CHANGE ORDER
No. 4
DATE OF ISSUANCE 9/11/20 EFFECTIVE DATE 9/11/20
OWNER City of Bozeman CONTRACTOR Martel Construction
Contract: Bogert Pavilion-GMP Amendment 2
Project: Bogert Pavilion Renovation OWNER'S Contract No. 181901
ENGINEER Morrison Maierle ENGINEER's Contract No. April I It,2019
You are directed to make the following chances in the Contract Documents:
Description: Provide additional roofing membrane for roof area.
Reason for Change order: Documents indicated a smaller roof area then what exists on site.
Attachments: (List documents supporting change)
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price Original Contract Times:
Substantial Completion: 9/9/20
$ 696,714 Ready for final payment: 9/9/20
(days or dates
Net Increase(Decrease)from previous Change Net change from previous Change Orders No. I to
Orders No. 1 to 3 No. 4 : N/A
Substantial Completion: 5
$ 0.00 Ready for final payment: 5
(days)
Contract Price prior to this Change Order: Contract Times prior to this Change Order:
Substantial Completion: 9/14/20
$ 696,714 Ready for final payment: 9/14/20
days or datcs)
Net increase(decrease)of this Change Order: Net increase(decrease)this Change Order:
Substantial Completion: 0
$ 28,600(to be used from Contingency) Ready for final payment: 0
(days)
Contract Price with all approved Change Orders: Contract Times with all approved Change Orders:
Substantial Completion: 9/14/20
$ 696,714 Ready for final payment:9/14/20
(days or dates)
Contractor certifies and agrees that there are no additional costs or claims for extra work, additional time, delays or
omitted items, of any nature whatsoever, associated with the subject change order items,except as identified and set
forth herein and unless expressly stated otherwise in the Change Order. And further,that the price agreed-upon herein
represents the full cost and value for the subject work performed and the materials supplied under the terms of the
contract and that the work quantities and value were properly determined and are correct.
1 by:
F;Docuftned
6- 6bmebt, 9/21/20 DocuSigned by:
CONTRACTOR(Authorized OYffiffl"'. Date
RECOMMENDED BY: APPROVED BY: '
G DocuSigned by:
1� DocuSigned by:
53678dp2)p0(�6C(s1A�F... � (� {(�(
(ENGINEER- Signature) Date O 5(5U ffikd Signature) Date 12/14/2020
Page 1 of 2
N:\0417\083-Bogert Roof\06 Construction\CO(Change Orders)\Change Order#4\COB Change Order Form-Bogert CO#4-Final.doc
DocuSign Envelope ID: FF3ADA3C-6554-439D-9732-D1112B124B85
CHANGE ORDER
INSTRUCTIONS
A. GENERAL INFORMATION
This document was developed to provide a uniform format for handling contract changes that affect Contract Price
or Contract Times. Changes that have been initiated by a Work Change Directive must be incorporated into a
subsequent Change Order if they affect Price or Times.
Changes that affect Contract Price or Contract Times should be promptly covered by a Change Order. The practice
of accumulating Change Orders to reduce the administrative burden may lead to unnecessary disputes.
If Milestones have been listed in the Agreement, any effect of a Change Order thereon should be addressed.
For supplemental instructions and minor changes not involving a change in the Contract Price or Contract Times, a
Field Order should be used.
B. COMPLETING THE CHANGE ORDER FORM
Engineer normally initiates the form, including a description of the changes involved and attachments based upon
documents and proposals submitted by Contractor, or requests from Owner, or both.
Once Engineer has completed and signed the form, all copies should be sent to Owner or Contractor for approval,
depending on whether the Change Order is a true order to the Contractor or the formalization of a negotiated
agreement for a previously performed change. After approval by one contracting party, all copies should be sent to
the other parry for approval. Engineer should make distribution of executed copies after approval by both parties.
If a change only applies to price or to times, cross out the part of the tabulation that does not apply.
Page 2 of 2
N:\0417\083-Bogert Roof\06 Construction\CO(Change Orders)\Change Order#4\COB Change Order Form-Bogert CO#4-Final.doc
DocuSign Envelope ID: FF3ADA3C-6554-439D-9732-D1112B124B85
• MARTEL
1/
CONSTRUCTION INC.
08.24.20 Revised
08.20.20
City of Bozeman
Bozeman, Montana 59715
ATTN: Jon Henderson
Martel COR# 04 R1.1
PROJECT: Bogert Pavilion Repairs
SUBJECT: Roof Area Increase&2x edge
REFERENCE: Quality Roofing Quote
Dear Jon:
We propose to provide all labor, materials, and equipment required to
perform the above mentioned work. Our lump sum quotation is based
on our interpretation of the instructions and scope of work
identified by the Proposal Request(s). If we have misinterpreted this information in any
way(omissions, etc.) please advise us prior to processing this quotation into a
formal Change Order. Other wise, our interpretation shall stand as correct.
We have not been directed to proceed with the work.
At this time, we are hereby requesting 0 calendar days for a time extension
Please note this proposal is valid until 8/28/20. Approval beyond that date may result in additional costs or delays.
Our proposal is based on receipt of a signed Change Order within (25)calendar days.
We are requesting an Adjustment to the Project lump sum for the amount of.• $ 28,600.00
If you have any questions, please call me at(406)600-4057
Sincerely,
MARTEL CONSTRUCTION, INC.
John Kalmon
Enclosure(s)
CC. File
DocuSign Envelope rID:rFF3ADA3C-6554-439D-9732-D1112B124B85 Spreadsheet Report Page z
Bogert Pavilion Renovation-CO#4 Roof Area Increase 8 2x Edge 812512020 10:37AM
Group Phase Description Takeoff Quantity Labor Amount Material Amount Sub Amount Equip Amount Other Amount Total Amount
1 07-0000 THERMAL& MOISTURE PROT.
2 07-5300 Membrane Roofing
3 Change to Untreaded 2x4 at Roof Edge (1.00) ea (181) (181)
4 Add for actual Roof Area vs.Bid Does. 1.00 ea 26,592 26,592
Membrane Roofing 26,411 26,411
THERMAL&MOISTURE PROT. 26,411 26,411
Estimate Totals
Description Amount Totals Rate
Labor
Material
Subcontract 26,411
Equipment
Other
26,411 26,411
General Liability Insurance 255 0.890 %
Gross Receipts Tax 286 1.000 %
Builders Risk 51 0.180 %
Bond 235 0.820 %
Construction Fee 1,362 5.000 %
Construction Contingency
2,189 28,600
Total 28,600
DocuSign Envelope ID: FF3ADA3C-6554-439D-9732-D1 112131241385
CHANGE ORDER No. -1 -
PROJECT: Bogert Pavilion Repairs
QUALITY ROOFING CONTRACTOR: Martel Construction
& SHEET METAL, INC. PROJECT NO. 19-024
490 Cobb Hill Road
Bozeman, MT 59718 DATE: 7/25/2020
CHANGE ORDER# 1
DESCRIPTION: Change perimeter nailer from treated 2x to untreated 2x.
COST OF CHANGE
COST OF TREATED MATERIAL
QUOTE 700'X.699/LF= $ 489.30
COST OF UNTREATED 2X
INVOICE 700'X 44.09/LF= $ 308.64
$ 180.66
ORIGINAL CONTRACT AMOUNT $ 226,725.00
Date Approved CHANGE ORDER AMOUNT $ (181.00)
CO#-1 $ (181.00)
CO#
CO#
CO#
NEW CONTRACT TOTAL
226,544
Sub Contractor Contractor
Quality Roofing & Shee Metal, Inc. Martel Construction
Signed: ---- Signed:
K.C. Barnhardt rKi
Title: President Date: 7/25/2020 Title: Date:
DocuSign Envelope ID: FF3ADA3C-6554-439D-9732-D1 112131241385
CHANGE ORDER No. -2-
PROJECT: Bogert Pavilion Repairs
QUALITY ROOFING CONTRACTOR: Martel Construction
& SHEET METAL, INC. PROJECT NO. 19-024
490 Cobb Hill Road
Bozeman, MT 59718 DATE: 8/11/2020
CHANGE ORDER# 2
DESCRIPTION: Additional Roof Area
COST OF CHANGE
Original Contract amount of$226,725.00 based on 24,640 sf......... $ 9.20 /sf
Acutal roof area with added area to the bottom
of the Arch-Plan area 24742/sf+2,890/sf=27,632/sf
2,890/sf @$9.20/sf $26,592.00
ORIGINAL CONTRACT AMOUNT $ 226,725.00
Date Approved CHANGE ORDER AMOUNT
CO#-1 $ (181.00) $ (181.00)
CO# -2 $ 26,592.00 $ 26,592.00
CO#
CO#
NEW CONTRACT TOTAL $ 253,136.00
Sub Contractor Contractor
Quality Roofing &Sheet etal Inc. Martel Construction
Signed: t/( Signed:
K.C. Barnhardt
Title: President Date: 8/11/2020 Title: Date:
DocuSign Envelope ID: FF3ADA3C-6554-439D-9732-D1112B124B85
Bogert Pavilion
CO#4 Estimate
Project Roof Area 27,632 s.f.
Plan Roof Area 24,742 s.f.
Added Area 2,890 s.f.
cost basis $9.20
CO#4 Proposed $26,591.68
Plan Roof Area
108' end—end of GL Beam arch (1/S200)
3'-8" end of GL Beam to OS of 2x sub-facia (2/S300)
111'-8" TOTAL ARCH LENGTH (111.7')
220'-6" Roof Length grid 1-10
8.75" GL Beam width (2 ends)
3" 2x sub-facia (2 ends)
221'-6" TOTAL ROOF LENGTH (2215)
111.7' Arch x 221.5' Length = 24,742 s.f.TOTAL PLAN AREA
Protect Roof Area
124.75' Arch Length (OS edge 2x sub-facia) x 221.5'Total Roof Length = 27,632 s.f. TOTAL PROJECT AREA
bottom joist to outside of plywood (Martel add)
west side 45" - (32"+3"sub) = 10"
east side 42" -(32"+3"sub) =7"
1.4'x 221.5' Length = 310 s.f.