HomeMy WebLinkAbout21- Change Order 1 - Dick Anderson Construction - WRF Solids Dewatering Building Expansion and Headworks Improvements Project EJCDC=
ENGINEERS JOINT CONTRACT
DOCUMENTS COMMITTEE
Change Order No. 01
Date of Issuance: 03/26/2021 Effective Date:
Owner: City of Bozeman Owner's Contract No.:
Contractor: Dick Anderson Construction Contractor's Project No.:
Engineer: HDR Engineering Engineer's Project No.:
10176456
Project: City of Bozeman WRF Contract Name:
Solids Dewatering Building Expansion and Headworks
Improvements Project
The Contract is modified as follows upon execution of this Change Order:
Bid Alternate A includes the installation of a new positive displacement pump, polymer system, and associated
piping modifications to allow both the existing and new screw press to operate in parallel.
Bid Alternate B includes the installation of a new transverse conveyor in the truck load-out to accommodate
solids from the existing and new conveyor s stems.
CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIMES
[note changes in Milestones if applicable]
Original Contract Price: Original Contract Times:
Substantial Completion:
$ 2,296,033.00 Ready for Final Payment:
days or dates
Increase from previously approved Change Orders No. Increase from previously approved Change Orders No.
to No. to No._
Substantial Completion:
$ N/A Ready for Final Payment:
days
Contract Price prior to this Change Order: Contract Times prior to this Change Order:
Substantial Completion:
$2,296,033.00 Ready for Final Payment:
days or dates
Increase of this Change Order: Increase of this Change Order:
Substantial Completion:
$ 274,114.00 Ready for Final Payment:
days or dates
Contract Price incorporating this Change Order: Contract Times with all approved Change Orders:
Substantial Completion:
$2,570,147.00 Ready for Final Payment:
days or dates
RECOMMENDED: ACCEPTED: ACCEPTED:
By: By: By:
Engineer(if required) a Authorized Signature) ontractor(Author' d Signature)
Title: Title: MAAa r Title: tZ03 T M h' eC t-
Date: Date Date
EJCDC°C-941,Change Order.
Prepared and published 2013 by the Engineers Joint Contract Documents Committee.
Page 1 of 1