF BOZEMAN
BOZEMAN, MONTANA 59771
TO: City Clerk
P.O. Box 1230
Bozeman, Montana 59771-1230
THE UNDERSIGNED BIDDER, having familiarized himself with the Work required by the Contract
Documents, the site(s) where the work is to be performed, local labor conditions and all laws,
regulations, municipal ordinances and other factors which may affect the performance of the Work, and
having satisfied himself of the expense and difficulties attending performance of the work:
HEREBY PROPOSES and agrees, if this bid is accepted, to enter into an Agreement, in the form
attached, to perform all work for the construction of ROUSE AVENUE LIGHTING BETWEEN MAIN
STREET AND LAMME STREET, including the assumption of all obligations, duties, and
responsibilities necessary for the successful completion of the contract and the furnishing of all materials
and equipment required to be incorporated in, and form a permanent part of, the work; tools, equipment,
supplies, transportation, facilities, labor, superintendence, and services required to perform the Work;
Bonds, Insurance and Submittals; all as indicated or specified in the Contract Documents to be
performed or furnished by Contractor within the time and for the prices set forth in the following
schedules.
The undersigned bidder agrees to be bound by this Bid for a period not to exceed that specified in the
Invitation to Bid.
The undersigned Bidder agrees to furnish the required Bonds and to enter into a contract within fifteen
(15) calendar days after Owner's acceptance of this Bid, and further agrees to complete all Work within
the time specified per schedule after commencement of the contract time as defined in the General
Conditions.
The allowed contract time shall be 45 calendar days total. These 45 days shall be consecutive days and
can occur any time between July 1, 2021 and October 29, 2021.
Where multiple schedules are awarded under a single Contract, the contract times shall run concurrently
unless separate notices to proceed are issued for the awarded schedules.
Liquidated Damages shall be as specified in Article 2.2 & 2.3 of the Agreement Form.
The undersigned Bidder agrees that the unit prices shall govern in checking the Bid, and should a
discrepancy exist in the total prices and total amount of Bid as listed above, after extensions are checked
BID FORM 2
and corrections made, if any, the total amount of the Bid as corrected shall be used in awarding the
contract.
The undersigned Bidder agrees that he has been afforded access to the construction site and has
performed those independent site investigations as he deemed necessary.
The undersigned Bidder hereby certifies the following:
A) That this Bid is genuine and is not made in the interest of, or on behalf of, any undisclosed person,
firm, or corporation, and is not submitted in conformity with any agreement or rules of any group,
association, organization, or corporation;
B) That he has not directly or indirectly solicited any other Bidder to put in a false or sham Bid;
C) That he has not solicited or induced any person, firm, or corporation to refrain from bidding;
D) That he has not sought by collusion to obtain for himself any advantage over any other Bidder or
over the Owner.
E) That he is not currently operating beyond the contract time on any previously awarded public works
contract as defined and required by Article 15-50-203, MCA, as amended.
The undersigned Bidder(s) either singularly or as a joint venture hereby certifies (certify) pursuant to
Article 37-71-203, MCA, that he (they) is (are) duly and regularly licensed.
BID FORM 3
BIDDER agrees to perform all the work described in the CONTRACT DOCUMENTS for the following
unit prices or lump sums:
BID SCHEDULE
Item Description Unit
Unit
Price
Estimated
Quantity
Total Estimated
Price
101 Mobilization L.S. 1
102 Traffic Control L.S. 1
103
Protect Existing Structures and
Utilities (Overhead and
Underground)
L.S.
1
Streetscape Improvements
201 Saw Cut Existing
Asphalt/Concrete L.F. 185 FT
202 Remove and Replace Existing
Asphalt S.Y. 42 SY
203 Remove and Replace Existing
Sidewalk S.F. 255 SF
204 Structural Concrete Pole
Foundation EA. 20
205 Conduit, 2.0” PVC, Sidewalk-
Boulevard Trench L.F. 108 FT
206 Conduit, 2.0” PVC, Street Trench L.F. 68 FT
207 Conductor, Copper, #10 AWG,
Lighting & Ground L.F. 3700 FT
208
Install Owner Supplied
Decorative Light Pole and
Luminaire Assembly
EA.
20
209 Electrical Service EA. 1
TOTAL BID $_____________________
____________________________________________________________________________________
(TOTAL BID - WRITTEN WORDS)
BID FORM 4
BASIS OF AWARD If the contract is awarded, the Owner will award a single Contract in accordance
with the Instructions to Bidders. Bidders shall submit a Bid for all bid Schedules on a unit price
basis for each item of Work listed as provided and described above. The Owner reserves the right to
accept or reject the Bids, or portions of the Bids denoted as separate schedules or alternates. The award
will be made by the Owner on the basis of that Bid from the lowest responsive, responsible Bidder
which, in the Owner’s sole and absolute judgment, will best serve the interest of the Owner. The low
bidder will be determined on the basis of the lowest Total Combined Bid.
The undersigned Bidder acknowledged receipt of the following Addenda, which have been considered in
preparation of this Bid:
No._____________________________ Dated____________________
No._____________________________ Dated____________________
No._____________________________ Dated____________________
No._____________________________ Dated___________________
Submitted this _____ day of _____________________, 2021.
SIGNATURE OF BIDDER:__________________________________________
Montana Contractor Registration Number______________________________
If an individual:_____________________________________________
doing business as_____________________________________________
If a Partnership:___________________________________________by
________________________________________, partner
_____________________________________________
If a Corporation:_____________________________________________
(a) ____________________________________________
by ____________________________________________
(Seal &
Title___________________________________________ Attest)
Business Address of Bidder: __________________________________
BID FORM 5
If Bidder is a joint venture, other party must sign below:
Montana License Number and Class______________________________
If an Individual:_______________________________________ doing
business as _________________________________________________.
If a Partnership: __________________________________________
by ________________________________Partner
__________________________________________
If a Corporation:____________________________________________
(a)______________________________Corporation
by _________________________________________
(Seal &
Title________________________________________ Attest)
AGREEMENT FORM
THIS AGREEMENT is dated as of the day of ________ in the year 2021, by and between
CITY OF BOZEMAN, hereinafter called OWNER, and ______________________ hereinafter
called CONTRACTOR.
OWNER AND CONTRACTOR, in consideration of the mutual covenants hereinafter set forth,
agree as follows:
Article 1. WORK.
CONTRACTOR shall complete all Work as specified or indicated in the Contract Documents.
The project work is generally described as follows: Reconstruction of South 6th Avenue from
Babcock Street to Cleveland Street including: replacement of existing water mains, valves,
fittings and appurtenances, sewer mains and manholes, and storm drainage pipe, inlets and
manholes; removing the existing road section from curb to curb and constructing a new road
section, new signage, spot replacement of existing sidewalks, adjusting existing utilities to
accommodate the new roadway, restoring boulevards to pre-existing conditions and all related
work incidental to construction.
The project for which the Work under the Contract Documents may be the whole or only a part is
generally described as follows: Rouse Avenue Lighting between Main Street and Lamme Street,
City of Bozeman.
Article 2. CONTRACT TIME.
2.1 The Work will be completed within 45 calendar days total after the date when the contract
time commences to run as provided in the General Conditions. These 45 days shall be
consecutive days and can occur any time between July 1, 2021 and October 29, 2021. Final
payment will be withheld until final completion and acceptance of the Work, as stipulated in
this Agreement.
2.2 Liquidated Damages. OWNER and CONTRACTOR recognize that time is of the essence in
this Agreement and that OWNER will suffer financial loss if the Work is not substantially
complete within the time specified above, plus any extensions thereof allowed in accordance
with the General Conditions. They also recognize the delays, expense and difficulties
involved in proving, in a legal or arbitration proceeding, the actual loss suffered by OWNER
if the Work is not substantially complete on time. Accordingly, instead of requiring any such
proof, OWNER and CONTRACTOR agree that as liquidated damages for delay (but not as a
penalty) CONTRACTOR shall pay OWNER seven hundred fifty dollars ($ 750.00) for each
day that expires after the time specified herein until the Work is substantially complete.
2.3 Special Liquidated Damages. OWNER and CONTRACTOR further recognize that time is
of the essence in accommodating water service interruptions throughout the course of the
project, and that owner will suffer financial loss if the provisions specified below are not
met:
1. All water system interruptions shall comply with the time frames specified in Special
Provision 33, or shall be subject to the provisions of this section of this agreement.
OWNER and CONTRACTOR also recognize the delays, expense and difficulties involved in
proving, in a legal or arbitration proceeding, the actual loss suffered by OWNER if the
provisions listed in section 2.3.1 of this agreement are not met. Accordingly, instead of
requiring any such proof, OWNER and CONTRACTOR agree that as liquidated damages for
delay (but not as a penalty) CONTRACTOR shall pay OWNER five hundred dollars ($
500.00) or for each hour that expires after the maximum time allowed for water service
interruptions specified in section 2.3.1 of this agreement, until the Work is substantially
complete.
Article 3. CONTRACT PRICE.
3.1 OWNER shall pay CONTRACTOR for performance of the Work in accordance with the
Contract Documents the sum (subject to adjustment as provided in the Contract Documents)
of _________________________________________________________ ($__________).
Article 4. PAYMENT PROCEDURES.
CONTRACTOR shall submit applications for payment in accordance with the General Conditions.
Applications for payment will be processed as provided in the General Conditions.
4.1 Progress Payments. OWNER will make progress payments monthly on account of the
contract price on the basis of CONTRACTOR'S application for payment as recommended by
ENGINEER. All progress payments will be on the basis of the progress of the Work
measured by the schedule of values provided for in the General Conditions.
4.1.1 The OWNER may retain five (5) percent of the amount due the CONTRACTOR in
accordance with the General Conditions and as outlined herein.
4.2 Final Payment. Upon final completion and acceptance of the Work in accordance with the
General Conditions, OWNER shall pay the remainder of the contract price as recommended
by ENGINEER.
Article 5. INTEREST.
All monies not paid when due hereunder shall bear interest at the simple rate established by
the Federal Cost of Money Rate commencing at the time of a claim.
Article 6. CONTRACTOR'S REPRESENTATIONS.
In order to induce OWNER to enter into this Agreement, CONTRACTOR makes the
following representations:
6.1 CONTRACTOR has familiarized himself with the nature and extent of the Contract
Documents, Work, locality, and with all local conditions and federal, state and local laws,
ordinances, rules and regulations that in any manner may affect cost, progress or performance
of the Work.
6.2 CONTRACTOR has studied carefully all reports of investigations and tests of subsurface
and latent physical conditions at the site or otherwise affecting cost, progress or performance
of the Work which were relied upon by ENGINEER in the preparation of the drawings and
specifications and which have been identified in the modifications to the General Conditions.
6.3 CONTRACTOR has made or caused to be made examinations, investigations and tests and
studies of such reports and related data in addition to those referred to above as he deems
necessary for the performance of the Work at the contract price, within the contract time and
in accordance with the other terms and conditions of the Contract Documents, and no
additional examinations, investigations, tests, reports or similar data are or will be required
by CONTRACTOR for such purposes.
6.4 CONTRACTOR has correlated the results of all such observations, examinations,
investigations, tests, reports and data with the terms and conditions of the Contract
Documents.
6.5 CONTRACTOR has given ENGINEER written notice of all conflicts, errors or discrepancies
that he has discovered in the Contract Documents and the written resolution thereof by
ENGINEER is acceptable to CONTRACTOR.
6.6 Nondiscrimination and Equal Pay: The Contractor agrees that all hiring by Contractor of
persons performing this Agreement shall be on the basis of merit and qualifications. The
Contractor will have a policy to provide equal employment opportunity in accordance with
all applicable state and federal anti-discrimination laws, regulations, and contracts. The
Contractor will not refuse employment to a person, bar a person from employment, or
discriminate against a person in compensation or in a term, condition, or privilege of
employment because of race, color, religion, creed, political ideas, sex, age, marital status,
national origin, actual or perceived sexual orientation, gender identity, physical or mental
disability, except when the reasonable demands of the position require an age, physical or
mental disability, marital status or sex distinction. The Contractor shall be subject to and
comply with Title VI of the Civil Rights Act of 1964; Section 140, Title 2, United States
Code, and all regulations promulgated thereunder.
Contractor represents it is, and for the term of this Agreement will be, in compliance with the
requirements of the Equal Pay Act of 1963 and Section 39-3-104, MCA (the Montana Equal Pay
Act). Contractor must report to the City any violations of the Montana Equal Pay Act that Contractor
has been found guilty of within 60 days of such finding for violations occurring during the term of
this Agreement.
Contractor shall require these nondiscrimination terms of its subcontractors providing
services under this Agreement.
Article 7. CONTRACT DOCUMENTS.
The Contract Documents which comprise the entire Agreement between OWNER and
CONTRACTOR are attached to this Agreement, made a part hereof and consist of the following:
7.1 This Agreement.
7.2 Exhibits to this Agreement (if any).
7.3 Performance Bond, Payment Bond, and Bid Bond.
7.4 Invitation to Bid.
7.5 Instructions to Bidders and Bid Form.
7.6 Certificate(s) of Insurance.
7.7 Standard General Conditions.
7.8 Supplementary Conditions.
7.9 Wage Rates.
7.10 Special Provisions and Measurement and Payment.
7.11 Montana Public Works Specifications, Sixth Edition, MDT Standard Specifications, Latest
Edition, and City of Bozeman Modifications to Montana Public Works Standard
Specifications Sixth Edition, March 31, 2011 with addenda (by reference).
7.12 Appendices
7.13 Addenda listed on the Bid forms.
7.14 CONTRACTOR'S executed Bid forms.
7.15 Documentation submitted by CONTRACTOR prior to Notice of Award.
7.16 Notice of Award.
7.17 Notice to Proceed.
7.18 Any modification, including Change Orders, duly delivered after execution of Agreement.
7.19 Any Notice of Partial Utilization.
7.20 Notice of Substantial Completion.
7.21 Notices of Final Completion and Acceptance.
7.22 Non-discrimination affirmation form.
7.23 Plan Set
7.24 Streetlamp Specifications
7.25 Order to Suspend Work and to Resume Work
7.26 Lien Waivers for Prime Contractors and Subcontractors. Any Contractor Certificates and
Releases
There are no Contract Documents other than those listed above in this Article 7. The Contract
Documents may only be altered, amended or repealed by a modification (as defined in the General
Conditions).
Article 8. MISCELLANEOUS.
8.1 Terms used in this Agreement which are defined in the General Conditions shall have the
meanings indicated in the General Conditions.
8.2 This Agreement and all of the covenants hereof shall inure to the benefit of and be binding
upon the OWNER and the CONTRACTOR respectively and his partners, successors,
assigns, and legal representatives. Neither the OWNER nor the CONTRACTOR shall have
the right to assign, transfer or sublet his interest or obligations hereunder without written
consent of the other party. The OWNER reserves the right to withdraw at any time from any
subcontractor where Work has proven unsatisfactory the right to be engaged in or employed
upon any part of the Work.
8.3 In the event it becomes necessary for either party to this Agreement to retain an attorney to
enforce any of the terms or conditions of this Agreement or to give any notice required
herein, then the prevailing party or the party giving notice shall be entitled to reasonable
attorney's fees and costs.
8.4 Any amendment of modifications of this Agreement or any provisions herein shall be made
in writing and executed in the same manner as this original document and shall after
execution become a part of this Agreement.
IN WITNESS WHEREOF, the parties hereto have executed this Agreement the day and year first
above written.
(CONTRACTOR)
By (SEAL &)
(ATTEST)
Title
_____________________________
(JOINT VENTURE)
By (SEAL &)
(ATTEST)
Title
_____________________________
City of Bozeman
(OWNER)
By _____________________________
(CITY MANAGER)
(SEAL &)
(ATTEST)
_____________________________
APPROVED AS TO FORM:
________________________________
(CITY ATTORNEY)