HomeMy WebLinkAboutHeli Contract Notice - Phase 2NOTICE OF HELICOPTER TIMBER CONTRACT
Phase 2 Sourdough Fuels Reduction Project
CITY OF BOZEMAN
Phase 2 of the Sourdough Fuels Reduction Project is located within E1/2 SE1/4 Section 7, W1/2 Section
17, and E1/2 Section 18 T3S R6E on City of Bozeman property. Approximately 5,449 tons of Douglas‐fir
sawlogs and 956 tons of Lodgepole Pine sawlogs are Contracted for helicopter removal along with
approximately 472 tons of merchantable non‐sawlog Other Material. The Other Material largely consists
of downed or standing dead Lodgepole Pine of merchantable quality.
Sealed bids will be received by City of Bozeman until June 9, 2021 at 2 p.m. at which time they will be
publicly opened and read aloud. Bids may be hand delivered or shipped to the address provided below
and will be accepted any time prior to the bid opening. Bids must be accompanied by a bid security of $2,000
made payable to City of Bozeman in cashier’s check, certified check, bank money order or bank draft.
Hand deliver or ship bids to: Mail bids to:
City Clerk City of Bozeman
City Hall, Suite 201 City Clerk
121 N Rouse Ave P.O. Box 1230
Bozeman, MT 59715 Bozeman, MT 59771‐1230
The Contract will be awarded to the lowest responsible bidder. If the successful bidder is unable to
execute the helicopter timber Contract within 30 calendar days from the date the Contract is awarded,
the bid deposit will be retained by the City of Bozeman as liquidated damages and the Contract will be
offered to the next lowest bidder. The right is reserved to reject any or all bids. Bid security will be
returned to unsuccessful bidders upon execution of a helicopter timber Contract with the successful
bidder.
The timber Contracted for removal has been laid out and will be administered by Gary Peck of Peck
Forestry, Inc. working on behalf of the City of Bozeman as its contracted Forest Officer. Any questions
concerning the timber Contract shall be directed to Mr. Peck at 406‐581‐2815, or peckgs@gmail.com.
Prospective bidders are encouraged, but not required, to tour the Contract area with Mr. Peck.
Prospective bidders can obtain the timber prospectus, Helicopter Timber Contract and bid forms from the
City of Bozeman by calling 406‐582‐2282, or email to bheaston@bozeman.net. These documents are also
available for download at the following webpage
https://weblink.bozeman.net/WebLink/Browse.aspx?id=237014&dbid=0&repo=BOZEMAN
CONTRACTOR and any of the CONTRACTOR’S subcontractors bidding or doing work on this project will be
required to be registered with the Montana Department of Labor and Industry (DLI). Forms for registration
are available from the DLI, PO Box 8011, 1805 Prospect, Helena, Montana 59604‐8011. Information on
registration can be obtained by calling (406) 444‐7734. CONTRACTOR is not required to have registered
with the DLI prior to bidding on this project, but must have registered prior to execution of the Helicopter
Timber Contract.
Discrimination in the performance of any agreement awarded under this project on the basis of race,
color, religion, creed, sex, age, marital status, national origin, or actual or perceived sexual orientation,
gender identity or disability is prohibited. This prohibition shall apply to the hiring and treatment of the
awarded entity’s employees and to all subcontracts.
As such, each entity submitting under this notice shall include a provision wherein the submitting entity,
or entities, affirms in writing it will not discriminate on the basis of race, color, religion, creed, sex, age,
marital status, national origin, or because of actual or perceived sexual orientation, gender identity or
disability and which also recognizes the eventual contract will contain a provision prohibiting
discrimination as described above and that this prohibition on discrimination shall apply to the hiring and
treatment of the submitting entity’s employees and to all subcontracts.
In addition, pursuant to City Commission Resolution 5169, the entity awarded a contract under this project
and any subcontractors must abide by the Equal Pay Act of 1963 and Section 39‐3‐104, MCA (the Montana
Equal Pay Act), and affirm it will abide by the above and that it has visited the State of Montana Equal Pay
for Equal Work “best practices” website, https://equalpay.mt.gov/BestPractices/Employers, or equivalent
“best practices publication and has read the material.
Published in Bozeman Daily Chronicle
May 16, 2021
May 30, 2021
TIMBER PROSPECTUS
CITY OF BOZEMAN
Contract Name: Phase 2 Sourdough Fuels Reduction Project
For specific Contract information, contact: Gary Peck
Phone : 406-581-2815 email: peckgs@gmail.com
For copies of the Helicopter Timber Contract and bid forms, contact:
Phone: 406-582-2282 email: bheaston@bozeman.net
City of Bozeman – Engineering Division
General Bidding Information
1. Bids must be submitted on City of Bozeman (City) bid forms.
2. The Helicopter Timber Contract will be awarded to the lowest responsible bidder; however,
the City reserves the right to reject any or all bids.
3. The City recommends that bidders contact the City Clerk at 406‐582‐2321 or
mmaas@bozeman.net prior to the bid opening to ensure that its bid has been received.
4. A Bid Security of $2,000 must accompany all bids and must be in the form of cash, cashier’s
check, certified check, money order, or bank draft payable to City of Bozeman.
5. The Contractor must submit a Performance Bond to the City within 30 days of notification of
Contract award. The bond amount will be at 100% of the total bid price of the Contract. The
performance bond may be cash, irrevocable letter of credit, surety bond or certificate of
deposit. See the Helicopter Timber Contract for additional information.
6. This timber Contract is based on the gross weight of all species. Bid price is on a per ton basis.
Unless otherwise specified, the price applies to all species, green and dead. Price may vary by
product. Payment will be based on gross weight. A weight ticket is required for each load
hauled, regardless of product type.
7. The Contractor is hereby notified that it must secure separate Purchase Agreements with mills
and/or other purchasers of timber products removed under this timber Contract. The
Contract shall select the final destination of timber products at its own discretion. Weight
tickets shall be provided to the Forest Officer and City prior to issuance of payment by the City
to the Contractor under this timber Contract.
8. The Forest Officer has estimated the net scale merchantable sawlog volume to be removed
under this Contract. Other products may be part of this Contract. All delivered wood will be
weighed and provided payment at per ton bid rates. The City recognizes that a percentage of
delivered wood may not meet the log manufacturing and recovery standards of the Helicopter
Timber Contract. The actual percentage will vary based on the log manufacturing and
recovery specifications of the Contractor and tree conditions in the Contract area. The actual
delivered weight may vary, resulting in an overrun or under‐run of the estimated tonnage.
The City strongly recommends that bidders evaluate these effects before bidding.
9. The City does not conduct detailed road appraisals. All appraised costs are gross estimates or
averages, provided only to show the relative amount of work required, and not the true
market value. The City strongly recommends that bidders make their own estimates based on
Contract requirements. Cost estimates provided are not guaranteed.
10. Bidders are encouraged to examine the complete Helicopter Timber Contract package and
Contract Area prior to bidding. Additional information regarding the Contract is available at the
phone numbers shown above.
11. Estimates for removal volume, species percents, defect, product class, etc. provided in this
prospectus and volume estimates listed in the Helicopter Timber Contract are not guaranteed.
12. This prospectus is provided for information purposes only. If the prospectus is in error or
contradicts the Helicopter Timber Contract, the Contract governs.
Additional Contract Information
1. SLASHING OF LOGGING‐DAMAGED TREES REQUIRED: The Contractor shall fell all
submerchantable trees with logging‐related root or stem damage, causing lean. The stem shall
be completely severed from the stump below the lowest live limb. Maximum stump height
shall be 12 inches on the uphill side.
2. Contact Gary Peck, Forest Officer, to arrange access to Contract area through the Liebmann
Existing Road (406‐581‐2815).
Helicopter Timber Contract Information Sheet City of Bozeman Phase 1 Sourdough Fuels Reduction ProjectTimber Cruise Data SPECIES PP DF WL LP ES WF CE WP Dead LP TOTAL or AVE Minimum Bid per ton Pounds per Board Feet 12.4 12.4 Estimated tons of sawlogs (5.6" top DIB) 5,449 690 266 6,405 tons Estimated tons of other material (pulp, etc) 472 472 tons Gross MBF (Scribner 5.6” top DIB) 967 122 51 1,140 MBF % Cull and Breakage 10 10 18 11% Net MBF (Scribner 5.6” top DIB) 879 111 43 1,033 MBF Average logs per MBF 11 11 logs/MBF Average DBH 14 14 in. Average tons per acre 87 tons/ac Average MBF per acre 14 MBF/ac Tons Per Thousand Board Feet 6,405 estimated tons to a 5.6 inch top / 1,033 Net MBF Scribner to a 5.6 inch top DIB 6.20 tons/MBF Contract Information Contract Termination Date: January 15, 2022 Operating Period: Not later than October 1 through December 15, 2021
Helicopter Timber Contract Information Sheet City of Bozeman Logging Information % of volume logged by clearcut or seed tree cut 100% % of volume logged with tractors 0% % of volume logged by skyline 0% % of volume logged by Helicopter 100% Yarding distance tractor (average) N/A Yarding distance skyline (average) N/A Yarding distance Helicopter 3,300 ft or less Estimated haul distance (paved) 40.0 miles Estimated haul distance (unpaved) 1.0 – 3.0 miles Unit Harvest Volume Unit Nos. Acres Est. Tons Est MBF Harvest Deadline East Side Units 1 – 15 54 4,582 739 October 31, 2021 West Side Units 16 - 25 25 2,295 370 December 15, 2021 79 6,877 1,109 Road development and maintenance fees and estimates Estimated road development cost total $0 Estimated road development cost per ton $0ton Estimated road development cost perMBF $0/MBF Estimated Contractor-do road maintenance cost total $2,750 Estimated Contractor-do road maintenance cost per ton $0.40/ton Private road maintenance charges per ton $0.00/ton USFS road maintenance charges per ton $0.00/ton Miles of road construction 0.0 miles Miles of road reconstruction 0.0 miles Miles of road with site improvements 0.0 miles Miles of road reclamation or abandonment 0.0 miles Miles of road maintenance and blading 4.0 miles
TIMBER PROSPECTUS
CITY OF BOZEMAN
Contract Name: Phase 2 Sourdough Fuels Reduction Project
For specific Contract information, contact: Gary Peck
Phone : 406-581-2815 email: peckgs@gmail.com
For copies of the Helicopter Timber Contract and bid forms, contact:
Phone: 406-582-2282 email: bheaston@bozeman.net
City of Bozeman – Engineering Division
General Bidding Information
1. Bids must be submitted on City of Bozeman (City) bid forms.
2. The Helicopter Timber Contract will be awarded to the lowest responsible bidder; however,
the City reserves the right to reject any or all bids.
3. The City recommends that bidders contact the City Clerk at 406‐582‐2321 or
mmaas@bozeman.net prior to the bid opening to ensure that its bid has been received.
4. A Bid Security of $2,000 must accompany all bids and must be in the form of cash, cashier’s
check, certified check, money order, or bank draft payable to City of Bozeman.
5. The Contractor must submit a Performance Bond to the City within 30 days of notification of
Contract award. The bond amount will be at 100% of the total bid price of the Contract. The
performance bond may be cash, irrevocable letter of credit, surety bond or certificate of
deposit. See the Helicopter Timber Contract for additional information.
6. This timber Contract is based on the gross weight of all species. Bid price is on a per ton basis.
Unless otherwise specified, the price applies to all species, green and dead. Price may vary by
product. Payment will be based on gross weight. A weight ticket is required for each load
hauled, regardless of product type.
7. The Contractor is hereby notified that it must secure separate Purchase Agreements with mills
and/or other purchasers of timber products removed under this timber Contract. The
Contract shall select the final destination of timber products at its own discretion. Weight
tickets shall be provided to the Forest Officer and City prior to issuance of payment by the City
to the Contractor under this timber Contract.
8. The Forest Officer has estimated the net scale merchantable sawlog volume to be removed
under this Contract. Other products may be part of this Contract. All delivered wood will be
weighed and provided payment at per ton bid rates. The City recognizes that a percentage of
delivered wood may not meet the log manufacturing and recovery standards of the Helicopter
Timber Contract. The actual percentage will vary based on the log manufacturing and
recovery specifications of the Contractor and tree conditions in the Contract area. The actual
delivered weight may vary, resulting in an overrun or under‐run of the estimated tonnage.
The City strongly recommends that bidders evaluate these effects before bidding.
9. The City does not conduct detailed road appraisals. All appraised costs are gross estimates or
averages, provided only to show the relative amount of work required, and not the true
market value. The City strongly recommends that bidders make their own estimates based on
Contract requirements. Cost estimates provided are not guaranteed.
10. Bidders are encouraged to examine the complete Helicopter Timber Contract package and
Contract Area prior to bidding. Additional information regarding the Contract is available at the
phone numbers shown above.
11. Estimates for removal volume, species percents, defect, product class, etc. provided in this
prospectus and volume estimates listed in the Helicopter Timber Contract are not guaranteed.
12. This prospectus is provided for information purposes only. If the prospectus is in error or
contradicts the Helicopter Timber Contract, the Contract governs.
Additional Contract Information
1. SLASHING OF LOGGING‐DAMAGED TREES REQUIRED: The Contractor shall fell all
submerchantable trees with logging‐related root or stem damage, causing lean. The stem shall
be completely severed from the stump below the lowest live limb. Maximum stump height
shall be 12 inches on the uphill side.
2. Contact Gary Peck, Forest Officer, to arrange access to Contract area through the Liebmann
Existing Road (406‐581‐2815).
Helicopter Timber Contract Information Sheet City of Bozeman Phase 1 Sourdough Fuels Reduction ProjectTimber Cruise Data SPECIES PP DF WL LP ES WF CE WP Dead LP TOTAL or AVE Minimum Bid per ton Pounds per Board Feet 12.4 12.4 Estimated tons of sawlogs (5.6" top DIB) 5,449 690 266 6,405 tons Estimated tons of other material (pulp, etc) 472 472 tons Gross MBF (Scribner 5.6” top DIB) 967 122 51 1,140 MBF % Cull and Breakage 10 10 18 11% Net MBF (Scribner 5.6” top DIB) 879 111 43 1,033 MBF Average logs per MBF 11 11 logs/MBF Average DBH 14 14 in. Average tons per acre 87 tons/ac Average MBF per acre 14 MBF/ac Tons Per Thousand Board Feet 6,405 estimated tons to a 5.6 inch top / 1,033 Net MBF Scribner to a 5.6 inch top DIB 6.20 tons/MBF Contract Information Contract Termination Date: January 15, 2022 Operating Period: Not later than October 1 through December 15, 2021
Helicopter Timber Contract Information Sheet City of Bozeman Logging Information % of volume logged by clearcut or seed tree cut 100% % of volume logged with tractors 0% % of volume logged by skyline 0% % of volume logged by Helicopter 100% Yarding distance tractor (average) N/A Yarding distance skyline (average) N/A Yarding distance Helicopter 3,300 ft or less Estimated haul distance (paved) 40.0 miles Estimated haul distance (unpaved) 1.0 – 3.0 miles Unit Harvest Volume Unit Nos. Acres Est. Tons Est MBF Harvest Deadline East Side Units 1 – 15 54 4,582 739 October 31, 2021 West Side Units 16 - 25 25 2,295 370 December 15, 2021 79 6,877 1,109 Road development and maintenance fees and estimates Estimated road development cost total $0 Estimated road development cost per ton $0ton Estimated road development cost perMBF $0/MBF Estimated Contractor-do road maintenance cost total $2,750 Estimated Contractor-do road maintenance cost per ton $0.40/ton Private road maintenance charges per ton $0.00/ton USFS road maintenance charges per ton $0.00/ton Miles of road construction 0.0 miles Miles of road reconstruction 0.0 miles Miles of road with site improvements 0.0 miles Miles of road reclamation or abandonment 0.0 miles Miles of road maintenance and blading 4.0 miles
1
2
16 3
17
1918
21
20
22
24
25
4
5
6
7
10
9
13 14
11
15
12
23 8
05
24
08
01
18
06
19 20
12
13 17
07 SOURDOUGH CANYON RDNASH RD
Liebmann Property
Liebmann Existing Road
Spur Road
USFS System Trails
PublicLands
City Government
US Forest Service
Sourdough Fuels Treatment Areas
Helicopter Unit
Nash Rd
Sourdough Canyon RdSourdough RdS 3rd RdAttachment A
Helicopter Timber Contract Map
Phase 2 Sourdough Fuels Reduction
0 1,000 2,000500Feet
¯
Lower Landing/Decking &
Refueling Site
Upper Landing/Decking &
Refueling Site
Phase 2 Sourdough Fuels Reduction
Vicinity Map
Phase 2 Sourdough Fuels