Sanderson Stewart is pleased to provide this scope of services for land agent services for street and
utility improvements for the Story Mill Road corridor from Bridger Drive to Griffin Drive. These
services are to be performed under the Professional Services Agreement for Streets and Land Agent
Services term contract (FY 2018 – FY 2020) for realty and engineering services. If this scope of
services is acceptable to you, please execute this agreement where noted.
Overview
We understand the City of Bozeman intends to construct street and utility improvements in the
Story Mill Road corridor in the near future. The future project improvements will provide improved
public transportation and utility facilities to cover current and future development growth in the
north-eastern part of Bozeman. To facilitate the improvements, additional permanent and temporary
right-of-way is required. Sanderson Stewart will provide professional right-of-way (R/W) acquisition
services to acquire new R/W for the project as shown on the attached Figure 1.
Scope of Work
Sanderson Stewart will provide the following services as part of its basic services:
1. Project Research
This task includes the preliminary R/W activities to obtain pertinent project information.
Subtasks under Item 1 include the following:
· Obtain and review available preliminary design plans and project documentation.
· Coordination meeting with the project team members
· Obtain current deeds and ownership information.
TG
DocuSign Envelope ID: 8BB4A58B-B12E-45D7-BC07-964028079780
Mr. Bob Murray
June 7, 2021
Page 2
_____
Initials
2. Initial Property Owner Contact
This task includes initiating coordination efforts with affected property owners. Subtasks
under Item 2 include the following:
· Compile contact information.
· Initiate contact with owners.
· Conduct pre-acquisition meetings with affected property owners.
3. R/W Mapping & Exhibits
This task consists of the preparation of R/W exhibits to acquire property interests. Subtasks
under Item 3 include the following:
· Sanderson Stewart is under contract to design the road project and will provide any
available proposed design and right-of-way plans/drawings for the project area.
· Permanent easements and temporary construction permits adjacent to Story Mill
Road will be acquired on two (2) parcels of land (Parcels 1 and 2).
· Temporary construction permits (only) will be acquired on three (3) parcels of land
(Parcels 3, 6, and 7).
· Prepare preliminary easement/permit exhibits for 5 parcels of land.
· QA/QC of exhibits
4. Title Commitments
This task consists of the preparation of title commitments for affected property interests.
Subtasks under Item 4 include the following:
· A title commitment will be secured for Parcel 2 requiring permanent easement
acquisition with compensation.
· Team coordination
5. Appraisals and Valuations
This task includes the preparation of valuation documents to value the property rights to be
acquired. Subtasks under Item 5 include the following:
· A waiver valuation will be completed for Parcel 2 by Sanderson Stewart for simple
acquisitions.
· For parcels with temporary construction permit acquisitions, the R/W agreements
will include lump sum compensation amounts for each permit as determined by the
City (Parcels 3, 6 and 7).
· Valuation documents will not be prepared for Parcel 1 as compensation amounts will
not be included in the R/W agreement. Parcel 1 is being redeveloped and will be
required to dedicate the necessary R/W as part of the City’s development process.
TG
DocuSign Envelope ID: 8BB4A58B-B12E-45D7-BC07-964028079780
Mr. Bob Murray
June 7, 2021
Page 3
_____
Initials
· A compensation package is not anticipated nor will be prepared for Parcel 8.
· Team coordination
· QA/QC of waiver valuations
6. Prepare Contracts
This task includes the preparation of the offer packages to acquire R/W, including
agreements, easements, temporary construction permits, exhibits, figures, and
correspondence letters. Subtasks under Item 6 include the following:
· Parcel 1 is being redeveloped and will be required to dedicate the necessary R/W as
part of the City’s development process. The R/W agreement will address the
required permanent easement and temporary construction permit for this project.
· Permanent easements and temporary construction permits adjacent to Story Mill
Road will be prepared for two (2) parcels of land (Parcels 1 and 2).
· Temporary construction permits (only) will be prepared for three (3) parcels of land
(Parcels 3, 6, and 7).
· Parcel 8 is a private business sign in public R/W (Lawson’s Greenhouse). Sanderson
Stewart will coordinate the removal or relocation of the sign, including preparation
of a R/W agreement or encroachment agreement, as necessary.
· Prepare acquisition documents including R/W agreements, maps and project
information.
· Prepare acquisition cost details and summary.
· Compile offer packages to acquire easements and/or permits for Parcels 1-3, 6 and
7, and prepare a R/W agreement for Parcel 8, as required.
· QA/QC of documents.
7. Acquisitions
This task includes conducting the acquisition meetings with affected property owners and
modifying the initial offer packages based on owner/client meetings. Subtasks under Item 7
include the following:
· Conduct acquisition meetings (minimum of 3 meetings per parcel).
· Conduct acquisition meetings with property owners of Parcels 1-3, and 6-8.
· Prepare final acquisition documents for all affected parcels.
· Prepare final acquisition costs for all affected parcels.
· QA/QC of documents.
TG
DocuSign Envelope ID: 8BB4A58B-B12E-45D7-BC07-964028079780
Mr. Bob Murray
June 7, 2021
Page 4
_____
Initials
8. R/W and Design Plan Updates
This task includes updating the right-of-way acquisition exhibits and documents based on
design changes, if required.
9. Relocation Services
This task is not included in this scope of services.
10. Title Clearing and Closing
This task includes coordinating and completing the title closing process with the title
company. Subtasks under Item 10 include the following:
· Prepare final title transfer documents and complete closing meetings for Parcel 2
(only) requiring permanent property acquisition with compensation.
· Obtain mortgage releases, clear taxes and liens, as required.
· Submittal of completed R/W acquisition offer packages to the City for review and
execution.
· Attend closing meetings.
· Team coordination.
11. Final Submittal and Closeout
This task includes the final project activities to finalize and submit executed acquisition
documents. Subtasks under Item 11 include the following:
· Prepare completed R/W acquisition project submittal packet.
· Deliver completed title transfer documents.
· Project closeout.
12. Contingency
The scope of services for this project includes all the necessary steps to acquire property
interests from private owners. A majority of the acquisition process relies on good
cooperation and timely responses from all parties involved in the process. Due to the
nature of coordination activities, the amount of time required to work with individual
property owners varies significantly. This task serves to capture the potential additional
costs incurred during the acquisition process due to challenging coordination activities with
property owners.
TG
DocuSign Envelope ID: 8BB4A58B-B12E-45D7-BC07-964028079780
Mr. Bob Murray
June 7, 2021
Page 5
_____
Initials
13. Project Administration
This task includes activities to manage the project requirements, deliverables, and tasks.
Subtasks under Item 13 include the following:
· Project status updates
· Budget and schedule monitoring and planning
· Invoicing and billing
The following items are not included in the scope of services or project budget for this project and
are therefore specifically excluded from this scope of services:
· Engineering or right-of-way design services
· Eminent domain proceedings, expert witness testimony, costs, or other services
necessary for legal proceedings
· Additional costs related to the actual purchase price of property interests as detailed
in R/W acquisition agreements
· Relocation costs paid to property owners as detailed in R/W acquisition agreements
If needed, these items will be added as a separate task order or contract amendment.
Services not set forth above as basic services are specifically excluded from the scope of Sanderson
Stewart’s services. Sanderson Stewart assumes no responsibility to perform any services not
specifically listed as basic services.
Additional services are not included in the basic services. If the Client and Sanderson Stewart agree
in writing via an amendment to this agreement, Sanderson Stewart will provide additional services as
requested by the Client.
Notwithstanding the foregoing, Sanderson Stewart shall have the right, but not the obligation, to
provide, without advance authorization from the Client, other services made necessary by the default
of the contractor or Client, or by deficiencies, delays, or defects in the work provided by the
contractor. Sanderson Stewart shall provide written notice of the provision of such services as soon
as reasonably possible.
Project Schedule
Once Sanderson Stewart receives Client’s authorization to proceed, Sanderson Stewart will
immediately proceed with fulfilling the project scope of services. The intent is to complete the R/W
acquisition activities in as short amount of time as necessary.
The Client and Sanderson Stewart are aware that many factors outside Sanderson Stewart’s control
may affect Sanderson Stewart’s ability to complete the services to be provided under this agreement.
Sanderson Stewart will perform these services with reasonable diligence and expediency consistent
with sound professional practices.
TG
DocuSign Envelope ID: 8BB4A58B-B12E-45D7-BC07-964028079780
Mr. Bob Murray
June 7, 2021
Page 6
_____
Initials
Fees and Billing Arrangements
Invoice and Billing: Sanderson Stewart will bill for its services on a time-and-materials basis with a
total cost not to exceed $20,726.00. Sanderson Stewart will begin work once this agreement has been
executed by both parties.
Right-of-Way Acquisition
1. Project Research $664.00
2. Initial Property Owner Contact $290.00
3. R/W Mapping & Exhibits $2,900.00
4. Title Commitments $445.00
5. Appraisals and Valuations $1,160.00
6. Prepare Contracts $3,020.00
7. Acquisitions $9,032.00
8. R/W and Design Plan Updates $580.00
9. Relocation Services $0.00
10. Title Clearing and Closing $435.00
11. Final Submittal and Closeout $580.00
12. Contingency $1,160.00
13. Project Administration $460.00
Total $20,726.00
Sanderson Stewart shall submit invoices to the Client for work accomplished during each calendar
month. Monthly invoices shall include, separately listed, any charges for services for which time
charges and/or unit costs shall apply. Such invoices shall also include, separately listed, any charges
for consultants retained by Sanderson Stewart, and reimbursable costs. Such invoices shall be
submitted by Sanderson Stewart as soon as possible after the end of the month in which the work
was accomplished and shall be due and payable by the Client upon receipt. The Client agrees that
the monthly invoice from Sanderson Stewart is correct, conclusive, and binding on the Client unless
the Client, within 20 working days from the date of receipt of such invoice, notifies Sanderson
Stewart in writing of alleged inaccuracies, discrepancies, errors in the invoice, or the need for
additional backup.
Conclusion
Mr. Murray, we look forward to working with you on this very exciting project. Feel free to call me
at 406/922-4304 if you have any questions regarding this proposal. Otherwise, if it meets your
TG
DocuSign Envelope ID: 8BB4A58B-B12E-45D7-BC07-964028079780
Mr. Bob Murray
June 7, 2021
Page 7
_____
Initials
approval, simply mail or email this signed and dated agreement to our office at 106 East Babcock,
Suite L1, Bozeman, MT 59715 or tgaddo@sandersonstewart.com. Thank you.
Sincerely,
Tony Gaddo, P.E., REALTOR®
Senior Engineer /
Right-of-Way Specialist
TG/JS
Enc.
**** END OF SCOPE OF SERVICES EXCEPT FOR SIGNATURES ****
TG
DocuSign Envelope ID: 8BB4A58B-B12E-45D7-BC07-964028079780
Mr. Bob Murray
June 7, 2021
Page 8
_____
Initials
This Task Order is dated ________________, 20___ between City of Bozeman, Montana (City)
and Sanderson Stewart (Contractor).
IN WITNESS WHEREOF, the parties hereto have executed this instrument the day and
year first above written.
CITY OF BOZEMAN, MONTANA SANDERSON STEWART
By: By:
Print Name: Print Name:
Print Title: Print Title:
Date: Date:
TG
Tony Gaddo
Project Manager
6/7/2021
June 22 21
DocuSign Envelope ID: 8BB4A58B-B12E-45D7-BC07-964028079780
City Manager
6/23/2021
Jeff Mihelich
FIGURE 1NORTH050SCALE:1" = 100'10050PARCEL 1PARCEL 2PARCEL 3PARCEL 4PARCEL 5PARCEL 6PARCEL 7PARCEL 8DocuSign Envelope ID: 8BB4A58B-B12E-45D7-BC07-964028079780