Loading...
HomeMy WebLinkAboutDevelopment Impact Fee Appeal of Administrative Decision - Nelson Meadows Subdivision CITY OF BOZEMAN DEVELOPMENT IMPACT FEE Appeal of Adminstrative Decision Date Recieved Day .5* Months Year 3gaj Applicant BARTIMCO PROPERTIES/SAWMILL Street/P.O. Box 701 Gold Avenue City/State/Zip Bozeman, MT 59715 Property Owner Same as Applicant Street/P.O. Box City/State/Zip Legal Desc. Nelson Meadows Subdivision Site Address Nelson Road, Bozeman MT 59718 Project Title Nelson Meadows Subdivision #20-457 - Impact Fee Cr Edit Project Desc. Impact Fee Credit Reason for Appeal-additional sheets may be attached if necessary. Please consider this form, with fee, the attached letter and all exhibits as the appeal from the denial of request for impact fees . The identified terms exceed the City ' s regulations , were required by the City of Bozeman and exceed the impacts of the subdivision. Applicant AM DATE Property Owner (('�//- 7� DATE Appeal fee of$500 shall be submitted with this form. Should the appeal be granted the fee will be refunded. SUSAN B. SWIMLEY 1807 West Dickerson, #B Bozeman MT 59715 Attorney and Counselor At Lary Phone: (406) 586-5544 Facsimile: (406) 586-3130 January 4, 2020 Bozeman City Commission Attention: Mike Maas 121 North Rouse Bozeman,MT 59715 RE: Appeal—impact fee credit Request—denial (project#20-457) Dear City Commission: Attached please find the appeal form, $500 fee and documentation of the appeal from the denial of the request for impact fee credit for Nelson Meadows. The subdivider appeals the City's denial of impact fee credit for the following items set out in BarTimCo Properties, LLC December 4, 2020 letter identified as follows: #4 Required dedication of right of way, instead of easement, on northerly boundary of Nelson Meadows Subdivision; #5 Requiring subdivider to construct Nelson Road to collector when local street standard accommodated the Nelson Meadows Subdivision impact; #6 Requiring dedication of Prince Lane,which was not required by City regulation and does not connect to another public street,road or highway; #7 Construction cost of expanding Nelson Road to collector when local street standard accommodated the Nelson Meadows Subdivision impact; #8 Construction cost of Prince Lane,which was not required by City regulation and does not connect to another public street,road or highway; Each impact fee credit item exceeded the City's subdivision regulations and the proportionate impacts of Nelson Meadows Subdivision. Initially,the City denied the request and waited approximately six (6)months to inform the subdivider. The City then reconsidered the request and City Manager Mihelich denied the request on December 18, 2020. The appeal is timely filed. In addition to the information set forth in the attached documentation,the requested impact fee credits were erroneously denied as "project related improvements". The improvements, for which credit is sought,were demanded by various City of Bozeman personnel as subdivision conditions. Each exceeds the minimum improvements needed to service the Nelson Meadows Subdivision project and has been denied for reimbursement of the respective requirement. Prince Lane is an easy example. Prince Lane is not required by any regulation. Block length could have been and was initially approved as a pedestrian/multi—access pathway to meet the block length requirements. City engineering required the installation and dedication of a full city street, which does not connect to any other street,road or highway. The connection will not be made as MRL owns the intervening land and refuses to grant access to the Frontage Road,which is controlled by MDT. MDT denied the request to connect. With all of that information,which was presented, City Engineering staff continued to require the construction and dedication of a street to nowhere,which serves no purpose and exceeds the City's regulations. Thus, determinations of Item Nos. 6 and 8 above were made in error. Additionally, Item Nos. 5 and 7 pertaining to the determination that Nelson Road be constructed to a"collector" standard as opposed to a local street standard was in error. The subdivision as proposed can be adequately accommodated with a local road standard. Nelson Meadows is entitled to the impact fee credit for the difference between the land dedication of the local road with a collector road, because expanding Nelson Road to the "collector"road width serves no purpose and exceeds the City's regulations and requirements for service to the subdivision. Finally, Item No. 4 pertaining to the determination that a 30' dedicated right of way, as opposed to an easement,be dedicated on the northerly boundary of the Nelson Meadows Subdivision exceeded the City's needs. The demand of a right of way rather than easement not only precludes the Applicant's ability to sell approximately 1.41 acres of land,but the right of way itself leads to a dead-end. In email dated July 25, 2018, identified as Exhibit A,the City admitted that the taking of a fee title would not further the needs of the community. Thus,the determination was made in error because it serves no purpose and exceeds the City's regulations. Thank you and we look forward to resolving this issue amicable. Since ely, Susan B. Swimley Encl. Page 2 of 2 BARTIMCO PROPERTIES, LLC December 4, 2020 Mr. Chris Saunders Assistant Planning Director City of Bozeman,MT 20 E. Olive Street Bozeman, MT. 59771 Mr. Jeff Mihelich Bozeman City Manager 121 N Rouse Avenue Bozeman,MT 59715 Nelson Meadows Impact Fee Credit—supplemental application#3 Gentlemen, Thank for you reconsidering our September 17,2019 request to obtain Impact Fee Credits from the City for Nelson Meadow subdivision. As you know, after this initial request submission, Nelson Meadows was not informed that our application had been considered by the City until February 24,2020,when we received,by email,the results of the City's process summarized by Shawn Kohtz's "sticky notes"memo, attached hereto. See Exhibit Kohtz, email to M. Ekstrom 2.20.2020. We have previously provided you all Exhibits referenced herein and will make them available to you upon request. We strongly believe our request is justified and appreciate your reconsideration of these items. Therefore, the following summarizes our amended request for Impact Fee Credits with which we may be able to receive partial reimbursement by selling these credits to the Buyers of Nelson Meadow lots during their application for Building Permit. We propose to use this summary as our agenda for next Thursday's(12.10.20)4:00 pm meeting with you...location of the meeting has vet to be confirmed. We will call you next week to establish the location. To that end, Barnard Construction Company's corporate headquarters (701 Gold Ave) has numerous large conference rooms that would easily provide social distancing. We would be more than happy to host this meeting. The following summarizes our revised request for your consideration. #1 - COB request to increase Water Service from 8" to 16". To facilitate future development in the area, COB requested that Nelson Meadows increase the size of the water service to the development from 8" to 16". In the interim,we have received partial reimbursement from the City in the amount of$339,363 for`oversizing' the water main. Therefore, No Impact Fee Credit regarding this matter is requested. #2 -Additional costs resulting from the City's request to upsize the water line. The costs associated with the replacement and manufacturing of the increased size of PRV were $150,425 and the costs associated with excavating,removing and replacing the connecting tee were an additional$7,831.43 for a total of$158,256.43. We have been informed by Morrison Maierle that we will soon receive a COB check in the amount of$155,000. 701 Gold Avenue, Bozeman, MT 59715 BARTIMCO PROPERTIES, LLC Assuming this information regarding our imminent receipt of a $155,000 from COB is accurate, we will withdraw our request. No Impact Fee Credit regarding this matter is requested at this time. #3 - Additional costs required to be paid to Montana Rail Link(MRL). Because the City of Bozeman failed to obtain access agreements from MRL for COB water and sewer lines that serve the Montana Department of Transportation("MDT")facility and because the City failed to respond to numerous MRL requests regarding the unpermitted pipelines,MRL refused to provide Nelson Meadows with similar permits for water and sewer until obtaining the MRL—City permits. MRL would not grant Nelson Meadows a Utility Occupancy Permit until Nelson Meadows obtained and submitted the Utility Occupancy Permit from the City for the Montana Department of Transportation facility. The City allowed the Montana Department of Transportation facility to install the 8" water line and the 1.5" sewer force main which serves the Montana Department of Transportation facility in the MRL-owned property without the same condition placed on Nelson Meadows. The City required Nelson Meadows to obtain the Utility Occupancy Permit after failing to require the Montana Department of Transportation facility to do so. However, that previous oversight does not obligate the City of Bozeman for impact fees in this situation. No Impact Fee Credit regarding this matter is requested. #4—Land: The 30 foot dedicated right-of-way,instead of an easement, on northerly boundary of the subdivision. The City's demand for land dedication by right-of-way, rather than an easement for potential future public use, precluded our ability to sell fee interest in the subject land. As stated by Tom Rogers in his July 25, 2018 message..."a road on the north property boundary does not further the needs of the community." The applicant sought to provide an easement for this potential extension of the future road system. In July of 2018 the City staff agreed by stating"However,providing an easement on the north boundary is supported, if provided". See Exhibit A email T. Rogers to M. Ekstrom 7.25. 2018. The potential 3/4 mile extension of Stone Gate Drive,from Springhill Road to Nelson Road,in addition to the roadway costs, would necessitate the construction of an $8 million dollar bridge to span over the Gallatin River. However improbable, this extension is not necessary to serve the Nelson Meadows Subdivision. In addition, the land that abuts the right-of-way to the north(which would be required to provide the northerly 50% fifty percent of land for the roadway),is under County jurisdiction and has already improved. Finally,the right-of-way terminates at Nelson Meadow's west property boundary at Sunset Memorial Gardens, a County cemetery which abuts Nelson Meadows and would create a dead-end termination point for the proposed extension. Subdivision Staff Report dated January 24,2019,Engineering Condition 36 required a dedicated right-of-way,which removed the underlying land from the applicant's use and precluded the future sale of the property for site building density, if not development. We believe that the taking of fee title to this land,as compared to the original mutual agreement to provide the City with an easement, combined with the City's admission that the taking does not further the needs of the community, qualifies our request to receive an Impact Fee Credit equal to the value of the land. 701 Gold Avenue, Bozeman, MT 59715 BARTIMCO PROPERTIES, LLC Therefore,the applicant seeks Impact Fee Credits for this dedication of land by right-of-way,rather than by a previously agreed upon easement,consisted of 1.41 acres (61,420 sf). The market cost of land for the right- of-way is currently$8.50/s.f. at 61,420 s.f.=$522,067. #5 — Land: COB required Nelson Road to be constructed to a "Collector" road standard, when subdivision and existing average daily vehicle trips could have been accommodated by a"Local" street standard. The Local street standard is 60 feet right-of-way and the Collector standard is 90 feet right-of-way. The estimated ADT from Nelson Meadows Subdivision at the Frontage Road is approximately 1,910 vehicles per day plus an estimated ADT of 20 vehicles per day on Nelson Road north of the subdivision. Nelson Road has a posted speed limit of 45 mph.At that operating speed,a two-lane street can handle between 6,400 and 7,000 vehicles per day and be estimated to function at LOS C. This is shown in Exhibit 16-16 of the Highway Capacity Manual, 0 Edition:A Guide for Multimodal Mobility Analysis (Transportation Research Board, October 2016). This information was presented in the Nelson Meadows Traffic Impact Study submitted to the City of Bozeman in a Preliminary Plat application 12/20/18. Nelson Meadows Subdivision would have been well served by a Local two-lane street. The City of Bozeman mandated Nelson Meadows Subdivision to build Nelson Road to a"Collector" standard.The applicant is entitled to Impact Fee Credit for the difference between the land dedication area of a Local street and the land required to construct a Collector roadway, which was demanded to accommodate future traffic not currently existing or generated by the Nelson Meadows subdivision. Therefore,the applicant seeks Impact Fee Credits equal to the value of the 15 feet right-of-way (applicant's side of the Collector) demanded by the City and not by easement. The area is 15 feet in width x 2249.13 in length for a total of 0.774 acres (33,737 sf). 33,737 sf x$8.50/sf=$286,765. #6—Land: Extension of Prince Lane from the Intersection at Royal Wolf Way to the subdivision property line— aligned with, but not connected to, the intersection of East Valley Center Spur Road and the Frontage Road (East Valley Spur Connection). This roadway extension was not a project improvement. The developer did not propose this extension, it was not included in our approved preliminaryplan and developer argued against it based upon: 1)the extended roadway creates a dead end street by not connecting to any other street; 2) does not improve the access to the subdivision; and 3)it was not necessary to meet the City of Bozeman requirements for subdivision access or block-length criteria. Our original Pre-application plan did not include the extension of Prince Lane to the East Valley Spur Connection. See Exhibit B, May 2 2018 project concept. Our initial layout, and our stated intent not to connect to the Frontage Road,was based upon our concern for traffic safety and this intersections history of fatal accidents. Our intent not to connect at the East Valley Spur intersection was further supported by conversations with Chris Saunders and MDOT officials during our preliminary planning,annexation and zoning process. Attached are the original versions of the Pre-Application Plan(lst Pre-App Plan Park Place l IX17 051618.pdf and 2nd Pre-App Plan 071918 22x34 rev 2.pdf).See Ex. C. July 18, 2018. As the City knows MRL owns the approximately 9' strip of land between the Nelson Meadows property line and the MDT has an easement(for the Frontage Road).Any future street connection would require an easement across the MRL land to make any connection to the East Valley Spur/Frontage Road intersection. MRL has provided written assurance,based upon traffic safety concerns,that they will not provide the required easement. 701 Gold Avenue, Bozeman, MT 59715 BARTIMCO PROPERTIES, LLC Our original preliminary plat application was submitted without the 600 foot extension of Prince Lane to the Frontage Road and East Valley Center Road Spur Connection. This was designed in concert with City Planning and Engineering staff to develop the street grid network for the project. The original preliminary plat is attached (Original Preliminary PLAT 090418.pdf). [See Ex. D attached hereto] Several months later, during the plat entitlement process, City Engineering's Shawn Kohtz demanded a connection to the East Valley Spur intersection. In response, applicant provided City Engineering with correspondence from both Montana Department of Transportation"MDT"and Montana Rail Link("MRL") stating that both entities would be against any connection at the Frontage Road and East Valley Center Spur intersection. Please see the attached letter from Jean Riley,MDT Exhibit E. BIDT letter dated 10.11.2018 and email from Joe Racicot,General Counsel for(Exhibit F-AI L-05.21.19 Joseph M. Racicot messgge.pdf)for details. In spite of strong opposition voiced by MDT,MRL and the Developer in opposition to the connection of Prince Lane to the East Valley Spur intersection, Khotz and City Engineering required Nelson Meadows to design and construct the extension of Prince Road. Ex. G— email 10.25.2018 and Exhibit H. 12.7.2018 report Nielsen to Rogers—see condition of approval 2. In spite of the above,City Engineering demanded the 600' extension of Prince Lane by right-of-way dedication. This extended roadway: 1) was not a project improvement; 2) served no purpose for traffic flow within the subdivision; 3) created a dead-end road; and 4)MRL had assured us that it will never allow a connection to the Frontage Road. Therefore,we believe it qualifies for an Impact Fee Credit. Based upon the above,the applicant hereby requests Impact Fee Credits for the value of this land by dedicated right-of-way(60 feet wide for a length of 600 feet) for a total area of 36,000 s.f.x $8.50/sf = $306,000. #7- Construction costs -Nelson Road required to be constructed as "Collector"rather than"Local" Street. For the same reasons as the applicant is entitled to Impact Fee Credit explained in land dedication in#5 above,the applicant is also entitled to be reimbursed for the cost of construction for increased roadway area to develop a "Collector" roadway, which was demanded by City Engineering to accommodate future traffic, although not currently existing or projected to be generated by the subdivision. It appeared that City Engineering recognized this was eligible for Impact Fee Credit based upon the below note inserted into the September 16,2019 Impact Fee request provided to the City: 2.20.2020 S. Kohtz denied by stating "This request was presented to the Impact Fee Advisory Committee at the November 5, 2019 meeting, and the Committee did not recommend prioritizing Impact Fee Funds for reimbursement of Nelson Road improvements. This request was also provided to the City Commission on the November 18, 2019 City Commission Meeting. An improvement to Nelson Road was also not prioritized in the City's capital plan. Therefore, no funds are available". Based upon the above, the applicant requests Impact Fee Credits for costs associated with the construction of the additional 15' of roadway width, which was Nelson Meadows' portion of the constructed over-standard Collector roadway in the amount of$232,065.64,the additional construction cost paid to Knife River. 701 Gold Avenue, Bozeman, MT 59715 BARTIMCO PROPERTIES, LLC #8 —Construction Costs —The City's demanded Nelson Meadows extend Prince Lane from the Intersection of Royal Wolf Way to the subdivision's south property line. (600 lineal feet). For the same reasons as referenced in Item#6 above, applicant is entitled to Impact Fee Credits for the cost of construction of the street that: 1)was not contained within the preliminary site plan design,which was approved by the City; 2)was not a desired a project improvement; 3)was not required for to meet subdivision or street length requirements; 4) does not enhance traffic by connecting to another public road; and 5)was not required for site access. Based upon the above, the applicant requests Impact Fee Credits for costs associated with the construction of the additional 36,000 s.f. of roadway which resulted in a Knife River Change Order in the amount of$106,437.50. Additional note: To put our request into economic perspective,the build-out of Nelson Meadows' 69 acres of industrial park will result in over 800,000 s.f. of development (FAR 27%) over the next five years. Using the current formula for Impact Fees and assuming that the City will not increase fees during this time, over $8,000,000 in fees will be generated by subdivision. Thank you for your reconsideration of this request. Nelson Meadows 701 Gold Avenue, Bozeman, MT 59715 BARTIMCO PROPERTIES, LLC July 16, 2020 Mr. Chris Saunders Assistant Planning Director City of Bozeman, MT 20 E. Olive Street Bozeman,MT. 59771 Mr. Jeff Mihelich Bozeman City Manager 121 N Rouse Avenue Bozeman,MT 59715 Nelson Meadows Impact Fee Credit—supplemental application Gentlemen, Thank you for reconsidering our request for Impact Fee credits for Nelson Meadow subdivision that was originally submitted on September 17, 2019. As you know, after the submission, Nelson Meadows was unaware that the application was considered and processed until February 20, 2020, when we received by email the results of the City's process summarized by Shawn Kohtz's "sticky notes"memo, attached hereto. See Exhibit Kohlz- email to M. Ekstrom 2.20.2020. The following summarizes and includes some information that the City already has in its possession but was not originally attached to the impact fee request and we feel might not have been considered. All information previously submitted on the September 17.2019 is requested to be considered together with the additional information included herein. The information below is addressed in the same order as presented previously. #1 —Land: The 30 foot dedicated right-of-way on northerly boundary of the subdivision. The dedication of land right of way, rather than by granted easement, is 1.41 acres(61,420 sf). Impact Fee credit is requested for the cost of right-of-way at$8.50/sf. 61,420 sf x$8.50=$522,066.00. This land dedication, rather than the easement dedicated to public use, is the reason this Impact Fee credit is sought. The extension does not serve Nelson Meadows Subdivision at this time. The lands directly to the north, that would be required to provide fifty percent of the roadway, are already improved and located outside of the City boundary in Gallatin County. The land to the west is not developed. Neither are within the municipal limits. There is no method to anticipate when, or if,these lands will seek annexation. 701 Gold Avenue, Bozeman, MT 59715 BARTIMCO PROPERTIES, LLC The applicant sought to provide an easement for this potential extension of the future road system. In July of 2018 the City staff agreed that the "road on the north property boundary does not further the needs of the community. However,providing an easement on the north boundary is supported, if provided". See Exhibit A, email T. Rogers to M. Ekstrom 7.25. 2018. Subdivision Staff Report dated January 24,2019 Engineering Condition 36 required a dedicated right-of-way,which removed the underlying land from the applicant's use and precluded the future sale of the property for site setbacks and density, if not development. The removal from use combined with the admission that it is not a project improvement,qualifies this land for impact fee credit. #2 — Land: Nelson Road required to be dedicated to a Collector road standard, when subdivision and existing average daily vehicle trips can be accommodated by a local street standard. The Local street standard is 60 feet right-of-way and the Collector standard is 90 feet right-of-way. Because applicant was required to dedicate additional land on one side of Nelson Road, applicant seeks the value of the 15 feet right of way(applicant's side of the Collector). The area is 15 feet width x 2,249.13 length for a total of 0.774 acres (33,736.95 sf). Impact Fee credit is requested for 33,736.95 sf x $8.50/sf=$286,764.07. The estimated ADT from Nelson Meadows Subdivision at the Frontage Road is approximately 1,910 vehicles per day plus an estimated ADT of 20 vehicles per day on Nelson Road north of the subdivision. Nelson Road has a posted speed limit of 45 mph.At that operating speed,a two-lane street can handle between 6,400 and 7,000 vehicles per day and be estimated to function at LOS C. This is shown in Exhibit 16-16 of the Highway Capacity Manual, 0 Edition:A Guide for Multimodal Mobility Analysis(Transportation Research Board, October 2016). This information was presented in our Traffic Impact Study that was submitted to the City of Bozeman in a Preliminary Plat application 12/20/18. As you can see,Nelson Meadows Subdivision would have been well served by a Local two-lane street. The City of Bozeman mandated Nelson Meadows Subdivision to build Nelson Meadows to a Collector standard. The applicant is entitled to a credit for the difference between the land dedication area of a Local street and the increase to a Collector,which was demanded to accommodate future traffic not currently existing or to be generated by the subdivision. #3 —Land: Extension of Prince Lane from the Intersection at Royal Wolf Way to the subdivision property line — aligned with intersection of East Valley Center Spur Road and the Frontage Road (East Valley Spur Connection). This was not a project improvement,was not proposed nor desired by the Developer,and because it does not extend to a connection was not necessary to meet the City of Bozeman requirements for subdivision access. The dedicated right-of-way is 60 feet wide for a length of 600 feet for a total acreage of 36,000 sf. Impact Fee credit is requested for 36,000 sf x $8.50/sf=$306,000. 701 Gold Avenue, Bozeman, MT 59715 BARTIMCO PROPERTIES, LLC Our original Pre-application plan did not include the extension of Prince Lane to the East Valley Spur Connection. See E:xhibil A May 2 2018 project concept. Our initial layout, and our stated intent not to connect to the Frontage Road was based upon our concern for traffic safety and this intersection's history of fatal accidents. Our intent not to connect at the East Valley Spur intersection was further supported by conversations with City of Bozeman's Assistant Director of Planning Chris Saunders and MDOT officials prior to and during our Annexation and Zoning process. Attached are the original versions of the Pre-Application Plan (1st Pre-App Plan Park Place IIX17 051618.pdf and 2nd Pre-App Plan 071918 2204 rev 2.pdo. See Ex. C. July 18, 2018. Our original preliminary plat application was submitted without the 600 foot extension of Prince Lane to the Frontage Road and East Valley Center Road Spur Connection. This was designed in concert with City Planning and Engineering staff to develop the street grid network for the project. The original preliminary plat is attached (Original Preliminary PLAT 090418.pdf). [See Ex. D attached hereto l It was months later, during the preliminary plat entitlement process that City Engineering's Shawn Kohtz demanded the extension to connect to the East Valley Center Spur Connection. In response, applicant provided City Engineering with correspondence from both MDT and MRL stating that both entities would be against any connection at the Frontage Road and East Valley Center Spur intersection. Please see the attached letter from Jean Riley, MDT Exhibit E. MDT letter dated 10.11.2018. and email from Joe Racicot, General Counsel for(Exhibit F-MRL- 05.21.19.Ioseph M. Racicot message.p& for details. In spite of MDT and MRL's not wanting the East Valley Spur Connection, City Engineering required Nelson Meadows to extend Prince Lane to potentially connect to the East Valley Center Spur Connection Ex. G— email 10.25.2018 and Exhibit H. 12.7.2018 report Nielsen to Rogers—see condition of approval 2. As the City knows, MRL owns the approximately 9' strip of land between the Nelson Meadows property line and the MDT easement (for the Frontage Road). Any future street connection would require and easement across the MRL land to allow the development of any connection to the East Valley Center Spur / Frontage Road intersection. The City Engineering required 600' extension of Prince Lane and the dedication of this land is not a project improvement as it serves no purpose for the interior of the subdivision and it was never going to connect to a public road as a subdivision access. Therefore, it qualifies for Impact Fee credit. #4- Construction Costs -Nelson Road required construction as Collector rather than Local Street. This request seeks the costs associated with construction for the additional 15' of roadway,which is the Nelson Meadows portion of the constructed Collector standard. Impact Fee credit requested is $232,065.64. For the same reasons as the applicant is entitled to Impact Fee credit explained in land dedication in#2 above, the applicant is entitled to the cost of construction for the difference between the construct cost of a local street and the increase to a collector, which was demanded to accommodate future traffic not currently existing or generated by the subdivision. It appeared that City Engineering recognized this was eligible for impact fee credit based upon the below note inserted into the September 16, 2019 Impact Fee request provided to the City: 2.20.2020 S. Kohtz denied the request by stating "This request was presented to the Impact Fee Advisory Committee at the November 5, 2019 meeting, and the Committee did not recommend prioritizing Impact Fee Funds for reimbursement 701 Gold Avenue, Bozeman, MT 59715 BARTIMCO PROPERTIES, LLC of Nelson Road improvements. This request was also provided to the City Commission on the November 18, 2019 City Commission Meeting. An improvement to Nelson Road was also not prioritized in the City's capital plan. Therefore, no funds are available". See Kohtz 2.20.20"sticky note" response re Nelson Meadows Impact Fee Request, attached hereto. #5 — Construction Costs — Extension of Prince Lane from the Intersection of Royal Wolf Way to the subdivision property line — aligned with intersection of East Valley Center Spur and the Frontage Road (East Valley Center Spur Connection). Impact Fee credit requested is$106,437.50. For the same reasons as the applicant is entitled to Impact Fee credit as explained in land dedication in#3 above, the applicant is entitled to the cost of construction for the street that is not a project improvement, was not required for the subdivision to meet requirements,does not connect to another public road and was not required for access. 46- Water line increased size. The City recommended by the Impact Fee Advisory Committee (IFAC) and the City Commission approved reimbursement for the amount of$339,363. Reportedly, a cash payment will become available after July 1, 2020, although no reimbursement has been received to date. 97 - Additional costs resulting from the City's upsizing of the water line. The City's recent demand to increase the size of water line from 8" to 16" also resulted in the need to increase the size of the Pressure Reducing Valve ("PRV") and the previously installed tee connection. The costs associated with the increased size of the PRV were$150,425 and the costs associated with excavating,removing and replacing the connecting tee were $7,831,43. Impact Fee credit is requested for a total of$158,256.43. See 07.15.20 Knife River cost summary, attached hereto. #8- Additional costs required to be paid to Montana Rail Link (MRL). Because the City of Bozeman failed to obtain permit agreements from MRL for the water and sewer line crossings that serve the MDT facility and because the City failed to respond to numerous MRL requests regarding the unpermitted pipelines, MRL refused to provide Nelson Meadows with similar permits for water and sewer until obtaining the MRL— City permits. MRL would not grant the Utility Occupancy Permit for Nelson Meadows until and unless Nelson Meadows obtained and submitted the Utility Occupancy Permit for the Montana Department of Transportation facility. The City allowed the Montana Department of Transportation facility to install the 8" water line and the 1.5" sewer force main which serves the Montana Department of Transportation facility in the MRL-owned property without the same condition placed on Nelson Meadows. It seems likely that the City required Nelson Meadows to obtain the Utility Occupancy Permit after failing to require the Montana Department of Transportation facility to do so. However, that previous oversight does not obligate the City of Bozeman for impact fees in this situation. This request is withdrawn. Thank you for your reconsideration of this request. Since•el , N Mead s lis 701 Gold Avenue, Bozeman, MT 59715 From: Tom Rooers To: Matt E.Ekstrom Cc: Kent Merselis;Michael Merselis;Scott Bechtle;"Martina Parrish";Chris Saunders;Martin Matsen Subject: RE:Nelson Meadows Revisions Date: Wednesday,July 25,20181:57:23 PM Attachments: 0magg001.Dna 18 0719 2204 rev 2.odF Mr. Ekstrom, Et.al., We have considered the revised plat based on our conversation last Wednesday.These comments do not constitute a Formal decision of the governing body,only advisory staff comments based on the information we have. New information, MDT determinations, public comment,and other may influence any decisions. Comments: 1. The City agrees that a road on the north property boundary does not further the needs of the community. However, providing a road easement on the north boundary is supported if provided. 2. Access directly onto Frontage Road furthers numerous City policies and is supported by our block and road configuration standards. However,we are cognizant of the issues related to converting any one of the existing access points from an agricultural use to an industrial use. In addition, MDT has indicated they may not support any further interaction with Valley Center Spur. While we do not believe an access is not possible, integrating the modifications shown on the revised pre-plat allow us support a design without direct access to Frontage Road. 3. Please consider aggregating the smallest lots into slightly larger parcels.We have found over many efforts that industrial lots less than one(1)acre are very difficult to design for any functional use.See lots 11-13, Block 2, Lots 17—19, Block 4. 4. Access to the lift station and Lot 3 of Block 5 will be required to a joint access to allow any future development of the lot to meet site plan criteria.You may want to consider an alternative location of the lift station to reduce possible zoning standard challenges during site development. Thank you for your effort and we look forward to working with you to usher the subdivision through the review process. If you have any questions or concern please do not hesitate to contact me. Tom Rogers I Senior Planner I AICP City of Bozeman 120 East Olive St.I P.O.Box 1230 1 Bozeman,MT troaerAftozeman.net 1406.582.2268 EEXHIBIT b D L From: Martina Parrish <martinap@bechtlearchitects.com> Sent:Thursday,July 19, 2018 2:47 PM To:Tom Rogers<TRogers@BOZEMAN.NET> Cc: Kent Merselis<kent.merselis@barnard-inc.com>; Michael Merselis<michael.merselis@barnard- inc.com>;Scott Bechtle<scottb@bechtlearchitects.com>; Matt E. Ekstrom<mekstrom@m-m.net> Subject: Nelson Meadows Revisions Hi Tom- I hope I'm not too late with this drawing. Attached is our revised plan based on our conversations yesterday. We are hoping you can discuss this option with the connectivity to the north at the staff meeting you have. We really appreciate you taking the time to look at this. Please let me know if you have questions. Thank you, Martina Parrish AAIA, LEED Green Associate INBECHTLE N ARCHITECTS 4515 Valley Commons Dr, Ste 201 Bozeman, MT 59718 p. 406.585.4161 City of Bozeman emails are subject to the Right to Know provisions of Montana's Constitution (Art. 11, Sect.9) and may be considered a "public record" pursuant to Title 2, Chpt. 6, Montana Code Annotated.As such,this email, its sender and receiver, and the contents may be available for public disclosure and will be retained pursuant to the City's record retention policies. Emails that contain confidential information such as information related to individual privacy may be protected from disclosure under law. 'REL...' PLAT NELSON MEADOWS SUBDIVISION AREA SUMMARY SITUATED IN THE SE/4 SECTION 22 AND THE NE/4 SECTION 27,TOWNSHIP 1 SOUTH,RANGE 5 EAST, OeER srti�mrers .ak PRINCIPAL MERIDIAN, CITY OF BOZEMAN,GALLATIN COUNTY,MONTANA. a cERTIFIGTEOF DEDICATION OEOrcaTmR atO EASEz1ERr ROTE cERnrIa,TEOF wRECTOR or wsuc woR%s w.�«��vwpw.bw..me..er®+nw..la..e..am°..,..,.a. T+�r,+..a na�n.+.•.t�..vmrarm...�a.a.•.-,.m.rs.a elrrwut.u.3t.rw4 N.MT0..NdrdNv..aetaaba.. mn•Tr M1saw tsev+.+a rgwsw+T era e+r wa.v.[twhw su.n eer¢awbwtwv..u=.d>..Yaemmucw-+.m rr.A•s'+i.we. .m..pM1we..t:mbdnaM1Lr,.rgm.eaar.edbeb,. v+w•+�c+�r. �o.mm.�'beecna'e�«t�bv.w��.v:arw�"•e,�a m ra a.n Irq e.tewa b.at� srrwb..+e rm t c.e r,.a t o a veo-m a s.t.r w un a a�• Srtem R.NNpvtetaM1 WM1.bpsadM1 WN..tpW CERTIF1fltTE OF fAIAPLETIDR OFIMPROVEMENIS rsu.rw,.aea.rrtwaaarw.arowmtrarow.ma�+>IatrsEta e� �L .��y O� _ana min xEtulas.snntFvwbwEuaM1 a.aynxv.�e•Rnm Rd.arTa. >.a.bM1saraaabm.�mnr nuroti-a.q bvu...*+.�b .>�ew�as.xctuREtu.uee.u>vdns+b+.�r�a�aw .ra�a�var. ���e.v..�mm.MTa�..da �.Y.W Hmai+lTmYbtaaq R+9.3 E.*l NbbL W�s.�.olaB®rav rY.Y.N9v�..vavwnf�iw•aiam3�za vtl mvaah[bi Fymcwv cv.ry.I.vrun..te..warTema.eat.n.. �,otidr e./.�+c rw at•craw..bi°ro Er w a R+°�a.a..e�vaw�r.Nmn�dR.iaawn.m•e vabxra�a s�aa..bwbvat�b xwaw.raM1ua.um,..dr,..om..a,e.c+,wsro..°ma.�.e ,�e.,ro"1Y° .snc.�RaraxEr,�.mmgnaw».ebR.aambca.e. �9'�"°` cERTwx•.nTE OFcouRTr rREwSORER inwce.-oxm•tntw..arne.a°unrcb.e. �`' y,p.,�..y I,Iv,�e.el/6a+,.t,rv...:a6r.et rn.e..um,.� Rus.mwy.swnwa.uwts.+larn i ams�bw.�d d+une.nay.m:.a.aarr,r �'�"aM1�"'�9 R..:c °Rsx"'t'cnw.r,9�M1w..rwy.awa,aa.�atatznl.n.� I.,,wmrowene�.,ma.,l...e..t '� ���"et�°n° 2e]tM.vv 8MY.6E.mSv d mtT.Ta fr.iaYaW../b.tln4.lo°r�aMYMlysaWgwd Tt.aM.tl.Mebt Rr.'b vpatrbe F.ex Fpv.v�nLNa µr6ldMp�.Yvn r�'.u.ra.rTRatwxx Eesa[nruszmaew..earoautTnbwvrr ea.d..m�emhM®raamv»� o.et rw mrd mia aa.y.ayTtemaro.Eo..bvmr.maWugmaalTaa�.vYu v+..p®u+mdrpucM.mm.nr�.,�evebreGTdmem,.,f M1 ala.�/aW e�vm+arnd<itao�n+.t,w•nsa cM uN.ena xaoleawerry. bi.aY°N b Cv..I..b..Kverowb.�adr br h Yad aeemv�bw�e.ew rl uhN.o-+-t�Fw.„.p.�'uoH�lYel raeestM o.wa Cv tvnY.lhtra ragrow..kT..W pbvp.t<aba.JobabM1eaHan eArttucOt'RooeTtEa myNbpucweNM1atyda.>mtatmpbv2wma,bma...rgN sm v+.a.•.....r.T0..bpy.o-µacw.Tv.hmrr°ba+0.cv..tdeee.�r Drr TuOw YrE 9W4PE Yt R.l lb.ttwcts TI•.ud.pWtri/p.tivbetAatlbsT{�miavmtwWtN�.b.plka u.mv�u.vr a'� TUONa �wr�rryawt>,. �y.p�_ 2edb W+tr�W bwlue.bLno- a.WvteaaridMulTat/FsvmefbNn�M btMtl�bety. Nvv.un � ry �d�"'��o- CERTIFIGTE OF CLERK ARO RECIXtDER BAFm.COPF0aER1L=S LLC l�Wwtor.Cs4v�a P.mtbder.at tov.I.W°.v.m MehtvVT.arobeydq w. >mi.�u..vyw4ae w M mi0.>di®0..abear_awn mpy. Adv��e.e�M CERIIrMATE OF E%CLUSKNI iRO.H MOtfrNU Om.m°. Ram6dnaelWx.mtlr.Oran Levq.Wunv OEPPATMENt OF ENVYLONtAEMAL WALIIY REVIEW Dnrb mTa mll Ana °:mbs�wt�'minw.u�rw.�aeM1.mviwwrtoMr:n...mol.e w.sam'�w.a°.a"tw•.TM.+"bR�'°i.;'w�"'+as�m�t:sn%n uuu. drowaou.en.p...u..a �n+mue...a„e.a,9.+.bmm�.b.a b ml.l e.Ta a e�r.mwcan..w>,. ro,r,°d e+.�nu.wwu.m d»,.,m.w... oTaem.a•.�..b,w CElZI1FXATE of sunvEroR e zwcwF uwDa...arI.asaw.wim..n.twtns.l..hwT..tM1 na.r�.ywauo.ua+vsmw+m.....t.,.audan,.a.�+e.,..t �a f+sTaiazzue.�.aro�uarteb.�+m�.°�aa,><�i e.�su��lot CwbpNebpwmvn�mMv(ath pe.v.an ttmti0�~Nau°T IJT t.mt9. w.aet. a,a la iv G Wreem Pl°.6aes ur�.laate� rll9aWFGf G>9_ ,Morrison 9 1 �Maierle - aE�LR�RTNu PRELIMINARY PLAT AREA SUMMARYNELSON MEADOWS SUBDIVISION 'bk SITUATED IN THE SE/4 SECTION 22 AND THE NE'/,SECTION 27, °ate TOWNSHIP 1 SOUTH,RANGE 5 EAST, sa k PRINCIPAL MERIDIAN, CITY OF BOZEMAN,GALLATIN COUNTY,MONTANA. 9 cili�I unurr EasFiaEerts `�'"`"""" \ W9`bZL6E M 7W Man f>t�rr tl �`\ II P � �.� � see'•:�reneov,n.uz. I I r l nme "`III... at a >ye p k v,e R 9 P w n'o.e�vEmrzw. $ vie � o uinn"tOw��r ------------------------ - ----- - -- -- ------------- 1 �. mvana I� nnss I � rsnawu�x �� ' I e � • 'I 1 I emi _ —_—_— - �\�� m o•^'. I � 4a �¢ F� �y�•E�°ten 4, ��_\ I I � � Nx AP F B•J � Pa �'t'b .n'�. °�ui. g ame € ene $ • a I 1 ga I 1 ,r �9a I � I I • ans I' ' I raein¢rmmi¢r.�i, � ,ne i i ,,omw[ mvs 6 I GE D O. ncaprmwet 9O 1 `�'u�r aw.¢ranowm w• •fma.64Tt.� a0a ar ra[ ,vn J� � a'�• n�,�.r��. ssa roswc,uowvirnam,r amauWA'narzan, ' mz¢na.a, [m.aeowaaa,iw, nnn BJ ,mMorrison 9===:— �M�� L_ MMaierle �� CONDITIONS OF APPROVAL SHEET NELSON MEADOWS SUBDIVISION SITUATED IN THE SE V4 SECTION 22 AND THE NE'/4 SECTION 27, TOWNSHIP I SOUTH,RANGE 5 EAST, PRINCIPAL MERIDIAN, CITY OF BOZEMAN,GALLATIN COUNTY,MONTANA. .a�+ar•Mrrnuev.eeaMl.nas:.e.emtwaa.r.:aa Nd+w tl5vnsn.ea�.n.a dlhmivbn.+nN pddanyv.aaop.-:..edmy.e,m.q.ebar..a Nbe!W.a9�..�+mot a�ewneta..redtl�o.NwaNao..yebama mau.a.m,rnemax!na^oebdN W aN vmeb.trfav Nbrym da.ew t r.dro�+ai�+ea.u..Nama.+s.+aoM+r.R.�.lb..ww•�n.e..aY�.. WdB�.�Na�.Y.11d.11N.u.Y.fof.{b+cw mrK.f�9�f.aW MNf�.gk6 aY,metl.,a..,d•..a N.mw»...r tr>-r w b,d anwm N�.a.n..ti ea.au. TMYaeN�.Ir.b,prMNmW bNpdaryww.n.ememb.debb.swWvjvnvt ta.�ac.+se.d Tnm strmwr Tnas.ausdm.Tr.auka.}ub iftlb Nfil[abd O.bbt N ay meb m n.yebay tr wa�+q N rn�eeniuw mavwnEs,uC t�.b 4/r ve.y tit N b'wYgv.Afh Ypar lq+.f beMNiRuwru dau¢IBaNBernw Wtytl Cei.sae m�a[9d+{w.waN..-„ µm+le.wnn.,.eeT w.etlbman,.v.wgwamce.*�a .�a.r.c..eb.®aw.nN.w.a.aud.as>a�a>eea�d..raaM.e..�wdde Y'Y+eeEbpmenetr Nme T.r'a.N eiver.e p.o...�<lvetap4 Mv.'+.s��sd..n.r�tl T..s qvcarbr e.a,yrY wrv.ry a tl em W ae Hwn�a.s l.pm-ro b N p�ary a«+ns doam�asmf euma..rov trer>nA'em N en.+sb o+a'+a dwn m N emaF+a d Nvod e.d�b�w;..re.h N W,m�«�+anehbie..!W avo++.�eeYtla.�a.ae.+.m�emld..xw....s.a..t ealN im Nd�abrvemamw.v ��...�+v�aeir�ewmu®.vveagway.b.+a. N9vet wpeartatr.e Dra dryd At4 e.bee m,Nuavegealmy Ta.b.Ft>r.t Iuew.eMm..�.rw dfl.ARCO WeOPEitTFS llC vb rYOMydbmtY.eJ R Nxey Reic'n W tr N s+bd xed]ryd ,mMorrison WO_ MMaierle —"— .--- 1 ti r IL007TRAIL \ --------1 , I LOT 2 LOT 3 O S r ;°LOT 4 LOT 5 LOT 6 3.33 AC I 2.87AC r'ti' 2.76 AC I 3.04 AC I 2.96 AC l 3 4 RI LOT I C-K 5 j B LO K 3 j �! 10.38 AC i i I �?•. r �__ _ � ,ram m_ 1�.. LOT 17 .00 AC 3 j SLOT 1fi r< I LOT 15 LOT 8 LOT 7 .,1 LOT 29 �m; i .95 AC g 2.27 AC I 1.22 AC 1.23 AC 2.61 AC r I� C� $ LOT 18 ` 1.01AC/ 1 .' �/ LOT19 LOT9I h\� /rLOT28 I'. f.� .85AC i � Y 1.95AC - 2.09 AC \ L -- SLOT 20• ..r .85 AC•. +. . - jL®+� ry ' i �� 313 �L�CK 2 ��\ LOT10 ^-, LOT 27 a LOT 14 ' / 1.78 AC 2.o8 AG1.73 AC // \ . 'LOT 26 e\ 1 t, 1.08 AC/ R / LOT 13 LOT 12 LOT 11 , LOT 25� 4 "'I .80 AC I .71 AC I .86 AC t 1.94 AC t\ i' +z LEGEND: _ -.- - _ ' _ 20 1. 'NWE EASEMENT 2.YELLOWSTONE PIPELINE EASEMENT 21 y 3.60'STREAM SETBACK ` 4.50'P.O.W.ROAD LOT 24 = 1.72AC -. 6.SIGN -�r` ' ..1{ 1.1Q AC I ..... . 7,FLASHING YELLOW LIGHT -.- 8.25'TRAIL EASEMENT - _ \r• �- 9.LIFT STATION 3 LOT 22 V r.( Ty` 30.30'TRAIL EASEMENT 1.67 AC ACERAGE SUMMARY: -_ L __�� • 1 TOTALACRES:69.29._ SELLIBLEACRES:59.64 LF ROAD:3,069 FT y 1`T LOT 23 4I 5 ROF LOTS:29 18) 2.7$AC AVERAGE LOT:2.05 AC (4 / DISCLAIMER:THIS DRAWING IS PRELIMINARY AND CONCEPTUAL IN � BLOCK I I NATURE,AND 155UBJECT TO CHANGE / / �. I J 4 FULL LEGAL DESCRIPTION: TRACT IC OF COS 13728 LOCATED IN SECTION 22,T15,RSE,GALLATIN COUNTY,MONTANA TRACT ID OF COS 1372 LOCATED IN SECTION 22,TIS,RSE,GALLATIN COUNTY,MONTANA - Y' THE NORTHEAST QUARTER OF THE NORTHEAST QUARTER(NE114, \� - NEl/4(AND THE EAST HALF OF THE EAST HALF OF THE WEST HALFOF THE NORTHEAST QUARTER(E1/2,El/2,W 1/2,NE1/41 OF SECTION V, TWENTY-SEVEN(27),TOWNSHIP ONE(1(SOUTH,RANGE 5(5(EAST, M.P.M. _ �mD 50 - IFFINI8IT PARK PLACEIJBECHTLE BARNARD INVESTMENTS 0 ARCHITECTS SCALE: 1:100 @ 2204; 1:200 @ 11x17 MAY 2, 2018 i - 0719 revision 15lf li JI)11�1,5(y-� I�]I I5110—{�—YAM---iNIIS� ;1 \ L00(TRAIL �L J BLOCK 5 BLOCK 5 n $LOCK 3 BLOCK 3 BLOCK 3 2 I' BLOCK 6 LOT 2 LOT 3 r1//// LOT 4 LOT 5 LOT 6 \ 2.60 AC j7\� 2.96 AC 3.05 AC 2.95 AC I \ I�',I, 2 94 AC LOT 1 I Y 6.13 AC \ L 3i BLOCK 9) R BLO K 3 a (.III BLOCK 7 � �-—-�c—- - _—3.069 LFJQgp— LOT 27 4.91 AC BLOC(" LOT 16 BLOCK 2 a BLOCK 2 a BLOCK 2 p I I 2.09 AC \$ LOT 15 LOTS R l LOT 7LOT _s BLOC 2,30 AC 1.21 AC 1.24 AC \ I 93 AC aBLOCK4 ° \ T) BLOCK � '\ LOT 18 a LOT 9 l� .85 AC v8 m!> 1.95 AC BLOCK ' ��\ \° BLOCK4� '��! LOT 26 y .\ LOT 19 I 3; L B�OCK®2+r K ^rrrlll� S.OlAC \ � ?C Al a I LO'(10 r .e BLOCK 2 ' 2.08 A6 LOT 14 155,1—(—Ixm---i'�'!to—• BLOCK 8 !h� 1.80 AC LOT 25 \ �' BLOCK 2 'BLOCK 2 BLOCK F Oi 1.80 AC 1�/ a 'a' a LOT 13 I LOT 12 LOT 11 i 6, 9 n C,' 80 AC 71 AC 86 AC BLOCKS w O LOT 24 v5 Pa 1� -- LEGEND: 1 '6� DS AC � I � H,1rr5 1 r I5. -_ g• � 1.2(yNWE EASEMENT O.S.. 2.YELLOWSTONE PIPELINE EASEMENT t I�BLOCK R BLOCK( 3.60'STREAM SETBACK BLOCK 1 4.GO'R.O.W.ROAD ' B - LOT 6.SIGN LOT 23 1.6 �1C 7.FLASHING YELLOW LIGHT 2 1.27 AC. - I �._ 8.25'TflAIIFASEMENT 31 BLOCK 9.UFTSTATION - ?: G.30'TRAIL EASEMENT I LOT 21 ACERAGE SUMMARY: 1.65 AC TOTAL ACRES:69.29-- ' SELLABLEACRES:59.64 ` \l 6 BLOCK LF ROAD:3,069 FT LOT 22 /Y )WE AGE(n 6�� AVERAGEER:2.20AC BZ 7b�K I ♦ / L® L NATURE,AN THIS DRAWINGCHANGE AND CONCEPTUAL IN II / + i NATURE,AND IS SUBIECT TO CHANGE FULL LEGAL DESCRIPTION: -1 � TRAR 1C OF C05 1372E LOCATED IN SECTION 22,T13,RSE,GAt1ATIN % COUNTY,MONTANA Oa TRACT ID OF COS 1372 LOCATED IN SECTION 22,TIS,RSE,GAUATIN COUNTY,MONTAHA Z IF' .r� p THE NORTHEAST QUARTER Of THE NORTHEAST QUARTER(NE1J4, e- NE1/4)ANDTHE EAST HALF OF THE EAST HALT OF THE WEST HALF Of Z� THE NORTHEAST QUARTER(El/2,El/2,WI/2,NEI/4)OFSECTION TWENTY-SEVEN(27),TOWNSHIP ONE(()SOUTH,RANGE 5(51 EAST, i •ny, 1.1.P.IA. 25 riDp 50 - EXHIBIT N d 6� BECHTLE NELSON MEADOWS ' BARNARD INVESTMENTS ARCHITECTS SCALE: 1:100 @ 2204; 1:200 @ 11x17 JULY 18, 2018 mrDr* Montana Department of Transportation Michael T.Tooley,Director 2701 Prospect Avenue Steve Bullock. Governor PO Box 201001 Helena MT 59620-)001 October 11, 2018 Kent Merselis Barnard Inc. 701 Gold Avenue Bozeman, MT 59715 Subject: Park Place Industrial—Frontage Road (P-205) RP 25.452 to 25.924 Traffic Impact Study—Comments Dear Mr. Merselis, The Montana Department of Transportation staff has reviewed the Traffic Impact Study (TIS) concerning the for the Park Place Industrial Development that parallels the Frontage Road (P-205) from Reference Post(RP) 25.452 to 25.924. The MDT staff has the following comments: • The development as no requested any approaches onto P-205. This is consistent with requirements of ARM 18.7.102. The Park Place Industrial Development does not abut the MDT right-of-way, any approach onto P-205 would have to be issued to the Railroad. • MDT concurs with the closure of the approach onto P-205 at Valley Center Spur Road and routing the development traffic onto Nelson Road. This provides for better safety and operations at the improved Valley Spur/P-205 intersection. • Based on the volumes shown in the TIS it is unclear if traffic signal control will be warranted with this development. Please have your consultant review the warrants for traffic signal control and if warranted (and MDT concurs), then traffic control should be provided at the intersection of Nelson Road/P-205. • It appears the site drains entirely away from P-205 and away from the MDT Area Offices on Nelson Road. If the drainage pattern does not change with the proposed development, no additional requirements are necessary. However, if the drainage is redirected at all toward the frontage road or the MDT Area Offices the plan must include stormwater retention. • If there are any changes in the proposed Park Place Industrial Development, a new TIS may be required. An Equal Opportunity Employer Planning 8 Policy Analysis Bureau Rail,Transit and Planning Division Phone:(406)444-3423 T)Y: (800)335-7592 Fax: (406)444-7671 Web Page: www.mdt.mt.gov If you have any questions concerning these comments, please contact me at(406)444- 9456 or email at jriley@mt.gov. Sinc rely, ' �-- Jean A. Riley,P.E. Transportation Planning Engineer Policy, Program&Performance Analysis Bureau Copies: Jeff Ebert, P.E.—Butte District Administrator Duane Liebel,P.E.—Butte District Engineering Section Supervisor Kyle Demars—Bozeman Area Maintenance Chief Tom Eastwood, P.E.—Morrison Maierle Shawn Kohtz,P.E. Bozeman Acting Public Works Director File Kent Merselis From: Joe Racicot Sent: Tuesday, May 21,2019 5:19 PM To: kent.merselis@barnard-inc.com Subject: RE: Nelson Meadows - Montana Rail Link Kent— It was good to speak with you today. I can confirm that Montana Rail Link ("MRL") has no intent on granting an easement to the City of Bozeman for purposes of creating access to the Nelson Meadows subdivision. MRL has worked in conjunction with the Montana Department of Transportation ("MDOT") regarding MDOT's current plans to upgrade the Valley Center Road-Frontage Road intersection. As part of that process, MRL expressed its concerns about the safety risks associated with adding a fourth "leg"to the intersection and is not in favor of such a design. At no time has MRL agreed to grant an easement to the City of Bozeman for purposes of accessing the Nelson Meadows subdivision via the Frontage Road at the intersection of Valley Center Road. If you need additional information, please do not hesitate to contact me. Sincerely, Joseph M. Racicot www.inontanaraii.coni 1 Morrison Maierle engineers surveyors planners scientists Memo TO: Chris Saunders FROM: Matt Ekstrom DATE: September 16, 2019 JOB NO.: 2286.009 RE: Nelson Meadows Subdivision— Impact Fee Credits CC: Kent Merselis, Susan Swimley ❑Urgent ®For Review ❑Please Comment ❑Please Reply ®For Your Use This memorandum continues our initial communication of April 22, 2019 wherein we discussed the process of applying for City Impact Fee credits as a means of reimbursement for those costs incurred in providing the City with increased land contributions and over-standard improvements above and beyond that required by code compliance. In August our contractor, Knife River, presented us with the Change Order that summarized the cost for each over-standard improvement items which provided us with the supporting cost information for this application. The value of the land is based upon a less-than-average summary of comparable lot sales that have already been place in escrow. The attached information is our Impact Fee Credit Application for the Nelson Meadows Subdivision (COB review #18458). Per your email request (see attached email from 9/6/19) we have prepared the following information: 1) LAND: The 30' dedicated Right-of-Way (ROW) on the north boundary of the property. This is preliminary plat condition of approval #36 (see attached conditions of approval). The area contained in this dedication is 1.41 acres (61,420 SF) (30' wide by 2047,78' long). See the attached highlighted section on the Plat located in Appendix A for details. The cost for this ROW is ($8.50 / SF x 61,420 SF) = $522,066.00. The $8.5 / SF is the going price for land in the Nelson Meadows Subdivision. 2) LAND: Nelson Road was built to a Collector road standard per the COB Transportation Plan. The Nelson Meadows Subdivision traffic generation would only dictate that Nelson Road be built to a Local road standard. The Collector road standard requires a 90' ROW compared to 60' ROW forthe Local road standard. Therefore the difference in ROW width on the Nelson Meadows Subdivision property is 15'. The area contained in this dedication is 0.774 acres (33,715 SF) (15' wide by 2249.13' long). See the attached highlighted Page 1 Morrison Nelson Meadows Subdivision—Impact Fee Credits Maierle section on the Plat located in Appendix A for details. The cost for this ROW is ($8.50/SF x 33,715 SF) = $286,581.00 3) LAND: The extension of Prince Lane from the intersection of Royal Wolf Way to the Frontage Road ROW. This ROW contains 0.826 acres(36,000SF)(60'wide by 600' long). See the attached highlighted section on the Plat located in Appendix A for details. The cost for this ROW is ($8.50 /SF x 36,000 SF) = $306,000.00 4) STREET: As was stated above, Nelson Road was built to a Collector road standard per the COB Transportation Plan. Located in Appendix B is the cost difference between building a Local road vs a Collector road. This cost difference is based on Knife River's (general contractor on the Nelson Meadows project) bid dated March 151h, 2019 (bid tabs are in Appendix B). Also located in Appendix B are the road plans for Nelson Road. The cost difference = $232,065.64 (this includes the extra road width, striping, signage, and storm drain). 5) STREET: The extension of Prince Lane from the intersection of Royal Wolf Way to the Frontage Road ROW. The cost of this road extension is included in Appendix C. Also located in Appendix C are the road plans for Prince Lane. The estimated cost to construct this portion of Prince Lane = $106,437.50 6) WATER:A 16"water main was requested by the COB to run through the Nelson Meadows Subdivision. The cost difference between a 16" main and an 8" main (which is what the Nelson Meadows Subdivision project would require) is located in Appendix D. The estimated cost to oversize the water main to 16"=$339,363.00, The 16"water plan sheets are also located in Appendix D. 7) MONTANA RAIL LINK PERMITTING: In our negotiations with Montana Rail Link (MRL) to secure Utility Occupancy Permits for Nelson Meadows project, it became apparent that the existing 8"water main and the 1.5"sewerforce main serving the MDT facility on Nelson Road were never permitted through MRL. In order to get approvals on the Nelson Meadow permits MRL required us submit the after the fact Utility Occupancy Permits for the MDT utilities. The cost for submitting these permits=$3,431.00($1200 of this total is for permit fees to MRL). The permits are attached in Appendix E. Chris, we sincerely appreciate your assistance with our application process and look forward to completing the application over the next few weeks. Please do not hesitate to contact us should you require additional information. NA2286\009\04 Design\Agency Submittal\COB\Tech Memo to Chris Saunders-Impact Fee Credit 090619.docx Page 2 O� Morrison Anin Maierle Memo engineers-surveyors planners-scientists TO: Chris Saunders FROM: Matt Ekstrom DATEE. September 16, 2019 J',B N0.: 2286.009 RE: Nelson Meadows Subdivision - Impact Fee Credits Dent Merselis, Susan Swimley ��Jr�en3 NFor Review 0Please Commend Please Reply gFor Your Use This memorandum continues our initial communication of April 22, 20,19 wherein we discussed the process of applying for City Impact Fee credits as a means of reimbursement for those costs incurred in providing the City with increased land contributions and over-standard improvements above and beyond that required by code compliance. In August our contractor, Knife River, presented us with the Change Order- that summarized the cost for each over-standard improvement items which provided us with the supporting cost information for this application. The value of the land is based upon a less-than-average summary of comparable lot sales that have already been place in escrow. The attached information is our Impact Fee Credit Application for the Nelson Meadows Subdivision (COB review 418458). Per your -email request (see attached email from 9/6/19)we have prepared the following information: 1) LAND: The 30' dedicated Right-of-Way (ROW) on the north boundary of the property. Sticky Note y plat condition of approval #36 (see attached conditions of approval). e skohtz 2/20/2020 11 52 AN-1 ed in this dedication is 1.41 acres 61,420 SF) (30' wide by 2047.78' Land is not eligible for impact fee reimbursement. tached highlighted section on the flat located in Appendix A for details. (r ro ROW is ($8.50 / SF x 61,420 SF) d $522,066.09. The $8.5 /SF is the going price for land in the Nelson Meadows Subdivision. 2) L�,P Nelson road was built to a Collector road standard per the COB Transportation Sticky Note � )n Meadows Subdivision traffic generation would only dictate that Nelson 7 skohtz 220,2020 11:52 AM a Local road standard. The Collector road standard requires a 90' ROW Land is not eligible for impact ROW for the Local road standard. Wherefore the difference in ROW width fee reimbursement. ,. „ .,eadows Subdivision property is '15'. The area contained in-this dedication is 0.774 acres (33 715 SF) (15' wide by 2249.13' long). See the attached highlighted Wage 1 Morrison Nelson Meadows Subdivision—Impact Fee Credits Maierie section on the Plat located in Appendix A for details. The cost for this ROW is ($8.50/SF x 33,715 SF) = $286,581.00 3) LA � The extension of Prince Lane from the intersection of Royal Wolf Way to the Fro)*e Road ROW. This ROW contains 0.826 acres(36,000SF)(60'wide by 600' long). See the attached highlighted section on the Plat located in Appendix A for details. The cost for this ROW is ($8.50 /SF x 36,000 SF) = $306,000.00 4) STREET: As was stated above, Nelson Road was built Sticky Note t Q OB Transportation Plan. Located in Appendix E y skohtz 2i2&2020 t2 07 Pki building a Local road vs a Collector road. This cost diff This request was presented to the Impact Fee Advisory Committee at (general contractor on the Nelson Meadows project) bid the November 5,2019 meeting, are in Appendix B). Also located in Appendix B are the ; and the Committee did not recom- mend rioritizin Im ac ee cost difference = $232,065.64 (this includes the extra r unds for reimbursement o Nel- son Road improvements. This re- storm drain). quest was also provided to the City 5) STREET: The extension of Prince Lane from the inters Commission on the November 18, ---F-7-117 2019 City Commission Meeting. Sticky Note W. The cost of this road extension An improvement to Nelson Road 5 skohtz 2/20/2020 12:07 PM C are the road plans for Prince Lane was also not prioritized in the City's capital plan. Therefore, no Local streets are not eligible for itn- e Lane = $106,437.50 funds are available for this request. pact fee reimbursement. .,.�r main was requested by the COB to Sticky Note skohtz 2/20/2020 12:06 Pfb1 Suision. The cost difference between a 16" main and This request was presented to the Nelson Meadows Subdivision project would require) is Impact Fee Advisory Committee estimated cost to oversize the water main to 16"=$339,3611 on November 5,2019. The Com- mittee forwarded a recommenda- are also located in Appendix D_ tion to support this request to e 7 MONTANA RAIL LINK PERMITTING: In our negotiations Citytommission. The City Com- mission agreed with the request, )ccupancy Permits for Nelson Meadows p and this item was included in the Sticky Note City's fiscal year 2021 capital im- `7 skohtz 2/20/2020 12 06 PM ter main and the 1.5"sewer force main ser provement plan. Reimbursement Not eligible for impact fee reim- permitted through MRL. In order to get ap of water main oversizing will be available on the first day of the fis- bursement. aired us submit the after the fact Utility 0 cal ,year 2021 (July 1, 2020). utilities. The cost for submitting these permits=$3,431.00 fees to MRL). The permits are attached in Appendix E. Chris, we sincerely appreciate your assistance with our application process and look forward to completing the application over the next few weeks. Please do not hesitate to contact us should you require additional information. W2286\009\04 Qesign\Agency Submittal\COB\Tech Memo to Chris Saunders-Impact Fee Credit 090619.docx Page 2