HomeMy WebLinkAboutC015_Construction-Traffic-Route-Map 12-18-2020AVEN19THAVENPROPOSED
SITE
BAXTER LN
TSCHACHE LN
OAK ST
INTERSTATE
90
19THTO
LEGEND
CONSTRUCTION
TRAFFIC - ENTERING
CONSTRUCTION
TRAFFIC - EXITING
1.ALL IMPROVEMENTS ON THIS PROJECT SHALL BE COMPLETED IN ACCORDANCE WITH THE MONTANA PUBLIC WORKS
STANDARD SPECIFICATIONS, 6TH EDITION DATED APRIL 2010 (MPWSS); THE CITY OF BOZEMAN MODIFICATIONS TO THE
MPWSS; AND THE PROJECT SPECIFICATIONS.
2.CONTRACTOR SHALL COMPLY WITH ALL APPLICABLE DIVISION OF INDUSTRIAL REGULATIONS (OSHA) SAFETY STANDARDS.
IF REQUESTED BY THE INSPECTOR, THE CONTRACTOR SHALL PROVIDE PROOF OF A PERMIT FROM SAID DIVISION.
3.THE CONTRACTOR'S OPERATIONS SHALL BE CONFINED WITHIN THE PROJECT LIMITS. MATERIALS AND EQUIPMENT SHALL
BE STORED ON THE PROJECT SITE WHERE APPROVED BY THE OWNER. IT SHALL BE UNDERSTOOD THAT THE
RESPONSIBILITY FOR PROTECTION AND SAFEKEEPING OF EQUIPMENT AND MATERIALS ON OR NEAR THE SITE WILL BE
ENTIRELY THAT OF THE CONTRACTOR AND THAT NO CLAIM SHALL BE MADE AGAINST THE OWNER BY REASON OF ANY ACT
OF AN EMPLOYEE OR TRESPASSER.
4.THE CONTRACTOR SHALL NOTIFY THE ENGINEER AND THE CITY, COUNTY, AND/OR STATE INSPECTOR 48 HOURS PRIOR TO
COMMENCING CONSTRUCTION AND 24 HOURS IN ADVANCE OF SPECIFIC INSPECTION NEEDS DURING THE COURSE OF THE
WORK. ALL WORK SHALL BE PERFORMED DURING NORMAL WORKING HOURS AND SUBJECT TO THE AVAILABILITY OF AN
INSPECTOR AND APPROVED BY THE ENGINEER. THE CONTRACTOR WILL BE BILLED FOR SAID INSPECTION SERVICES AS
PROVIDED IN THE MOST RECENTLY ADOPTED FEES FOR SUCH SERVICES.
5.THE CONTRACTOR SHALL PERFORM ALL CONSTRUCTION ACTIVITIES IN A MANNER TO MINIMIZE INCONVENIENCE TO THE
ADJACENT BUSINESSES.
6.THE CONTRACTOR SHALL BE RESPONSIBLE FOR PROTECTING ALL PUBLIC AND PRIVATE PROPERTY INSOFAR AS IT MAY BE
AFFECTED BY THESE OPERATIONS, ALL COSTS FOR PROTECTING, REMOVING, AND RESTORING EXISTING IMPROVEMENTS
SHALL BE BORNE SOLELY BY THE CONTRACTOR.
7.THE CONTRACTOR SHALL AT ALL TIMES TAKE WHATEVER MEASURES ARE NECESSARY TO ASSURE THE PROPER
CONTAINMENT AND DISPOSAL OF POLLUTANTS ON THE SITE IN ACCORDANCE WITH ANY AND ALL APPLICABLE LOCAL,
STATE, AND FEDERAL REGULATIONS.
8.THE CONTRACTOR SHALL IMMEDIATELY CLEAN UP ANY CONSTRUCTION MATERIALS INADVERTENTLY DEPOSITED ON
EXISTING STREETS, SIDEWALKS, OR OTHER PUBLIC RIGHTS-OF-WAY AND MAKE SURE STREETS AND WALKWAYS ARE
CLEANED AT THE END OF EACH WORKING DAY.
9.CONSTRUCTION WORK ZONE TRAFFIC SIGNS SHALL BE FURNISHED, INSTALLED, AND MAINTAINED IN ACCORDANCE WITH
APPLICABLE REQUIREMENTS OF THE REGULATORY AGENCIES HAVING JURISDICTION. A TRAFFIC CONTROL PLAN,
PREPARED BY THE CONTRACTOR, MAY BE REQUIRED BY THE CITY OR STATE. "CONSTRUCTION AHEAD" WARNING SIGNS
ARE TO TO BE INSTALLED ALONG ADJACENT ROADS OR DRIVEWAYS. FLASHERS WITH CAUTION TAPE ARE TO BE
INSTALLED WHERE ANY CONSTRUCTION ACTIVITY CROSSES A SIDEWALK OR PEDESTRIAN PATH IN ACCORDANCE WITH
THE SPECIFICATIONS AND ANY OR ALL LOCAL REGULATIONS.
10.NO STOPPING, PARKING, OR STORING OF CONSTRUCTION MATERIALS IN THE PUBLIC STREETS /ROADS, RIGHTS-OF-WAY,
OR ANY DRIVEWAY IS ALLOWED.
11.CONTRACTOR IS RESPONSIBLE FOR VERIFYING THAT THERE IS A CONSTRUCTION PERMIT APPROVED BY THE MONTANA
DEPARTMENT OF ENVIRONMENTAL QUALITY (MDEQ) OR LOCAL GOVERNING AGENCY AS APPROPRIATE FOR THE CONTROL
OF STORM WATER RUNOFF. IF THERE IS NOT AN APPROVED PERMIT, THE CONTRACTOR SHALL BE RESPONSIBLE FOR
OBTAINING THE NECESSARY APPROVALS FROM MDEQ OR THE LOCAL GOVERNING AGENCY.
12.CONTRACTOR IS RESPONSIBLE FOR PROJECT DUST CONTROL.
GENERAL NOTES:
GRAPHIC SCALE
0
(IN FEET)
100 200100200
1 INCH = 200 FT
11x17 HORIZONTAL SCALE: 1" = 400'
Know what's below.
before you dig.Call
R
REVIEWSUBMITTALDEVELOPMENTAPARTMENT UNITS IN BOZEMAN, MONTANAFARRAN REALTY PARTNERSBOZEMAN EAST MIXED-USE4202 BELTWAY DRIVE ADDISON, TX 75001hedk.com214.520.8878Engineering1800 RIVER DR. NO. • GREAT FALLS, MONTANA 59401406.761.3010 • tdhengineering.com