HomeMy WebLinkAbout18 - Design Report - The Nest PUD - Stormwater
DESIGN REPORT
STORMWATER MANAGEMENT
THE NEST P.U.D. SUBDIVISION
Prepared for:
Center Arrow Partners, LLC
P.O. Box #1633, Bozeman, Montana 59771
Prepared by:
C&H Engineering and Surveying, Inc.
1091 Stoneridge Drive, Bozeman, MT 59718
(406) 587-1115
Project Number: 180805
October 2019
Page 1 of 21
INTRODUCTION
The proposed Nest PUD Subdivision is a 44-lot townhome and condominium development located
on a 5.41-acre parcel in Section 4, Township 2 South, Range 5 East of P.M.M., Gallatin County,
City of Bozeman. A combination of site grading, curb and gutter, storm inlets, piping, and swales
will be used to manage stormwater runoff on the site. Supporting stormwater calculations are
attached to this report. A Drainage Area Map is included in Appendix A. Calculations for each
individual drainage area (total area, weighted C factor, and time of concentration) are included in
Appendix B.
RETENTION/DETENTION POND DESIGN
All ponds have been sized according to City of Bozeman Design Standards. They are designed
with an effective water depth of 1.5 feet, and maximum side slope of 4:1. Detention ponds are
sized to limit discharge to pre-development rates for the 10-year storm event. Detention ponds are
also sized to retain the first 0.5 inches of rain from a 10-year, 2-hour storm event before the outlet
structure begins to discharge. Calculations used for sizing each pond can be found in Appendix C.
Design pond capacities were calculated using volume surfaces in AutoCAD Civil3D.
STORM SEWER FACILITIES DESIGN
Storm sewer facilities were sized for the 25-yr storm using Manning’s Equation. For each inlet,
the contributing area, weighted C factor, and time of concentration were calculated. These values
were input into Manning’s Equation to check capacity and flow characteristics for inlets, storm
drain pipes, and curb gutters. All curbs are designed to maintain 0.15’ freeboard per C.O.B. Design
Manual Section IV.C.5. For the purposes of this report, each pipe section was named to match the
associated upstream structure. Pipe sizing calculations are included in Appendix D.
Existing Retention Pond #1
Existing Retention Pond #1 is located north of Durston Road along the southern property line Lot
4. This pond will be relocated with the proposed development and will be upgraded to a detention
pond in order to reduce the required footprint. The pre-development time to concentration was
calculated to be 9.3 minutes and the pre-development runoff rate for the 10-yr storm was calculated
Page 2 of 21
to be 0.51 cfs. There is a 1” weir in the outlet structure that limits runoff to the pre-development
runoff rate of 0.51 cfs. The weir is to be located 1’ above the bottom of pond so that the first 0.5
inches of rain is retained before the stormwater is discharged into the existing wetland area. It
receives runoff from Durston Road (Drainage Area #EX1). The new required pond volume was
calculated to be 1,167 cubic feet from Drainage Area #EX1, totaling 1.20 acres. The proposed
pond volume is 2,014 cubic feet. In the case of larger storms beyond the pond’s capacity to capture
and infiltrate, the pond will overtop and flow west into Baxter Creek. Supporting calculations for
the required pond volume can be found in Appendix C.
Existing Retention Pond #2
Existing Retention Pond #2 is located south of Annie Street and west of proposed Lot 4. It receives
runoff from Drainage Areas 1 and EX2, totaling 6.22 acres. The existing retention pond will be
upgraded to a detention pond by installing an outlet structure in order to reduce the required
footprint of the pond. The pre-development time to concentration was calculated to be 52 minutes
and the pre-development runoff rate for the 10-yr storm was calculated to be 0.87 cfs. There is a
1.7” weir in the outlet structure that limits runoff to the pre-development runoff rate of 0.87 cfs.
The weir is to be located 1’ above the bottom of pond so that the first 0.5 inches of rain is retained
before the stormwater is discharged into the existing wetland area. The pond currently receives
runoff from Annie Street (Drainage Area #EX2). The existing pond volume is 6,445 cubic feet at
an effective water depth of 1.5’. The water depth has the ability to exceed 1.5’ as it is currently a
2.5’ deep pond. There is an existing chain link fence installed around the pond to provide a safety
barrier to pedestrians. The existing required pond volume is 2,669 cubic feet (retention) from the
Westbrook Subdivision and the new required pond volume including the Nest development was
calculated to be 6,151 cubic feet (detention) from Drainage Areas #1 and #EX2, totaling 6.22
acres. In the case of larger storms beyond the pond’s capacity to capture and infiltrate, the pond
will overtop and flow west into Baxter Creek. Supporting calculations for the required pond
volume can be found in Appendix C.
Page 3 of 21
APPENDIX A
DRAINAGE AREA MAP
Page 4 of 21
Page 5 of 21
APPENDIX B
DRAINAGE AREA CALCULATIONS
Page 6 of 21
DRAINAGE AREA #1
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2)C * Area
Hardscape 0.95 126546 120219
Landscape 0.2 109161 21832
Total 235707 142051
A = Area (acres)5.4111
C = Weighted C Factor 0.60
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%) 1.3% Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.35 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)139 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)14.4
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (%)0.72%
L = length of gutter (ft)1000
V = mean velocity (ft/s)2.54
Tc Gutter Flow (minutes) =6.6
Tc Total =21.0 (5 minute minimum)
Page 7 of 21
DRAINAGE AREA #EX1
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2)C * Area
Hardscape 0.95 52151 49544
Landscape 0.2 0 0
Total 52151 49544
A = Area (acres)1.1972
C = Weighted C Factor 0.95
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%) 1.0% Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.35 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)15 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)5.2
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (%)0.65%
L = length of gutter (ft)600
V = mean velocity (ft/s)2.42
Tc Gutter Flow (minutes) =4.1
Tc Total =9.3 (5 minute minimum)
Page 8 of 21
DRAINAGE AREA #EX2
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2)C * Area
Hardscape 0.95 35155 33397
Landscape 0.2 0 0
Total 35155 33397
A = Area (acres)0.8070
C = Weighted C Factor 0.95
2. Calculate Tc (Time to Concentration)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%) 1.0% Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.35 2 to 10 1
Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1
D = Length of Basin (ft)15 26 to 50 1.2
51 to 100 1.25
Tc Overland Flow (minutes)5.2
Tc Gutter Flow
Tc = L/V/60
V = (1.486/n)R2/3 S1/2
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft)0.13 (0.15' below top of curb)
S = slope (%)0.72%
L = length of gutter (ft)400
V = mean velocity (ft/s)2.54
Tc Gutter Flow (minutes) =2.6
Tc Total =7.8 (5 minute minimum)
Page 9 of 21
APPENDIX C
POND SIZING CALCULATIONS
Page 10 of 21
DETENTION POND #1
REQUIRED VOLUME
1. Calculate Area and Weighted C Factor (Post-Development)
Contributing Area C Area (ft 2 )C * Area
Hardscape 0.95 52151 49544
Landscape 0.2 0 0
Total 52151 49544
A = Area (acres)1.1972
C = Weighted C Factor 0.95
3. Calculate Tc (Pre-Development)
Tc (Pre-Development) (minutes)9.3
4. Calculate Rainfall Intensity (Duration = Pre-Development Tc)
i = 0.64x-0.65 (10-yr Storm, Fig. I-3, COB Design Standards)
x = storm duration (hrs)0.16 (Tc Pre-Development - DA EX1)
i = rainfall intensity (in./hr.)2.15
5. Calculate Runoff Rate (Pre-Development)
Q = CiA
C = Rational Method Runoff Coefficient 0.2 (open land)
i = rainfall intensity (in./hr.) 2.15 (calculated above)
A = Area (acres) 1.20 (calculated above)
Q = Runoff Rate (Pre-Development) (cfs) 0.51
Page 11 of 21
6. Calculate Required Pond Volume
Total Area (acres) = 1.20 acres
Weighted C = 0.95
Discharge Rate (cfs) = 0.51 cfs (Equal to Pre-Development Runoff Rate)
Duration(min) Duration(hrs)
Intensity
(in/hr)Qin (cfs)Runoff
Volume
Release
Volume
Required
Storage (ft3)
16 0.27 1.51 1.72 1650 494 1156
17 0.28 1.45 1.65 1685 525 1161
18 0.30 1.40 1.59 1719 555 1164
19 0.32 1.35 1.54 1752 586 1166
20 0.33 1.31 1.49 1784 617 1167
21 0.35 1.27 1.44 1815 648 1167
22 0.37 1.23 1.40 1845 679 1166
23 0.38 1.19 1.36 1873 710 1164
24 0.40 1.16 1.32 1902 741 1161
25 0.42 1.13 1.29 1929 771 1157
OUTLET STRUCTURE SLOT
Q=CLH3/2
Q = Discharge (cfs)0.51 (calculated above)
C = Weir Coefficient 3.33 (per COB Design Standards)
H = Head (ft)1.5
L = Horizontal Length (ft)0.08
L = Slot Width (inches)1.0
Page 12 of 21
DETENTION POND #2
REQUIRED VOLUME
1. Calculate Area and Weighted C Factor (Post-Development)
Contributing Area C Area (ft 2 )C * Area
Hardscape 0.95 161701 153616
Landscape 0.2 109161 21832
Total 270862 175448
A = Area (acres)6.2181
C = Weighted C Factor 0.65
3. Calculate Tc (Pre-Development)
Tc Overland Flow
Tc = 1.87 (1.1-CCf)D1/2/S1/3
Storm
S = Slope of Basin (%) 1.24% Return (yrs)Cf
C = Rational Method Runoff Coefficient 0.2 2 to 10 1
Cf = Frequency Adjustment Factor 1 11 to 25 1.1
D = Length of Basin (ft)1115 26 to 50 1.2
51 to 100 1.25
Tc (Pre-Development) (minutes)52
4. Calculate Rainfall Intensity (Duration = Pre-Development Tc)
i = 0.64x-0.65 (10-yr Storm, Fig. I-3, COB Design Standards)
x = storm duration (hrs)0.87 (Tc Pre-Development)
i = rainfall intensity (in./hr.)0.70
5. Calculate Runoff Rate (Pre-Development)
Q = CiA
C = Rational Method Runoff Coefficient 0.2 (open land)
i = rainfall intensity (in./hr.) 0.70 (calculated above)
A = Area (acres) 6.22 (calculated above)
Q = Runoff Rate (Pre-Development) (cfs) 0.87
Page 13 of 21
6. Calculate Required Pond Volume
Total Area (acres) = 6.22 acres
Weighted C = 0.65
Discharge Rate (cfs) = 0.87 cfs (Equal to Pre-Development Runoff Rate)
Duration(min) Duration(hrs)
Intensity
(in/hr)Qin (cfs)Runoff
Volume
Release
Volume
Required
Storage (ft3)
59 0.98 0.65 2.61 9225 3080 6145
60 1.00 0.64 2.58 9280 3133 6147
61 1.02 0.63 2.55 9334 3185 6149
62 1.03 0.63 2.52 9387 3237 6150
63 1.05 0.62 2.50 9440 3289 6151
64 1.07 0.61 2.47 9492 3341 6151
65 1.08 0.61 2.45 9544 3394 6150
66 1.10 0.60 2.42 9595 3446 6149
67 1.12 0.60 2.40 9645 3498 6147
68 1.13 0.59 2.38 9695 3550 6145
OUTLET STRUCTURE SLOT
Q=CLH3/2
Q = Discharge (cfs)0.87 (calculated above)
C = Weir Coefficient 3.33 (per COB Design Standards)
H = Head (ft)1.5
L = Horizontal Length (ft)0.14
L = Slot Width (inches)1.7
Page 14 of 21
APPENDIX D
STORM SEWER FACILITIES DESIGN
Page 15 of 21
PIPE #1 25-YR OUTFLOW RATE
REQUIRED CAPACITY
1. Calculate Area and Weighted C Factor (Post-Development)
Contributing Area C Area (ft 2 )C * Area
Hardscape 0.95 52151 49544
Landscape 0.2 0 0
Total 52151 49544
A = Area (acres)1.1972
C = Weighted C Factor 0.95
2. Calculate Rainfall Intensity (Duration = Max Tc from Contributing Drainage Areas)
i = 0.78x-0.64 (10-yr Storm, Fig. I-3, COB Design Standards)
x = storm duration (hrs) 0.16 DA #EX1
i = rainfall intensity (in./hr.) 2.57
3. Calculate 25-yr Pond Outflow Rate
Q = CiA
C = Rational Method Runoff Coefficient 0.95 (calculated above)
i = rainfall intensity (in./hr.) 2.57 (calculated above)
A = Area (acres) 1.20 (calculated above)
Q = 25-yr Flow Rate (cfs) 2.92
Page 16 of 21
MANNING'S EQUATION FOR PIPE FLOW
Project: Pipe 1 Location: Detention Pond 1 Outlet Pipe
INPUT
D= 15 inches
d= 14.07 inches
Mannings Formula n= 0.013 mannings c
57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.004 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter V=(1.49/n)Rh2/3S1/2
S=slope of channel Q=V x A
n=Manning's roughness coefficient
Solution to Mannings Equation
Area,ft2 Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.01
1.20 3.30 0.36 3.68 4.39 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
D
Page 17 of 21
PIPE #2 25-YR OUTFLOW RATE
REQUIRED CAPACITY
1. Calculate Area and Weighted C Factor (Post-Development)
Contributing Area C Area (ft 2 )C * Area
Hardscape 0.95 161701 153616
Landscape 0.2 109161 21832
Total 270862 175448
A = Area (acres)6.2181
C = Weighted C Factor 0.65
2. Calculate Rainfall Intensity (Duration = Max Tc from Contributing Drainage Areas)
i = 0.78x-0.64 (10-yr Storm, Fig. I-3, COB Design Standards)
x = storm duration (hrs) 0.35 DA #1
i = rainfall intensity (in./hr.) 1.53
3. Calculate 25-yr Pond Outflow Rate
Q = CiA
C = Rational Method Runoff Coefficient 0.65 (calculated above)
i = rainfall intensity (in./hr.) 1.53 (calculated above)
A = Area (acres) 6.22 (calculated above)
Q = 25-yr Flow Rate (cfs) 6.15
Page 18 of 21
MANNING'S EQUATION FOR PIPE FLOW
Pipe: Pipe 2 Location: Detention Pond 2 Outlet Pipe
INPUT
D= 15 inches
d= 14.07 inches
Mannings Formula n= 0.013 mannings C
57.7 degrees
Q=(1.486/n)ARh2/3S1/2 S= 0.01 slope in/in
R=A/P
A=cross sectional area
P=wetted perimeter V=(1.49/n)Rh2/3S1/2
S=slope of channel Q=V x A
n=Manning's roughness coefficient
Solution to Mannings Equation
Area,ft2 Wetted
Perimeter, ft
Hydraulic
Radius, ft velocity ft/s flow, cfs PVC 0.013
1.20 3.30 0.36 5.81 6.95 PE (<9"dia) 0.015
PE (>12"dia) 0.02
PE(9-12"dia) 0.017
CMP 0.025
ADS N12 0.012
HCMP 0.023
Conc 0.013
Manning's n-values
d
D
Page 19 of 21
APPENDIX E
BAXTER CREEK DOWNSTREAM
INFRASTRUCTURE
Page 20 of 21
Page 21 of 21
INSPECTION AND MAINTENANCE FOR
STORMWATER MANAGEMENT FACILITIES
The Property Owners Association shall be responsible for the maintenance of the stormwater
drainage facilities within The Nest PUD Subdivision development. Storm Water Facilities:
1. Drainage swales slope toward retention and detention ponds to collect storm water
runoff and channel it to the retention or detention pond.
2. Retention/Detention Ponds collect storm water runoff and store the water until it evaporates and/or infiltrates into the ground.
3. Detention ponds collect storm water runoff while allowing some water to drain to
another location.
4. Culverts are pipes which channel storm water from ditches or swales under roads.
5. Pipe Networks convey storm water to different discharge locations underground. 6. Inlets are facilities where storm water runoff enters a pipe network. Inlets include storm
water manholes and drains.
7. Catch Basins are sumps typically located directly below storm water inlets and allow
sediment to settle before storm water enters the pipe network.
8. Outlets are points where storm water exits a pipe network. 9. Drywells are underground storm water collection facilities that collect and temporarily
store runoff from roof tops and landscaped areas before allowing storm water to infiltrate
into the ground.
Post Construction Inspection: 1. Observe drain time in retention/detention ponds for a storm event after completion of the
facility to confirm that the desired drain time has been obtained. If excessively slow
infiltration rates are observed then excavate a minimum 5 ft by 5 ft drain to native gravels
(or native well-draining material) and backfill with well-draining material (pit-run).
2. Observe that drywells, catch basins, and outlet structures are clear of any material or obstructions in the drainage slots. Inspect these structures to insure proper drainage
following a storm event. Immediately identify and remove objects responsible for
clogging if not draining properly.
Semi-Annual Inspection: 1. Check retention/detention ponds and dry wells three days following a storm event
exceeding ¼ inch of precipitation. Failure for water to percolate within this time period
indicates clogging or poor-draining soils. Clear any clogs and replace any poor-draining
soils with well-draining gravely soils.
2. Check for grass clippings, litter, and debris in drainage swales, catch basins, dry wells, culverts and retention/detention ponds. Flush and/or vacuum drywells or storm water
pipes if excessive material is observed in the facilities.
Standard Maintenance:
1. Remove sediment and oil/grease from retention ponds and detention ponds. 2. Inspect and remove debris from drainage swales, catch basins, dry wells, and
retention/detention ponds. Use a vacuum truck to clean catch basins and dry wells.
3. Monitor health of vegetation and revegetate as necessary to maintain full vegetative
cover. 4. Inspect for the following issues: differential accumulation of sediment, drain time, signs of petroleum hydrocarbon contamination (odors, oil sheen in pond water), standing water,
trash and debris.
Sediment accumulation: In most cases, sediment from a retention/detention pond does not contain toxins at levels posing a hazardous concern. However, sediments should be tested for toxicants in compliance with current
disposal requirements and if land uses in the drainage area include commercial or industrial zones,
or if visual or olfactory indications of pollution are noticed. Sediments containing high levels of
pollutants should be disposed of in accordance with applicable regulations and the potential sources of contamination should be investigated and contamination practices terminated.