HomeMy WebLinkAboutConcurrent Construction Request 01-04-21 MADISON
ENGINEERING
January 4th, 2021
Mr. Griffin Neilson, PE
City of Bozeman Engineering
PO Box 1230
Bozeman MT 59771
RE: Concurrent Construction Request—Palisades Condominium project
On behalf of our client, we are requesting concurrent construction for the required public
infrastructure improvements for the proposed Palisades Condominium project on Block 21 of the
Cattail Creek Sub PH 3, located on Catamount @ Warbler Way.
The required public improvements are for a water and sanitary sewer main extension on the east
side of the property. The improvement are required for the proposed development of the
condominium units.
Based on the Bozeman Unified Development Code (UDC), Section 38.270.030.C.1 b&c we
believe the following conditions allowing concurrent construction are met.
38.270.030.C.1.b The water mains, sewer mains and streets to be extended to provide
service to the development are: located within a publicly dedicated right-
of-way or easement; constructed to city standards; are physically adjacent;
are installed and accepted by the city; and are adequate in capacity to
provide necessary service to the proposed development; and comply with
the requirements of this subsection C.Lb and subsection C.1.c of this
section;
Response:
1. The water and sewer main extensions will be within a publicly dedicated right-of-
way and easement.
2. The required main extensions will be constructed to City Standards.
3. The water and sewer main extensions are on and adjacent to the lot on which the
Palisades Condominium project is being built.
4. The water main extension is the same size as the mains being connected to. The
water main extension loops into existing mains. The water and sewer main
extensions are of adequate capacity to provide necessary service to the proposed
development.
GAMADISON ENGINEERING\PROJECTS\2018\18-122 Pallisades Condom inium\Application\Concurrent Construction\Concurrent
Review Request letter_doc
895 Technology Blvd Ste 203 ♦ Bozeman,MT 59718 ♦ (406)586-0262 ♦ Fax(406) 586-5740
January 41h,2021 Palisades Condominium-Concurrent Construction
Request
5. The required public utility and access easement has been submitted to the city for
review and processing.
38.270.030.C.1.c Water mains, sewer mains and streets shall meet the following
requirements:
(1) Any required on-site extensions of water mains, sewer mains or streets to be
dedicated to the public shall be located entirely within publicly held easements or
rights-of-way; shall serve only a single lot; are the subject of an irrevocable offer
of dedication to the city upon completion of the project; the development is under
the control of a single developer who shall retain control of the entire project until
final completion; all work is under the supervision of a single general contractor;
and no subdivision of land is involved;
Response:
1. The water main extension will serve only one lot and will be located
within an existing Public Right of Way and Easement. The required
public utility and access easement has been submitted to the city and
approved. A copy of the recorded easement is included in this site plan
submittal.
2. The water main extension is being constructed for the development of the
Palisades Condominium project.
3. The developer agrees to the required irrevocable offer of dedication of the
improvements to the city upon completion of the project.
4. The water and sewer main extensions will be under the control of a single
developer who shall retain control of the entire project until final
completion.
5. All work will be under the supervision of a single general contractor.
6. No subdivision of land is involved with this site plan approval.
(2) The DRC shall determine when the standards of this subsection C.1 are met. The
fire department must consider whether adequate fire protection services are
available from existing hydrants, and water supply exists to meet needs during
construction. If adequate fire protection does not exist then concurrent
infrastructure and building construction may only occur under the provisions of
subsection C.l.c.(3) of this section. Based on evaluation by the fire department,
simultaneous construction of infrastructure to be dedicated to the public and
private construction may be permitted only within a defined portion of the site;
Madison Engineering LLC Page 2
January 41h, 2021 Palisades Condominium-Concurrent Construction
Request
Response: Scott Mueller at the Bozeman Fire Department, has been contacted with
regards to this request to allow concurrent construction and has provided an
approval letter, which is attached to this Concurrent Construction request.
(3) Approval of the final engineering design, including location and grade, for the
infrastructure project must be obtained from the engineering department, and the
state department of environmental quality when applicable, prior to issuance of
any building permit for the development;
Response: Infrastructure design has been submitted for review and approval has been
granted from both DEQ and the City of Bozeman for the main extensions.
(4) No occupancy, either temporary or final, may be issued until all on-site and
offsite water, sewer and street or drive improvements are installed and accepted or
approved as applicable by the city.
Response: The owner acknowledges no occupancy of any structures or
commencement of any use will be allowed until required infrastructure
improvements have been completed, inspected and accepted by the city, and a
certificate of occupancy has been issued.
Please consider our request at your earliest convenience. If you have any questions regarding
this proposal please feel free to call us at 586-0262.
Sincerely,
Madison Engineering, Inc.
Chris G. Budeski, PE
Principal
Cc: Jeff Pfeil
file
Madison Engineering LLC Page 3
BOZ E MAN MT
FIRE DEPARTMENT
January 14, 2021
Chris Budeski
Madison Engineering, LLC
895 Technology Blvd, Suite 203
Bozeman, MT 59718
RE: Concurrent Construction for the proposed Palisades Condominium project located on Lot 7
Block 21 of the Cattail Creek Sub PH 3, located on Catamount @ Warbler Way.
Mr. Budeski,
Per concurrent construction request documents emailed to me on January 8, 2021.
I approve concurrent construction for Palisades Condominium project.
The following requirements must be met for this approval to be binding.
1. 365/24/7 access to working hydrants and acceptable, approved water source
2. Staging plan for location of construction materials,temporary work trailer, and any
additional combustible materials
3. Ingress and egress routes for emergency services
4. All weather site access
5. Knox locks for fenced or gated areas
Scott Mueller
Deputy Chief Fire Marshal
406.582.2353
smueller@bozeman.net
CC: COB Engineering Department, Lance Lehigh, Griffin Nielsen
P.O. Box 1230
TDD: 406-582-2301 THE MOST LIVABLE PLACE