DESIGN REPORT
FOR
YELLOWSTONE PEAKS MOBILE HOME PARK
Prepared for:
DENNIS BALIAN
Prepared by:
C &H ENGINEERING AND SURVEYING, INC.
614 WEST LANIlVIE STREET
BOZEMAN, MT 59715
(406) 587-1115
96270
FEBRUARY, 1997
INTRODUCTION
The proposed Yellowstone Peaks Mobile Home Park is located on West Babcock Street
approximately 1,800 feet west of the intersection of West Babcock and Main Street, in
Bozeman,Montana. Currently,there is one single family dwelling with an attached garage on
the site, served by private a well and septic system. The tract is part of the Fowler Subdivision
and is 1,333.2 feet long in the north-south direction and varies in width from 197.6 to 218.6 feet
in the east-west direction. It is the owner's desire to develop the tract into 36 "lots" under the
City of Bozeman's R-MH zoning designation. This would include tying into City of Bozeman
water and sewer utilities, paving West Mendenhall where it crosses the site and constructing a
private road(Sunlight Avenue)up the middle of the tract. Sunlight Avenue will be constructed
with curb and gutter to a width of 23 feet from back of curb to back of curb. West Mendenhall
will be constructed to City of Bozeman standards, 37 feet from back of curb to back of curb.
This preliminary plat application is made as a replacement for the previously approved 44 unit
Yellowstone Peaks Townhouses. A Traffic study was submitted as part of that application, and
the remainder of the environmental assessment and community impact report was waived due to
the inclusion of that information in the master plan for the area.
WATER SYSTEM
Summary
Current water mains and stubs in the area include a 10 inch D.I.P. that runs east-west on the
south side of West Babcock, a 6 inch stub to the west of the proposed development in West
Mendenhall Street (in the Westgate Subdivision), and a 6 inch stub to the northwest of the
proposed development from the Greenway Subdivision. At the time of this writing, plans have
been submitted for the construction of the Wheeler Mobile Home Park immediately to the west
of the proposed subdivision. Approximately 1,400 feet of 6 inch D.I.P. will be run northerly
from the 10 inch main on the south to the stub at the Wheeler Mobile Home Park on the north.
A 6 inch diameter water main will be run in the proposed West Mendenhall Street from the stub
in the proposed Wheeler Mobile Home Park to the west, to the east boundary line where it will
be stubbed and capped. By connecting to the stub in the Wheeler Mobile Home Park,two loops
will be created.
Individual water services to each unit will connect to 1.5 inch diameter service headers with
meter pits, which in turn are connected to the new 6 inch line. The existing house will connect
directly to the 6 inch line, via a 3/4" service line.
Design Requirements
Daily Domestic Usage=350 gpd per unit
Total Units=35
2
Daily Domestic Usage For All Units=(350 x 35) 12,250 gpd
Peaking Factor= 3
Peaked Daily Domestic Usage For All Units=36,750 gpd=25.52 gpm
Irrigation Flow=(1 inch/week) x(1/12 ft/inch) x(43560 ft2/acre)x(4 acres)x (1/7 weeks/day) x
(7.48 gal/ft )= 15,516 gpd= 10.80 gpm
Fire Flow= 1000 gpm
Total Flow=25.52 gpm + 10.80 gpm + 1000 gpm= 1036.32 gpm
Available Pressure= 125 psi
Residual Pressure Required=20 psi
Available Pressure For Head Loss =(125-20) 105 psi
Available Head=(105 x 2.31)=242.55 ft
Head Loss= 9 ft(Hazen-Williams, C=120)
Head Remaining=(242.55 -9)=233.55 ft
A conservative value of C= 120 was used in the Hazen-Williams equation for the ductile iron
pipe. No minor losses were introduced into the analysis as the C-factor is considered
conservative. Using a iterative nodal analysis, a head loss of 9 feet can be expected. Since this
is less than the available head loss,the proposed system is satisfactory.
WATER DISTRIBUTION SYSTEM SIZING
Meters and Service Lines are sized based on the Fixture Unit method found in the Uniform
Plumbing Code. (U.P.C.)
Fixture Units:
Kitchen sink =2
Bathtub/shower =2
Sink = 1
Toilet =3
Laundry =2
Half Bath or D/W =2
= 12
Lots 2-11
12 F.U. /unit x 10 units = 120 Total F.U.'s
From Chart A-3 (U.P.C.), 120 F.U. =48 gpm
3
From Chart A-4 (U.P.C.), 48 gpm = 1.5" pipe @ 9 ft/s @ 8 psi of head loss per 100 ft of pipe .
400'/ 100' x 8 psi = 32 psi. Head loss OK, use 1.5" service line.
Lots 12-22
12 F.U. /unit x 12 units = 144 Total F.U.'s
From Chart A-3 (U.P.C.) 144 F.U. = 54 gpm
From Chart A-4 (U.P.C.) 54 gpm = 1.5" pipe @ 10 ft/s @ 10 psi of head loss per 100 ft of pipe
400'/ 100' x 10 psi =40 psi. Head loss OK, use 1.5" service line.
Lots 23-35
12 F.U. /unit x 13 units = 156 Total F.U.'s
From Chart A-3 (U.P.C.) 156 F.U. = 56 gpm
From Chart A-4 (U.P.C.) 56 gpm= 1.5" pipe @ 10 ft/s @ 10 psi of head loss per 100 ft of pipe
400'/ 100' x 10 psi =40 psi. Head loss OK, use 1.5" service line.
SEWER SYSTEM
Summary
Sewer lines will run adjacent to the proposed water lines in Sunlight Avenue. The proposed
sewer line will connect to the City system in only one location. A stub has been provided in the
park area of the Wheeler Mobile Home Park at the north end of the proposed subdivision. A
total of four new manholes will be constructed.
Design Requirements
Waste water flows were estimated in the following manner:
Daily Flow=350 gpd per unit
Total Units=35
Total Flow= (35 x 350)= 12,250 gpd= 8.51 gpm
Peak Factor= (18+P")/(4+P"2) where P=population in thousands(35 units x 3 persons per
unit= 105) = 4.2
Peak Total Flow=(4.2 x 8.51)35.74 gpm
Waste water mains were sized in the following manner:
4
Manning's N=0.013
Minimum Slope=0.011 ft/ft
Q=35.74 gpm=0.0796 cfs
Percent Full (8" PVC)= 17.33
Velocity=2.02 fps
Based on the previous calculations an 8" PVC sewer line at the grade shown will be more than
adequate to carry the design flows.
STORM WATER MANAGEMENT
Summary
Storm water run-off from the site will be directed by curb and gutter to a storm water retention
pond located in the park area of the proposed subdivision. This retention area will filter
sediment and oils from the storm runoff. The retention basin was sized for a 10 year/2 hour
storm event.
STORM WATER RUNOFF (PRE DEVELOPMENT)
AREAS
Pavement = 4578 ft2
Roofs = 1692 f12
Open land = 261,543 ft2
TOTAL = 267,813 ft2
Using Q=CiA where:
Q=Flow(ft3/hr)
C =Runoff coefficient
=0.20 (open land)
=0.60 (gravel road)
=0.85 (paved road)
=0.90 (roofs)
i =Rain fall intensity per NOAA ATLAS
=0.034 ft/hr
5
A=Area(ft2)
We Have:
Pavement (0.85)(0.034 fFt/hr)(4,578 ft2) = 132.3 ft3/hr
Roofs (0.90)(0.034 ft/hr)(1,692 ft2) = 51.8 ft3/hr
Open Land (0.20)(0.034 ft/hr)(261,543 ft2) = 1,778.5 ft3/hr
TOTAL = 1,962.6 ft3/hr
244.7 gpm
For a 2 hour event = 5,347.1 ft3
STORM WATER RUNOFF (POST DEVELOPMENT)
AREAS
Paved = 73,738 ft2 (sidewalks, driveways, road)
Roofs 34x 12'x 50' = 14,400 ft
Open land = 173,675 ft2
I
TOTAL = 267,813 ft2
Using Q=CIA where:
Q=Flow(ft3/hr)
C=Runoff coefficient
=0.20 (open land)
=0.60(gravel road)
=0.85 (paved road)
=090 (roofs)
i =Rain fall intensity per NOAA ATLAS
=0.034 ft/hr
A=Area(ft2)
We have:
Paved (0.85)(0.034 ft/hr)(73,738 ft2) =2,131 ft3/hr
6
ii
f
Roofs (0.90)(0.034 ft/hr)(20,400 ft2) =624 ft3/hr
Open land (0.20)(0.034 ft/hr)(173,675 ft2) = 1,181 ft3/hr
TOTAL =3,936 ft3/hr
For a 2 hour event 7,872 ft3
Post Development Volume to Retain 7,872 ft3
STREETS, CURB AND GUTTER, SIDEWALKS
Summary
Access to the site will be provided form three points, West Mendenhall Street through the
Wheeler Mobile Home Park,the Farwestern Subdivision, and West Babcock Street. West
Mendenhall will be improved to City of Bozeman standards. Sunlight Avenue is a private road
and will be constructed to a width of 23 feet measured from the back of curb to back of curb.
Curb and gutter will be constructed to City of Bozeman standards. A 4 foot wide sidewalk on
the west side of Sunlight Avenue will extend from West Babcock to the park area on the north
end of the site.
Street Design Requirements
Both West Mendenhall and Sunlight Avenue will use the same section varying only with regard
to width and sidewalk location. The surface will consist of 3 inches of asphaltic concrete over a
3 inch base of 1 inch minus crushed gravel over 9 inches of 4 inch minus select pit run. This is
based on the inspection of the soils on site and sites in the immediate vicinity of the proposed
construction, in addition to the previous performance of this section in similar applications. As
is normally done, the topsoil will be removed, and the sub-grade material will be inspected for
suitability, and compacted to 95% of maximum before placement of sub-base and base course
material. Any soft clay or organic material encountered will be removed and replaced.
7