Loading...
HomeMy WebLinkAbout85 - Design Report - Westgate - Storm DESIGN OF STORM DRAINAGE STRUCTURES for WESTGATE ADDITION SUBDIVISION Bozeman, Montana prepared for WESTGATE SUBDIVISION PARTNERSHIP prepared by KERIN AND ASSOCIATES Consulting Engineers 225 E . Mendenhall Bozeman, Montana 59715 January 18, 1985 Page 1 DLOIGN OF STORM DRAINAGE STRu�TURES WESTGATE ADDITION SUBDIVISION Using the Soil Conservation Service Drain-Cale computer program (for the Apple II computer) the peak flows and hy'drographs were computed for the pre and post development conditions for the project from the following baseline data . COMPUTER DATA Pre-Development Conditions Curve Number CN = 68 Hydraulic Length = 1333 feet Total Area = 383 , 494 SF or 8. 8 acres 10 year - 24 hour storm Total Precipitation = 1. 8 inches Runoff Depth = 0. 11 inches Average Slope S . = 1 . 28% Velocity V = 0 . 8F/S Time of Concentration Tc = 1666 seconds or 27 . 77 min. Post-Development Conditions Weighted Curve Number CN = 77 Hydraulic Length : Reach I = 100 feet Reach 2 = 1271 feet Velocity V: Reach 1 = 0 . 7 FIS Reach 2 = 2 . 4 FIS Slope So : Reach 1 = 1. 0% Reach 2 = 1. 33% Total Area = 383 , 494 S . F. or 8. 8 acres 10 year - 24 hour storm Total Precipitation = 1. 8 inches Runoff Depth = 0 . 32 inches Travel Time Tt : Reach 1 = 143 seconds or 2 . 38 min. Reach 2 = 529 seconds or 8 . 82 min. Time of Concentration Te = 672 seconds or 11 . 20 min . Page 2 Storm Drainage ructures GUTTER AND INLET CATCH BASIN DESIGN The street curb and gutter will convey stormwater and snowmelt runoff to the two inlet catch basins on the northern end of the subdivision. Both inlets will be standard Neenah Standard R-3067 open back curb inlet frame and box, as specified by Neenah Foundry Company, Box 729 , Neenah, WI 54956. Each inlet can pass approx- imately 7 . 0 CFS , (using the orifice equation Q =0 . 6A 2gh ) against a static head of 0 . 42 feet . When the head drops to three inches of water above the grate , the flow rate drops to 5 . 7 CFS through each grate . The standard City of Bozeman parabolic street section can transport approximately 12 . 5 CFS . This figure is based on the following: a Mannings Roughness Coefficient "n" of 0 . 013 , a street cross section of 3 . 0 square feet . A gutter depth at the curb of five inches . A gutter velocity of 4. 0 ft/sec, an average gutter slope of 0 . 013 feet per foot . In summary, the gutter and inlet gates have sufficient cross sectional area and opening areas , respectively, to pass stormwater generated from a 10-year, 24-hour rainfall event in Westgate Addition. The peak flow for a 10-year, 24-hour storm for pre-development conditions (hydrograph attached) is 1 . 0 CFS . For post-development conditions the hydrograph peaks at 3. 6 CFS . (See attached computer print out) . For both pre and post development this design storm event far exceeds the minimum criteria as recommended by the Water Quality Bureau of the Department of Health, which requires a minimum 5 year, 1-hour rainfall event for the design of hydraulic structures in subdivisions . The design storm event presented in this report exceeds the State ' s minimum, due to the fact the SLS computer model is programmed to accept a minimum 10 year, 24 hour event . The Precipitation-Frequency Atlas of the Western United States - NOAA Atlas 2 , published by the National Oceanic and Atmospheric Administration - 1973, was used to estimate the 5 year , 1 hour event for the Bozeman area. NOAA offers multiple-regression screen- ing techniques used to develop equations for estimating one-hour duration values . The relation for the region west of the Continental Page 3 Storm Drainage ructures Divide was developed for the area that extends from west of the divide to the west of the Cascade Range . The equation is : y = 0 . 019 + 0. 711 [x1 (xl/x2) ] + 0. 001 (x3) , where y = the estimated 2-year hour ppt . x1= 2-yr, 6-hr value x2= 2-yr, 24-hr value x3= point elevation in hundreds of feet From NOAA' s isopluvial maps for the above duration/frequency events , the above values are : x 1= 0. 7" x2= 1. 2" x3= 48 y = 0. 4" (rounded) The same equation is used to determine the 100-year, 1-hour precip- itation. From NOAA' s isopluvial maps , again, the following value can be determined : x1 = 100-year , 6-hour ppt = 1 . 6" x2 = 100-year, 24-hour ppt = 2 . 8" x3 = 48 y = 0 . 72" The 1-hour values for the 2- and 100-year return periods can be plotted on the nomograph of figure 6 to obtain values for return periods greater than 2 years or less than 100 years . The five-year, 1-hour value of 0 . 5" is obtained from the nomograph (see Figure 2) . From the pre and post development computer data on page l of this report , the 10-year, 24-hour precipitation depth is 1. 8 inches . The precipitation depth then , for this event is nearly four times that of a required 5-year, 1-hour event . In addition to requiring a minimum design rainfall event , the Bureau also requires minimum treatment of stormwater . Treatment menas reduction to 10 mg/l oil and grease and 30 mg/l suspended sediment . Based on averages of the sampling data presented in the 1982 Bozeman Storm Drainage Study, peak concentrations of oil and grease and total suspended solids in Bozeman' s stormwater run approximately Page 4 Storm Drainage S, sctures 18 mg/l and 419 mg/l , respectively. To achieve the effluent levels required in the guidelines , removals of 44. 4% of oil and grease and 92 . 8% of total suspended solids are necessary. Fifty percent removal of oil and grease can be anticipated from the recommended vegetative channels and/or grease trap inlet structures . Removals of total suspended solids will vary with the actual gradation of the stormwater sediment . Based on a hydrometer analysis of surface soils at Kagy Boulevard in Bozeman, removal of a recommended 40 micron particle and larger will remove 32% of the total sediment load. The Blue Ribbons of Big Sky Report (reference 1) and APWA' s report (reference 2) suggest that 94% and 88% removal , respectively, can be achieved by removal of the 40 micron particle and larger. In lieu of actual stormwater sediment gradations for a particular watershed, 50% removal of the total suspended solids is a reasonable estimate for design purposes . Designing for removal of finer particles is economically infeasible due to the extremely large surface area requirements caused by slow settling velocities of fine- particles . For example , removal of particles greater than or equal to one micron requires a surface area of approximately 203 , 211 square feet per 1 cfs release rate . This is 1 , 400 times larger than the area required to remove a 40 micron particle . STORM DRAIN DESIGN The storm drain connecting the two inlets is sized to be a 12-inch reinforced concrete pipe (RCP) . This size selection was based on the following parameters : a. Manning roughness coefficient "n" = 0 . 13 b. Design Q = 1. 8 CFS (one-half of subdivision contributing) C. Pipe slope - 0 . 30% The pipe designed for the 10-year, 24-hour event , is to convey stormwater and snowmelt runoff to a detention basin in Lot 11 of Westgate Addition. DETENTION BASIN DESIGN The volume under the pre-development drain calc hydrograph (see appendix) equals 0 . 07 acre-feet . The post-development runoff volume for the design storm equals 0 . 22 acre-feet . The total detention storage requirement then , based on the 10-year , 24-hour Page 5 Storm Drainage Structures is post-development volume less the pre-development volume or 0. 15 acre--feet . To reduce this value and provide sufficient volume and surface area to store runoff and settle particulates use a storage .volume of 0. 10 acre-feet . The volume in cubic feet is 4360 cubic feet (0 . 1 x 43560) . The surface area requirement at a maximum pond depth of 1. 5 feet is 2900 square feet . Based on the velocity of a 40 micron particle, the minimum de- tention basin surface area required is 145 square feet for 1 CFS release rate (Stormwater Master Plan for the City of Bozeman, 1983, p . III-9) . The minimum area required for the development is then : 145 ft2/CFS x 0. 5 CFS = 72 .5 square feet . A maximum release rate of 0 . 5 CFS will be utilized for design purposes . The recommendation for a maximum basin depth of 1 . 5 feet is a good one since it significantly reduces the threat of accidental drownings . Deeper basins , designed only for storm water detention, should be placed in remote areas and preferably fenced . (See : Storm Water Master Plan for the City of Bozeman, 1982 , p . III-10) . The required area, then, for the basin is : Area Required : 2900 square feet } 72 .5 SF For Detention Basin use 2900 square feet Page 6 Storm Drainage Structures SWALE DESIGN - (From catch inlets and detention pond) The configuration of the swale that will connect the catch basin inlets to the detention pond can be a trapezoidal grassed channel with 5 : 1 side slopes . The detention pond will hold the excess runoff while gradually releasing the pre-development base flow to the nearby ditch. The release rate will not exceed 0. 5 CFS . Peak flow Q = 3 . 6 ft3/sec (See attached computer data) Min. velocity or Non-silting velocity = 2-3 F/S (See : Chow p . 158) Use velocity of 2 . 25 F/S Non-Silting and Non-Eroding Minimum area of Swale required is computed as follows : A Swale = Q = A = 3 . 6 F3/S = 1. 60 ft2 V 2 .25 F/S For Trapezoidal Sections A = (b + zy)y T Use Z : 1 = 5 : 1 1' . Use b = 1. 5 ft . z a A = (b + zy)y = 1 . 5 = (1. 5 + 5y)y 1. 6 = 1 . 5 + 5y2 5y2 + 1 . 5 y - 1. 6 = 0 y = 0 . 43 Depth of water in swale will be approximately 0 . 4 feet . Use a freeboard of six inches Total Canal width with one foot freeboard is 0 . 93 feet . Use 1. 0 feet . Cross Sectional Area = ( (1 . 5 + 11 .5) z x 1 . 0) = 6 . 5 x 1 = 6 . 5 sq . ft . Calculate Swale Slope : Q = 1. 486 AR2/3 S2 or V = 1. 486 R2/3 s2 n n SF = n2V2 2 . 22 R4/3 (Chow p . 221) Where : SF = Slope of Channel V = Mean Velocity n = Roughness Coefficient R = Hydraulic Radius R = (b + zy)y b + 2y 1 + 22 (Chow p . 21) Page 7 Storm Drainage Sti .'cures 2 2 SF 2 .T2—R4/3 R, = ( (1. 5 + 5 (. 5) ) . 5 1. 5 + 2 ( . 5) (1 + 52)2, R = 6.59 = 0 . 30 n = 0. 030 (Chow p. 113) SF = (0 . 03)2 (2 . 25)2 SF = 0.010 2 . 22 0. 30 4/3 SAVL = 0 . 010 ft/ft Use SF = 0 . 010 V = 1. 486 R2/3 S 2 = 1. 486 (0. 300)2/3 (0 . 010)2 n 0. 03 V = 2 .25 ft/sec 2 V 3 ft/sec Ok! ! At a velocity approximately 2 . 25 ft/sec no scouring will occur . Minimum silting will occur with this velocity as well . Use a trapezoidal channel as shown below with a bottom width of 1. 5 ft. and side slope of 5 : 1. Total Depth y = 1. 0 ft . The total distance from top of bank to top of bank is 11 .5 ft . 1.01 -� 5 Use the same section on all channels within the project area if open channels are preferred. The developer also has the option to the catch basin inlets to the detention basin by way of reinforced concrete pipe . The min- imum sized pipe must be 15-inches . This design is based on the following: Pipe Slope - 0 . 33% Manning "n" - 0 . 012 Discharge volume - 4. 3 CFS Type of pipe - RCP Min. pipe diameter - 15" OUTLET STRUCTURE AND CHANNEL The outlet structure and temporary diversion channel are shown on the plans as well . The design outlet rate is 0 . 5 CFS . The pre- development runoff rate is 1 . 0 CFS . The choice of using 0 . 5 CFS is a conservative release rate . At this rate the outflow pipe must be minimum sized 12-inch diameter pipe . This sizing is based on the following: Page 8 Storm Drainage —ructure - Manning "n" = 0 . 012 - Minimum pipe slope - 0 . 49% - Minimum velocity - 2 . 7 ft/sec - Maximum discharge - 3 . 0 CFS - Pipe size - 12" diameter - Type of pipe - RCP EXISTING DITCH The release water from the detention basin will flow through the outlet pipe to the existing irrigation ditch, commonly called the Harmon Ditch. The Harmon Ditch flow irrigation water seasonally. It is tributary to the Farmer ' s Canal . Water enters the ditch directly from a headgate to the ditch. Twin 24-inch diameter culverts carry ditch water under West Babcock in the southeast corner of the subdivision. The combined flow of the two pipes when flowing full can pass approximately 12-14 cubic feet per second. The cross sectional area of the ditch, north of Babcock, varies from 5 square feet to 30 square feet . The ditch cross sectional area is Page 9 Storm Drainage Structure at the minimum, on the immediate south end of the Westgate Sub- division in Lot 1. Little or no stormwater runoff will enter the ditch at this point , however. The ditch widens and deepens sig- nificantly as the ditch leaves this first lot . A typical cross sectional on the ditch at the north end of the subdivision is shown in Figuie 1. The stormwater return channel from the detention basin will connect to the ditch where cross sectional areas of the Harmon Ditch is at 18 square fee minimum. Ditches typically flow at less than capacity. An allowance for freeboard for this analysis is assumed to be one foot . With this considered, the effective ditch section is calculated to be 10 . 0 square feet . The carrying capacity of the ditch with consideration for freeboard is calculated to be 31 cubic feet per second, based on the following design parameters : a. Mannings roughness coefficient of 0. 050 b. Channel slope - 1. 3% C. Effective channel cross sectional area - 10 . 0 square feet d. Wetted perimeter "D" = 11. 5 feet The ditch, as it flows north of Westgate Addition, passes through one additional down gradient culvert at Durston Road (see attached map) . The pipe is a 36-inch diameter culvert with a carrying capacity of 17-20 cubic feet per second, assuming a minimum pipe gradient of 0 . 002 - 0. 003 feet/foot and no headwater depth on the inlet end of the pipe . Before a headwater depth would develop on Durston, the ditch water would overflow to the west along the south ditch of Durston. The Harmon Ditch then is limited by the size of the culverts on West Babcock Street- and Durston Road. The ditch itself has more capacity than the upstream and downstream culverts . Page 10 Storm Drainage Structures Existing water rights through the Harmon Ditch total 175 miners inches . Harriott Smith owns 150 of those inches . The balance is owned by Howard Barrick. The Barrick property lies adjacent and north of Westgate. The Smith property is adjacent and north of Durston Road. The 175 inches equates to 4. 4. cubic feet per second (40 miners inches equals 1 CFS) . In the springtime the ditch typically flows more than 4. 4 CFS , but not more than the culverts can carry. In discussing historical flooding of the adjacent property due to voerflow from the Harmon Ditch with longtime residents of the area, no one recalls the Harmon Ditch overflowing its banks . DESIGN OF RELEASE STRUCTURE FROM POND For a release rate of 0 . 5 cubic feet per second against a total dynamic head of 1. 0 feet , the cross sectional area of the slotted release structure must have a cross sectional area of 1 . 04 square feet . This figure is based on the orifice equation Q = 0. 6A /2gh and the following design criteria : Q = 0 . 5 CFS g = 32 . 2 ft/sec h = 1. 0 feet At 0 . 104 square feet , the rectangular slot will have 'the dimensions of 3. 0 inches in width and 6 inches in length. In summary, the gradual release of stormwater from Westgate, at a rate of 0 . 5 cubic feet per second will go undetected in the Harmon Ditch. The ditch and its hydraulic structures have sufficient capacity to accept the controlled runoff from the subdivision. Mean of Annual Series Precipitation(Inches) w 1 , N .r I 1 0 QI Rf f 1 Co }4 O r-1 Ln � 1 Ul u ' c N a 0 O g 0 . 7"` m - a` 21 5 10 25 50 100 Return Period in Years,Partial-Duration Series .Figure 2- Precipitation depth versus return period for partial-duration: series. Nomograph: NOAA - Atlas 2 Precipitation-Frequency Atlas of Western United States - 1973 FIGURE I - TYPICAL CROSS SECTION - HARMON DITCH 3 I 4 1 FT. FREEBOARD J Q 5 F= cr W > I 6 7 i 240 250 260 270 280 HORZ. SCALE 1'l= 10, LEGEND OVERALL DITCH AREA 18.0 SO.FT EFFECTIVE DITCH AREA ® 10.0 SO. FT. WETTED PERIMETER 11.5 FT. KERIN a ASSOCIATES CONSULTING ENGINEERS BOZEMAN,MONTANA 59715 . / ESTGATE ADDITION ' TORM DRAIN ANALYSIS UBCAT 1-PRE DEVELOPMENT CONDITIONS UBCAT 2-POST DEVELOPMENT CONDITIONS 1PUT THE FUNCTION DESIRED, (0=MENU) 4 ______......... __________________ EXISTING SUBCATCHMENT DATA ___...............________________ SUBCAT #1 AREA- 8. 8 ACRES C N= 68 TC= 27 PEAK FLOW 1 CFS RAINFALL- 1 . 8 INCHES SUBCAT #2 AREA= 8. 8 ACRES CN= 77 TC= 11 PEAK FLOW= 3. � CFS RA[NFALL- 1 . 8 INCHES _........._.............__ EXISTING ROUTING DATA EXISTING MEMORY DAT : EllWiNG WADING PONDI!16 UATA � CUBIC FEET >� SECOND ' ) ********************* |OUR 0 *0 0. 2 *0 0. 4 *0 0. 6 *0 0. 8 *0 1 *0 1 . 2 *0 1 . 4 1 . 6 2. 2 2. 4 2. 6 2. 8 3. 2 3. 4 ******. 1 3. 6 ******. 1 3. 8 4 ******. 1 4. 2 4. 4 1. 6 ******. 1 08 5. 2 ******. 1 5. 4 5. 6 *0 5' 8 *0 b *0 j. 2 *0 �. 4 *0 �. 6 *0 ,. 8 *0 ' *0 '. 2 *0 '. 4 *0 '. 6 *0 '. 8 *0 } *0 |. 2 *0 �. 4 *0 1. 6 *0 ' 8 *0 *0 � . 2 *0 . 4 *0 . 6 *0 . 8 *0 *0 CUBIC FEET PER SECOND HOUR 10 *0 10. 2 *0 10. 4 *0 10. 6 *. 1 ' 10. 8 *. 1 11 *. 1 11 . 2 *. 1 11 . 4 ***. 2 11 . 6 *******. 4 ^ 12 12. 2 12. 4 12. 6 - 12. 8 13 13. 2 13. 4 ***. 2 L3.6 ***. 2 13. 8 ***.2 i4 ***. 2 i4. 2 ***. 2 i4. 4 ***. 2 i4.6 *. 1 i4.B *. 1 i5 *. 1 i5.2 *. 1 i5.4 *. 1 ` '5. 6 *. 1 .5. 8 *. 1 .6 *. L ' .6. 2 *. 1 .6. 4 *. 1 6. 6 *. 1 6. 8 *. 1 7 *. 1 7. 2 *. 1 7. 4 *. 1 7. 6 *. 1 7.8 *. 1 8 *. 1 8. 2 *. 1 8. 4 *. 1 8. 6 *. 1 8. 8 *. 1 9 *. 1 9.2 *. 1 9. 4 *. 1 9. 6 *. 1 9. 8 *. 1 0 *. 1 � � - - . |HICH COMPUTATION DO YOU W. } TO � ,ERFORM (0=11ENU) ? 13 HE VOLUME UNDER THE CALCULATED YDROGRAPH= . 07 ACRE FT. HICH COMPUTATION DO YOU WISH TO ERFORM (0=MENU) ? 12 OLUME SUBCAT 2 " HICH COMPUTATION DO YOU WISH TO ' ERFORM (0=MENU)? 13 HE VOLUME UNDER THE CALCULATED YDROGRAPH= . 22 ACRE FT. HICH COMPUTATION DO YOU WISH TO �RFORM ((-)----:MENU) ? 12 � _ ` � � ~ . � | | / i | \ . � � i ' | .- . , ^ HYDROBRAPH FOR SUBCATCHMENT #1 ' --------------------------------- CUBIC FEET PER SECOND ********************* iOUR L0 *0 !0. 1 *0 ,0.2 *0 .0. 3 *0 .0.4 *0 ./}. 5 *0 0.6 *0 0. 7 *0 0.9 *0 0. 9 *0 1 *0 1 . 1 *0 1 .2 *0 1 .4 ******. 1 | | 1 . 5 ******. 1 . 1 . 6 1 . 7 *************. 2 1 . 9 2 2. 1 **************e***************************************************1 2. 2 2. 3 2.5 2. 6 2. 7 i 2. 8 *************. 2 ! 2. 9 *************. 2 3. 2 ******, 1 3. 3 ******, 1 5. 4 ******, 1 ' 5. 5 ******. 1 5. 6 ******. 1 5. 7 ******. 1 � 5. 8 ******, 1 � 1. 9 ******. 1 ' �] ` 14. 4 ******. 1 14. 5 1*****. 1 _ 14. 6 14. 7 ******. 1 14.8 ******. 1 14. 9 ******. 1 15 15. 1 15. 2 15. 3 15. 4 15. 5 15. 6 *0 , 15. 7 *0 15. 8 *O 15. 9 *0 ` 16 *0 ' 16. 1 *0 16. 2 *0 ` 16. 3 *0 16. 4 *0 16. 5 *0 16. 6 *0 16. 7 *0 16.8 *0 16. 9 *0 17 *0 - 17. 1 *0 17.2 *0 17. 3 *0 17.4 *O 17. 5 *0 i7. 6 *0 i7. 7 *0 i7. 8 *0 L7. 9 *0 i8 *0 i8. 1 10 L8.2 *0 i8. 3 *0 i8. 4 *0 i8.5 *0 18. 6 *0 ' i8. 7 *0 0. 8 *0 .8. 9 *0 .9 *O .9. 1 *0 9.2 *0 9.3 *0 3.4 *0 .9. 5 *0 .9. 6 *0 � ,9. 7 *0 9.8 *O 9. 9 *0 A *0 ^ _______________________________ ' � CUBIC FEET / l SECOND -- ' ' OUR, 0 *0 0~ 1 *0 0.2 *0 0. 3 *0 ' 0. 4 *0 0. 5 *. 1 0.6 *. 1 0. 7 *. 1 ^ 0.8 *. 1 0.9 *. 1 1 *. 1 1 .2 *. 1 1 .3 ***. 2 1 . 4 ***. 2 1 . 5 ***. 2 1 ~ 6 1 . 7 ******************1 1 .9 2 2. 1 2.2 2. 3 2. 4 ***********.6 2. 5 ***********. 6 ` Z. 6 *********. 5 2. 7 *******. 4 . 2. 8 2.9 3. 2 3 L * � � 3 **. 2 L4 ***. 2 3. 5 ***. 2 5.6 ***. 2 5. 7 ***. 2 . 1.8 ***. 2 1. 9 ***. 2 1 ***. 2 1. 1 ***. 2 1. 2 ***. 2 1. 3 ***. 2 ^. 4 ***. 2 | '. 5 ***. 2 1 { 7 *. 1~ | . 8 *. 1 ^ 9 *. 1 i *. 1 i. 2 *. 1 /. 3 *. 1 . 4 *. 1 . 6 *. 1 - 7 *. 1 . y 8 * 1. . � 16. 1 *. 1 16. 2 14). 3 / 16. 4 *. 1 16. 5 *. 1 16. 6 *. 1 16. 7 *. 1 16. 8 *. 1 16.9 *. 1 17 *. 1 17. 1 *. 1 17.2 *. 1 17. 3 *. 1 , 17.4 *. 1 17. 5 *. 1 17. 6 *. 1 17. 7 *. 1 ' 17. 8 *. 1 ' 17.9 *. 1 18 *. 1 18. 1 *. 1 18.2 *. 1 18. 3 1 18. 4 *. 1 18.5 *. 1 18.6 *. 1 ' 18. 7 *. 1 � 18.8 *. 1 18.9 *. 1 19 *. 1 ` i9. 2 *. 1 - i9. 3 *. 1 i9. 4 *. 1 i9. 5 *. 1 i9. 6 *. 1 i9. 7 *. 1 - i9.8 1 �9. 9 *. 1 �0 *. 1 - � � �