This section is a response to the requirements of the City of Bozeman Unified Development
Ordinance Section 38.220.060 relative to Water and Sewer. The original Sanitary Sewer Design
Report provides analysis for the entire PUD including Phase 4. Flows from Phase 4 are designed
to flow west to the existing sewer main in Fowler Avenue (see updated sewer main exhibit).
Since the report was written, the City of Bozeman Design Standards and Specifications have
been revised to reflect a lower required flow rate for B-2 zoning, decreasing from 3495
gal/ac/day to 2000 gal/ac/day. Previous calculations combined with the reduction in B-2 flow
rates indicate that the existing system will meet the required sewer design criteria for Phase 4 of
the Bozeman Gateway.