Loading...
HomeMy WebLinkAbout21- Task Order 18 - Sanderson Stewart - ROW Aquisition Story Mill Rd _____ Initials June 7, 2021 Mr. Bob Murray, PE City of Bozeman 20 East Olive St. Bozeman, MT 59715 Reference: City of Bozeman Land Agent Services Project Scope of Services – Task Order No. #18 Story Mill Road R/W Acquisition Dear Mr. Murray: Sanderson Stewart is pleased to provide this scope of services for land agent services for street and utility improvements for the Story Mill Road corridor from Bridger Drive to Griffin Drive. These services are to be performed under the Professional Services Agreement for Streets and Land Agent Services term contract (FY 2018 – FY 2020) for realty and engineering services. If this scope of services is acceptable to you, please execute this agreement where noted. Overview We understand the City of Bozeman intends to construct street and utility improvements in the Story Mill Road corridor in the near future. The future project improvements will provide improved public transportation and utility facilities to cover current and future development growth in the north-eastern part of Bozeman. To facilitate the improvements, additional permanent and temporary right-of-way is required. Sanderson Stewart will provide professional right-of-way (R/W) acquisition services to acquire new R/W for the project as shown on the attached Figure 1. Scope of Work Sanderson Stewart will provide the following services as part of its basic services: 1. Project Research This task includes the preliminary R/W activities to obtain pertinent project information. Subtasks under Item 1 include the following: · Obtain and review available preliminary design plans and project documentation. · Coordination meeting with the project team members · Obtain current deeds and ownership information. TG DocuSign Envelope ID: 8BB4A58B-B12E-45D7-BC07-964028079780 Mr. Bob Murray June 7, 2021 Page 2 _____ Initials 2. Initial Property Owner Contact This task includes initiating coordination efforts with affected property owners. Subtasks under Item 2 include the following: · Compile contact information. · Initiate contact with owners. · Conduct pre-acquisition meetings with affected property owners. 3. R/W Mapping & Exhibits This task consists of the preparation of R/W exhibits to acquire property interests. Subtasks under Item 3 include the following: · Sanderson Stewart is under contract to design the road project and will provide any available proposed design and right-of-way plans/drawings for the project area. · Permanent easements and temporary construction permits adjacent to Story Mill Road will be acquired on two (2) parcels of land (Parcels 1 and 2). · Temporary construction permits (only) will be acquired on three (3) parcels of land (Parcels 3, 6, and 7). · Prepare preliminary easement/permit exhibits for 5 parcels of land. · QA/QC of exhibits 4. Title Commitments This task consists of the preparation of title commitments for affected property interests. Subtasks under Item 4 include the following: · A title commitment will be secured for Parcel 2 requiring permanent easement acquisition with compensation. · Team coordination 5. Appraisals and Valuations This task includes the preparation of valuation documents to value the property rights to be acquired. Subtasks under Item 5 include the following: · A waiver valuation will be completed for Parcel 2 by Sanderson Stewart for simple acquisitions. · For parcels with temporary construction permit acquisitions, the R/W agreements will include lump sum compensation amounts for each permit as determined by the City (Parcels 3, 6 and 7). · Valuation documents will not be prepared for Parcel 1 as compensation amounts will not be included in the R/W agreement. Parcel 1 is being redeveloped and will be required to dedicate the necessary R/W as part of the City’s development process. TG DocuSign Envelope ID: 8BB4A58B-B12E-45D7-BC07-964028079780 Mr. Bob Murray June 7, 2021 Page 3 _____ Initials · A compensation package is not anticipated nor will be prepared for Parcel 8. · Team coordination · QA/QC of waiver valuations 6. Prepare Contracts This task includes the preparation of the offer packages to acquire R/W, including agreements, easements, temporary construction permits, exhibits, figures, and correspondence letters. Subtasks under Item 6 include the following: · Parcel 1 is being redeveloped and will be required to dedicate the necessary R/W as part of the City’s development process. The R/W agreement will address the required permanent easement and temporary construction permit for this project. · Permanent easements and temporary construction permits adjacent to Story Mill Road will be prepared for two (2) parcels of land (Parcels 1 and 2). · Temporary construction permits (only) will be prepared for three (3) parcels of land (Parcels 3, 6, and 7). · Parcel 8 is a private business sign in public R/W (Lawson’s Greenhouse). Sanderson Stewart will coordinate the removal or relocation of the sign, including preparation of a R/W agreement or encroachment agreement, as necessary. · Prepare acquisition documents including R/W agreements, maps and project information. · Prepare acquisition cost details and summary. · Compile offer packages to acquire easements and/or permits for Parcels 1-3, 6 and 7, and prepare a R/W agreement for Parcel 8, as required. · QA/QC of documents. 7. Acquisitions This task includes conducting the acquisition meetings with affected property owners and modifying the initial offer packages based on owner/client meetings. Subtasks under Item 7 include the following: · Conduct acquisition meetings (minimum of 3 meetings per parcel). · Conduct acquisition meetings with property owners of Parcels 1-3, and 6-8. · Prepare final acquisition documents for all affected parcels. · Prepare final acquisition costs for all affected parcels. · QA/QC of documents. TG DocuSign Envelope ID: 8BB4A58B-B12E-45D7-BC07-964028079780 Mr. Bob Murray June 7, 2021 Page 4 _____ Initials 8. R/W and Design Plan Updates This task includes updating the right-of-way acquisition exhibits and documents based on design changes, if required. 9. Relocation Services This task is not included in this scope of services. 10. Title Clearing and Closing This task includes coordinating and completing the title closing process with the title company. Subtasks under Item 10 include the following: · Prepare final title transfer documents and complete closing meetings for Parcel 2 (only) requiring permanent property acquisition with compensation. · Obtain mortgage releases, clear taxes and liens, as required. · Submittal of completed R/W acquisition offer packages to the City for review and execution. · Attend closing meetings. · Team coordination. 11. Final Submittal and Closeout This task includes the final project activities to finalize and submit executed acquisition documents. Subtasks under Item 11 include the following: · Prepare completed R/W acquisition project submittal packet. · Deliver completed title transfer documents. · Project closeout. 12. Contingency The scope of services for this project includes all the necessary steps to acquire property interests from private owners. A majority of the acquisition process relies on good cooperation and timely responses from all parties involved in the process. Due to the nature of coordination activities, the amount of time required to work with individual property owners varies significantly. This task serves to capture the potential additional costs incurred during the acquisition process due to challenging coordination activities with property owners. TG DocuSign Envelope ID: 8BB4A58B-B12E-45D7-BC07-964028079780 Mr. Bob Murray June 7, 2021 Page 5 _____ Initials 13. Project Administration This task includes activities to manage the project requirements, deliverables, and tasks. Subtasks under Item 13 include the following: · Project status updates · Budget and schedule monitoring and planning · Invoicing and billing The following items are not included in the scope of services or project budget for this project and are therefore specifically excluded from this scope of services: · Engineering or right-of-way design services · Eminent domain proceedings, expert witness testimony, costs, or other services necessary for legal proceedings · Additional costs related to the actual purchase price of property interests as detailed in R/W acquisition agreements · Relocation costs paid to property owners as detailed in R/W acquisition agreements If needed, these items will be added as a separate task order or contract amendment. Services not set forth above as basic services are specifically excluded from the scope of Sanderson Stewart’s services. Sanderson Stewart assumes no responsibility to perform any services not specifically listed as basic services. Additional services are not included in the basic services. If the Client and Sanderson Stewart agree in writing via an amendment to this agreement, Sanderson Stewart will provide additional services as requested by the Client. Notwithstanding the foregoing, Sanderson Stewart shall have the right, but not the obligation, to provide, without advance authorization from the Client, other services made necessary by the default of the contractor or Client, or by deficiencies, delays, or defects in the work provided by the contractor. Sanderson Stewart shall provide written notice of the provision of such services as soon as reasonably possible. Project Schedule Once Sanderson Stewart receives Client’s authorization to proceed, Sanderson Stewart will immediately proceed with fulfilling the project scope of services. The intent is to complete the R/W acquisition activities in as short amount of time as necessary. The Client and Sanderson Stewart are aware that many factors outside Sanderson Stewart’s control may affect Sanderson Stewart’s ability to complete the services to be provided under this agreement. Sanderson Stewart will perform these services with reasonable diligence and expediency consistent with sound professional practices. TG DocuSign Envelope ID: 8BB4A58B-B12E-45D7-BC07-964028079780 Mr. Bob Murray June 7, 2021 Page 6 _____ Initials Fees and Billing Arrangements Invoice and Billing: Sanderson Stewart will bill for its services on a time-and-materials basis with a total cost not to exceed $20,726.00. Sanderson Stewart will begin work once this agreement has been executed by both parties. Right-of-Way Acquisition 1. Project Research $664.00 2. Initial Property Owner Contact $290.00 3. R/W Mapping & Exhibits $2,900.00 4. Title Commitments $445.00 5. Appraisals and Valuations $1,160.00 6. Prepare Contracts $3,020.00 7. Acquisitions $9,032.00 8. R/W and Design Plan Updates $580.00 9. Relocation Services $0.00 10. Title Clearing and Closing $435.00 11. Final Submittal and Closeout $580.00 12. Contingency $1,160.00 13. Project Administration $460.00 Total $20,726.00 Sanderson Stewart shall submit invoices to the Client for work accomplished during each calendar month. Monthly invoices shall include, separately listed, any charges for services for which time charges and/or unit costs shall apply. Such invoices shall also include, separately listed, any charges for consultants retained by Sanderson Stewart, and reimbursable costs. Such invoices shall be submitted by Sanderson Stewart as soon as possible after the end of the month in which the work was accomplished and shall be due and payable by the Client upon receipt. The Client agrees that the monthly invoice from Sanderson Stewart is correct, conclusive, and binding on the Client unless the Client, within 20 working days from the date of receipt of such invoice, notifies Sanderson Stewart in writing of alleged inaccuracies, discrepancies, errors in the invoice, or the need for additional backup. Conclusion Mr. Murray, we look forward to working with you on this very exciting project. Feel free to call me at 406/922-4304 if you have any questions regarding this proposal. Otherwise, if it meets your TG DocuSign Envelope ID: 8BB4A58B-B12E-45D7-BC07-964028079780 Mr. Bob Murray June 7, 2021 Page 7 _____ Initials approval, simply mail or email this signed and dated agreement to our office at 106 East Babcock, Suite L1, Bozeman, MT 59715 or tgaddo@sandersonstewart.com. Thank you. Sincerely, Tony Gaddo, P.E., REALTOR® Senior Engineer / Right-of-Way Specialist TG/JS Enc. **** END OF SCOPE OF SERVICES EXCEPT FOR SIGNATURES **** TG DocuSign Envelope ID: 8BB4A58B-B12E-45D7-BC07-964028079780 Mr. Bob Murray June 7, 2021 Page 8 _____ Initials This Task Order is dated ________________, 20___ between City of Bozeman, Montana (City) and Sanderson Stewart (Contractor). IN WITNESS WHEREOF, the parties hereto have executed this instrument the day and year first above written. CITY OF BOZEMAN, MONTANA SANDERSON STEWART By: By: Print Name: Print Name: Print Title: Print Title: Date: Date: TG Tony Gaddo Project Manager 6/7/2021 June 22 21 DocuSign Envelope ID: 8BB4A58B-B12E-45D7-BC07-964028079780 City Manager 6/23/2021 Jeff Mihelich FIGURE 1NORTH050SCALE:1" = 100'10050PARCEL 1PARCEL 2PARCEL 3PARCEL 4PARCEL 5PARCEL 6PARCEL 7PARCEL 8DocuSign Envelope ID: 8BB4A58B-B12E-45D7-BC07-964028079780