HomeMy WebLinkAbout18 - Design Report - The Crossing 2 at Baxter Meadows Ph 4G & 4H - StormJuly, 2018 L:\172708\Engineering Reports\Storm Report\Stormwater Report.doc Page 1 The Crossing 2 at Baxter Meadows Subdivision – Phase 4G & 4H Stormwater Report Bozeman, MT Introduction This report provides a design basis and hydraulic calculations for sizing stormwater infrastructure for The Crossing 2 at Baxter Meadows Subdivision – Phase 4G & 4H. The project in total is 5.8 acres of residential development and is located between the intersection of Vaquero Parkway and Baxter Lane to Vaquero Parkway and Davis Lane. Phases 4A through 4F of The Crossing have already been constructed. Stormwater calculations for the entire project (including phase 4G and 4H) were submitted in The Engineering Design Report for The Crossing at Baxter Meadows (March 2013). Generally the stormwater system and calculations have stayed consistent with what was originally submitted, but this report provides updated and additional information including inlet calculations, culvert capacity calculations and pond sizing. Much of this report will reference the Engineering Design Report for The Crossing at Baxter Meadows (March 2013). The City of Bozeman Design Standards and Specifications (March 2004) was used as the primary guideline for this stormwater drainage design along with The 2002 Edition of the Circular 8 of Montana Department of Environmental Quality (MDEQ). General Design Phase 4G and 4H will be a combination of roadway and residential lots. Vaquero Parkway has been designed with curb and gutter as originally designed in 2013. Stormwater runoff generated from the roadway and residential lots is designed to be collected by the curb and gutter and then directed toward the storm drain inlets. The runoff will then move through the storm sewer system pipes to the detention ponds. The detention ponds have been designed with outlet structures to limit stormwater runoff from the developed site to the pre-developed runoff rates. Inlets & Storm Sewer Using the Modified Rational Method, a contributing flow to each inlet in the system was determined. The inlet grates were designed to accommodate the 25-year storm event without overtopping a depth 0.15’ below the top of curb or spreading greater than 9 feet. Inlets at sag points were modeled using 50% clogging. Inlets and manholes will have a 9” sump for sediment collection. To avoid crossing Spring Ditch with the storm sewer, the two northern more inlets (SDI- 100 and SDI-101) were moved south from their original 2013 design location. This change created a larger drainage area that flows north to Existing Pond 7. The additional flowrate and volume was modeled to verify that Pond 7 could handle the added area without exceeding the pre-development flow rate. Storm pipes were sized to accommodate the 100-year storm event and were modeled in Storm and Sanitary Analysis. Pipes are sloped to maintain a minimum velocity of 3 ft/s when flowing full to prevent sediment deposit. The Hydraulic Grade line was plotted throughout the system and pipes were sized to keep the HGL within the pipe during the July, 2018 L:\172708\Engineering Reports\Storm Report\Stormwater Report.doc Page 2 25 yr storm and 100 yr storm. A manning’s N of 0.009 was used for the A-2000 Storm pipe within the model per the manufactures specifications. Stormwater Treatment The City of Bozeman requires infiltration, evapotranspiration or capture for reuse of the runoff generated from the first 0.5 inches of rainfall from a 24 hour storm. A common methodology for estimating the volume of direct runoff from a drainage basin is the SCS method. This method requires basic data similar to the Rational Method: drainage area, a runoff factor, time of concentration, and rainfall. However, the SCS approach is more sophisticated in that it also considers the time distribution of the rainfall and an infiltration rate that decreases during the course of a storm. The SCS method takes into account the Initial Abstraction (Ia) which is all losses before runoff begins. This includes surface depressions, water intercepted by vegetation, evapotranspiration and infiltration. Initial abstraction generally correlates with soil and cover parameters. Through studies of many small watersheds, Ia was found to be approximated by the following empirical equation: Ia = 0.2 x S [eq. 2-2 TR-55] Where S = (1000/CN) – 10 [eq. 2-4 TR-55] According to USDA’s Urban Hydrology for Small Watersheds, the Curve Number associated with soil type B and ¼ acre residential lots is 80 (Table 2-2a). Using the standard SCS method, S = (1000/80) – 10 = 2.5 inches Ia = 0.2 * 2.5 inches = 0.5 inches Using a 10-year 24-hour rain event in the City of Bozeman the total precipitation (P) is 1.88 inches of which 0.5 inches is lost due to initial abstraction according to USDA’s SCS method. Therefore this drainage plan includes provision for the first 0.5 inches of rainfall from the 24-hour storm to be retained in surface depressions, intercepted by vegetation, or evapotranspired or infiltrated Stormwater Detention Ponds Pond 5 and Pond 1A were designed in the original 2013 design report. Pond 1A will remain the same as originally designed but updated calculations are provided for clarity and it has been renamed Pond 1B. Pond 5 is similar to the original design but it has been oversized to account for future development along Vaquero Parkway. This Pond has been renamed Pond 5B and new calculations have been provided. The ponds are designed with outlet structures to limit stormwater runoff from the developed site to the pre-developed runoff rates for the 10-year storm and to not overtop during the 100-year storm. With this phase, additional drainage area will be added to the Existing Pond 7 basin. Pond 7 was originally slightly oversized allowing for this extra volume to be attenuated without exceeding the predeveloped rate. Revised pond calculations modeling the existing pond volume and existing outlet structure can be found in the appendices July, 2018 L:\172708\Engineering Reports\Storm Report\Stormwater Report.doc Page 3 Groundwater Groundwater is known to be high in this area. A geotechnical report was done in 2001 that included borings near both pond location. ST-29 near Pond 5B showed depth to groundwater at 3 feet below existing ground and ST-32 near Pond 1B showed depth to groundwater at 9 feet below existing ground. Due to the high groundwater the maximum pond excavation depth for Pond 5B is 2 feet. Culverts Both culverts under Vaquero Parkway were designed in the 2013 Design Report and modeled in the flood plain study conducted in 2007. Inverts and length changed slightly from the original design so new calculations are provided. Both culverts were modeled in HY-8 for the 25-year storm, 100-year storm, and emergency overflow events. According to the City of Bozeman standards the emergency overflow capacity shall be 100-percent of the whole culvert for the major storm. Both culverts meet this requirement by providing the entire emergency overflow capacity within the culvert and without overtopping the roadway. The headwater depth for the 25-year storm is provided in the culverts calculations and does not exceed 1.5 times the culvert depth. Maintenance Regular maintenance of stormwater facilities is necessary for proper function of the drainage system. In general, regular mowing of detention pond areas and removal of debris from the outlet structure will be required to maintain functionality of the system. Sediment removal from the ponds may be required over time to restore the detention pond volume. Additional maintenance items include removing debris from inlet grates and culverts, cleaning and flushing pipes, cleaning manhole sumps, and establishing ground cover after construction. All of the detention ponds will be maintained by the HOA (as is with the other existing ponds) after the phases have been incorporated into the HOA. Appendices L. Stormwater Drainage Basins M. Sub-Basin Runoff Calculations & Inlet Capacities N. Pipe Profiles with HGL O. Detention Pond Sizing and Outlet Structure Calculations P. Culvert Sizing