Loading...
HomeMy WebLinkAbout2020 Storm Improvements - Contract DocumentsBIDDER agrees to perform all the work described in the CONTRACT DOCUMENTS for the following unit prices or lump sums: BID SCHEDULE Schedule 1: General Conditions & installation of storm drain at2014 Commonwealth Street, including: removing and replacing existing curb and gutter, removing and replacing existing street section curb to curb, removing and replacing existing sidewalk, installing new storm drain inlet, installing new storm drain pipe, installation of outlet velocity dissÍpation, restoring existing boulevard and detention pond to pre-existing conditions, and all related work incidental to construction. TOTAL SCHEDULE 1 BID $ì,q- pi¡11--k *l,l l,[1,. lh" J"IL, .,J ilone,-- Item Description Ilnit Unit Price Estimated Ouantity Total Estimated Price 1 0 1 Taxes, Bonds, Insurance L.S.7w*I 7aÐ 102 Mobilization L.S 4tt€1 9to* 103 Remove Existing Concrete S.F.tÐ 54 7<t9 t04 1.5" Minus Crushed Base Course C.Y 7rÐ 5 3ço"2 105 Asphalt Concrete Pavement 4" Thickness S.Y.<*22 IttsØ 106 Concrete Curb and Gutter L.F It l*- -6 kro> 107 Concrete Sidewalk 4" Depth S.F ¡t4lôlF 36 ?e/> 108 Standard Storm Drain Inlet Each ),qu*I ) t*9 109 12" Schedule 40 PVC Storm Drain Pipe L.F 5*6t j.?7 1r0 Install Outlet Velocity Dissipation Each /5ç1+I 7<0> 111 Connection to Existing 2" Foundation Drain L.S lqA I /.oq,u-lt2 Site Restoration L.S.i snu I lg+ 113 Traff,rc Control L.S ZaL 1 çoo>tt4 Miscellaneous 'Work Each $1.00 5,000 $5,000.00 (TOTAL/SCHEDULE I BID - WRTTTEN V/O ) 3 BID FORM Schedule 2: Installation of storm drain in Oconnell Drive, including: modifying existing stormwater basin inlet structure, removing existing storm manhole, installing new storm manholes, installing new storm drain pipe, installing outletvelocity dissipation, restoring existing gravel driveway, repairing existing driveway and swale, restoring existing asphalt parking, regrading existing street side ditch, and all related work incidental to construction. TOTAL SCHEDULE 2 BID æt uLE2 BrD - WRTTTEN WORDS) $ 4 Item Description Unit Unit Price Estimated Quantity Total Estimated Price 201 Mobilization L.S 7rrt9 1 lrrt* 202 Core I5" Penetration into Existing Pond Inlet Structure L.S 1.KIL I î/o> 203 Remove Existing Storm Drain Manhole L.S.&*I &)L 204 48" Storm Drain Manhole Each 3.(fis 4 H çrre 205 8" Schedule 40 PVC Storm Drain Pipe L.F .ro-t36 (. t*u 206 15" Class 3 RCP Storm Drain PiPe L.F 6t*8 S*q!z- 207 Asphalt Concrete Pavement 4" Thickness S.Y.ÁBe 7 7æ 208 Site Restoration L.S.-ldi- lt-lo-1 l rcnz 209 Regrade Ditch L.F 'lq¿38 7ù9+ 210 Install Outlet Velocity Dissipation Each 7sÊ 1 7x¡+ 211 1.5" Minus Crushed Base Course C.Y.7t>20 I s6o: 212 Traffic Control L.S.Itúu:l--1 &)e 2r3 Miscellaneous Work Each $ 1.00 5 000,$5,000 BID FORM Schedule 3: Installation of new storm drain inlet, pipe, and swale at New Hyalite View Park. TOTAL SCHEDULE 3 BID $o e- (TOTAL SCHEDULE 3 BrD -woRDS) 5 Item Description Unit Unit Price Estimated Quantity Total Estimated Price 301 Mobilization L.S ?tau I arctL 302 Remove Existing Concrete S.F.XqY-t6 'fute 303 Concrete Curb and Gutter L.F.lrcL 4 9+s+ 304 Concrete Valley Gutter S.F 5tc¡8 16qe 305 Standard Storm Drain Inlet Each ?,?cnY I 2.Çcae 306 12" Schedule 40 PVC Storm Drain Pipe L.F (zL l5 l,cttf 307 Install Outlet Velocity Dissipation Each 7aL 1 7rÈ 308 Install Swale L.F.lzL 133 2xtØ 309 Site Restoration L.S.I no*I *rto* 310 Traffic Control L.S.ire+1 ìú'eL- 311 Miscellaneous Work Each $1.00 5,000 $5,000 BID FORM BASIS OF AWARD If the contract is awarded, the Owner will award a single Contract in accordance with the Instructions to Bidders. Bidders shall submit a Bid for all bid Schedules on a unit price basis for each item of Work listed as provided and described above. The Owner reserves the right to accept or reject the Bids, or portions ofthe Bids denoted as separate schedules or alternates. The award will be made by the Owner on the basis of that Bid from the lowest responsive, responsible Bidder which, in the Owner's sole and absolute judgment, will best serve the interest of the Owner. The low bidder will be determined on the basis of the lowest Total Combined Schedule 1,2,3 and 4 Bid. The undersigned Bidder acknowledged receipt of the following Addenda, which have been considered in preparation of this Bid: No.Dated No Dated No Dated No Dated Submitted this day of SIGNATURE OF Montana Contractor If an individual Number (- ão 2 doing business as If a Partnership by partner If a Corporation: (a) Title Vio C lr'Þ by ?( (Seal & Attest) f//c øBusiness Address of Bidder: lllZ 11.,r* 6 BTD FORM If Bidder is a joint venture, other party must sign below: Montana License Number and Class If an Individual: business as If a Partnership by Partner If a Corporation: doing (a Corporation by Title (Seal & Attest) 7 BID FORM MEASUREMENT AND PAYMENT 1 SECTION 00100 MEASUREMENT AND PAYMENT The quantities listed in the Bid Form are estimates for the purpose of bidding only. Payment to the Contractor will be made based on the actual satisfactorily completed work quantities measured in the field. Under the terms of this contract, the unit price as contained in this Bid Form shall be applicable to quantity overruns. The following measurement and payment sections do not necessarily name every incidental item required by the Contract Documents to complete the work. Cost of all such incidental items shall be included in the various related bid items. Storm water pollution prevention shall be included as an item required under the contract and incidental to construction. Item 101: (Taxes, Bonds, Insurance) To be paid on the first progress pay estimate one-hundred percent (100%) upon mobilization to begin construction, only if the bid price for this item is less than five percent (5%) of the total price. For that portion of the taxes, bonds, and insurance greater than five percent (5%), if any, payment shall be made on the basis of the percentage of the work completed of each progress estimate. Items 102, 201, & 301: (Mobilization) Fifty percent (50%) to be paid on the first progress estimate when mobilizing to begin construction, and fifty percent (50%) to be paid following substantial completion and acceptance of the work. Items 103 & 302: (Remove Existing Concrete) Measurement and payment shall be as per MPWSS Section 02112 4.2 where the quantity shall be measured by the square foot (SF) of concrete sidewalk, curb, gutter, and valley gutter removed, which price shall include all removal and disposal work (saw cutting included) regardless of the thickness of the concrete. Items 104 & 211: (1.5” Minus Crushed Base Course) Measurement and payment shall be as per MPWSS Section 02235 4.1. Work shall include base course for street restoration, driveway restoration, asphalt parking pad restoration, and driveway and swale repair. Items 105 & 207: (Asphalt Concrete Pavement 4” Thickness) Measurement and payment shall be as per MPWSS Section 02510 4.2. Items 106 & 303: (Concrete Curb and Gutter) Measurement and payment shall be as per MPWSS Section 02528 4.1.A. Item 107: (Concrete Sidewalk 4” Depth) Measurement and payment shall be as per MPWSS Sections 02529 4.3, and 4.4. Payment shall be inclusive of excavation, placing 1.5” minus crushed base material, and backfill. Items 108 & 305: (Standard Storm Drain Inlet) Measurement and payment shall be as per MPWSS MEASUREMENT AND PAYMENT 2 Section 02720 4.4.A. Items 109 & 306: (12” Schedule 40 PVC Storm Drain Pipe) Measurement and payment shall be as per MPWSS Section 02720 4.2.A. Payment shall also include full compensation for saw cutting and removing asphalt, excavation and removal of material, pipe bedding, backfill, and compaction. Items 110, 210, & 307: (Install Outlet Velocity Dissipation) Measurement and payment shall be by the numerical count of outlet velocity dissipation devices installed. Payment shall include full compensation for all labor, materials, and equipment necessary to install the device, including: excavation, backfill, geotextile placement, riprap placement, and disposal of excess existing soils as required, and all other items incidental to the completion of this item. Item 111: (Connection to Existing 2” Foundation Drain) Measurement shall be made on a lump sum basis. Payment shall include full compensation for all labor, materials, and equipment necessary to make the connection, including: excavation, backfill, concrete demolition and disposal as required for the penetration, grouting and all other items incidental to the completion of this item. Items 112, 208, & 309: (Site Restoration) Measurement shall be made on a lump sum basis. Payment at the contract unit price shall constitute full compensation for all topsoil placement, seeding, and temporary stabilization as necessary to restore disturbed project areas. The work shall include providing topsoil, site preparation, seed, fertilizer, stabilization, related materials, labor, tools, equipment, and incidentals necessary to complete the item. Items 113, 212, & 310: (Traffic Control) Measurement and payment shall be as per MPWSS Section 01570-4.1. Items 114, 213, & 311: (Miscellaneous Work) The item Miscellaneous Work has been provided in the proposal for any work and/or materials which may be encountered during construction, but which is not addressed elsewhere in the contract. Miscellaneous work will be measured by the respective unit for material and/or work performed as directed in writing by the Engineer. Payment for Miscellaneous Work, measured as provided above, will be at agreed upon prices or on force account basis. The number of units in dollars set down in the contract is an estimated amount only, which may be adjusted up or down by the Engineer in accordance with the needs of the project. Item 202: (Core 15” Penetration into Existing Pond Inlet Structure) Measurement shall be by the numerical count of each core made into an inlet structure. Payment shall include full compensation for all labor, materials, and equipment necessary to core the structure, including: excavation, backfill, concrete demolition and disposal as required for the penetration, and all other items incidental to the completion of this item. Item 203: (Remove Existing Storm Drain Manhole) Measurement shall be by the numerical count of each manhole and/or inlet removed. Payment at the contract unit price shall constitute full compensation for removal of the structure in its entirety, trench excavation, dewatering, backfill, and compaction, proper disposal of all waste materials including the structure and all its appurtenances, storm sewer pipe MEASUREMENT AND PAYMENT 3 of various sizes as shown on the plans and Fernco flexible couplings to reconnect the existing main where manholes have been removed, and all other work necessary or incidental for completion of the item. Item 204: (48” Storm Drain Manhole) Measurement and payment shall be as per MPWSS Section 02720 4.3. Where the manhole is replacing an existing manhole on the existing storm sewer main, this item shall also include connection to the exiting main on both upstream and downstream side, including extra excavation, dewatering, various sizes of pipe, various sizes of Fernco flexible couplings, backfill, compaction, disposal of all waste materials including existing pipe, and all other work necessary or incidental for completion of the item. Item 205: (8” Schedule 40 PVC Storm Drain Pipe) Measurement and payment shall be as per MPWSS Section 02720 4.2.A. Item 206: (15” Class 3 RCP Storm Drain Pipe) Measurement and payment shall be as per MPWSS Section 02720 4.2.A. Item 209: (Regrade Ditch) Measurement and payment shall be on a per lineal foot basis for ditch regraded. Payment shall be made at the unit bid price for all labor, equipment, materials and incidentals necessary to grade and stabilize the ditch, per the plans. Item 304: (Concrete Valley Gutter) Measurement and payment shall be as per MPWSS Section 02529 4.2.A. Item 308: (Install Swale) Measurement and payment shall be on a per lineal foot basis for swale constructed. Payment shall be made at the unit bid price for all labor, equipment, materials and incidentals necessary to construct the swale, including: excavation, grading, stabilization, disposal of excess materials as necessary and all other items incidental to the completion of this item. 37 Stabilization Measures Disturbed Area Introduction Stabilization measures reduce erosion, increase infiltration, slow the flow of water, and minimize raindrop impact of disturbed areas during and after construction activities. Stabilization measures can be temporary or permanent depending on their type and application. Disturbed areas that will remain inactive for 14 or more days are required to be stabilized. Applicable Local Requirements 1. Stabilize disturbed areas Approved Options 1. Surface Roughening: Consists of 3” minimum depressions running perpendicular to slopes using equipment, such as a grouser or sheep’s foot. 2. Crimped Straw Mulch: Consists of weed-free straw with a 12” minimum length evenly distributed at a rate of 4000 lbs/acre and crimped into the soil. Straw blowers and hand broadcasting are useful distribution methods. Flat shovels and disc plows work well for crimping. 3. Wood Mulching: Consists of shredded wood and compost evenly distributed. Apply wood mulch and compost to a depth of 2”-3”. 4. Rolled Erosion Control Products: Consists of biodegradable blankets composed of fibers such as jute, straw, coconut, or a combination of straw and coconut fibers. Installation criteria to consider include anchor slots, overlapping adjacent blankets, check dams, and staking. See page 36 for an installation specification 5. Sod: Immediately stabilizes disturbed areas. Consider sod type, soil preparation, soil amendments, and irrigation until establishment 6. Hydro-Seed: Consists of wood mulch, tackifier/binder, and seed sprayed by machine or hand depending on the application and area. Hydro-seed immediately stabilizes barren ground and can be used in temporary or permanent applications. Image 34 - Sprayed hydro-seed Image 32 - Erosion Control Product Image 31 - Wood Mulching Image 30 - Crimped Straw Mulch Image 29 - Surface Roughening 38 **Note: Taken from MDT’s December 2016 Erosion and Sediment Control Best Management Practices Manual 39 **Note: Taken from MDT’s December 2016 Erosion and Sediment Control Best Management Practices Manual