HomeMy WebLinkAbout11-20-20 Public Comment - C. Selby - SID 762 S. 6th AveFrom:Kellen Gamradt
To:cselby@bresnan.net
Cc:Katherine Maines
Subject:RE: S. 6th Proposed Reconstruction Project
Date:Friday, November 20, 2020 12:09:28 PM
Hi Corinne,
I looked into your question below. The City only schedules out 5-years of capital improvements for
water and sewer renovations. The plan shows water and sewer renovations scheduled to be
completed at the same time as the street reconstruction on S 6th as we mentioned in the meeting
last night. If the street project fails to get public support, then the water and sewer renovations
work would be moved to “unscheduled” on our capital improvement plan which means that the
work needs to be done; however, it is not scheduled to be completed within the next 5-years.
Every fall, the city commission adopts a new capital improvement plan as projects get completed
and the City’s needs change. Therefore, water/sewer improvements on S. 6th could end up on a
future CIP plan, but they would be “unscheduled” if the street reconstruction fails.
Thanks,
City of Bozeman MT
Kellen Gamradt, PE| Engineer II
o: 406.582.2283
c: 406.579.9643
kgamradt@bozeman.net
From: Katherine Maines <KMaines@BOZEMAN.NET>
Sent: Friday, November 20, 2020 11:50 AM
To: Kellen Gamradt <KGamradt@BOZEMAN.NET>
Subject: FW: S. 6th Proposed Reconstruction Project
Kellen – Please see Corinne’s question below.
From: Corinne Selby <cselby@bresnan.net>
Sent: Friday, November 20, 2020 11:30 AM
To: Katherine Maines <KMaines@BOZEMAN.NET>
Subject: RE: S. 6th Proposed Reconstruction Project
You might want to correct the letter before mailing. See p 2:
Again, if property owners representing more than 50% of the street frontage
vote against creation at that time, the SID will not be created and West
Harrison will not be improved.
Can you tell us when S 6th is scheduled for sewer and water line updates?
Cheers…Corinne
From: Katherine Maines [mailto:KMaines@BOZEMAN.NET] Sent: Friday, November 20, 2020 10:59 AMTo: Katherine MainesSubject: S. 6th Proposed Reconstruction Project
Good morning. This email is to follow up on the neighborhood meeting that was held last night
regarding the South 6th Avenue proposed reconstruction project. Letters were mailed today asking
homeowners for their vote and any feedback they’d like to provide on this project. That letter is also
attached to this email. As mentioned in that letter, information on this project can be found in by
visiting https://bzncloud.bozeman.net/s/bZTawN4HL8EWHCQ.
To submit your vote, you can either send an email to me, call me at the number listed below, or
submit the postcard that will accompany the letter that was mailed.
Thank you so much for your participation! Please reach out if you have any questions and please
share with neighbors who may not have received our communications.
Sincerely,
Katherine Maines | Public Works Technician
City of Bozeman | 20 E. Olive St. | Bozeman, MT 59715P: 406.582.2273www.bozeman.net
City of Bozeman emails are subject to the Right to Know provisions of Montana’s Constitution (Art. II,
Sect. 9) and may be considered a “public record” pursuant to Title 2, Chpt. 6, Montana Code
Annotated. As such, this email, its sender and receiver, and the contents may be available for public
disclosure and will be retained pursuant to the City’s record retention policies. Emails that contain
confidential information such as information related to individual privacy may be protected from
disclosure under law.