HomeMy WebLinkAbout20173 Staff Report Staff Report
Southbridge Living
Site Plan Review Application 20173
December 17, 2020
Page 1 of 14
Application No. 20173 Type Site Plan
Project Name Southbridge Living Site Plan
Summary A Site Plan application to allow the construction of two 2-unit and two 4-unit apartment
buildings with associated infrastructure and open space.
Zoning R-3 Growth
Policy
Medium Density Residential Parcel Size 1.6 acres
Overlay District(s) NA
Street Address 1940, 1942, 1948, 1950 Southbridge Drive
Legal Description Southbridge Subdivision, Phase IA, Section 23, Township 2, Range 5 East, Block 5, Lot 1
Owner DA Land Company, 2320 W Main St. Bozeman, MT 59715
Applicant DA Land Company, 2320 W Main St. Bozeman, MT 59715
Representative JDS Architects, Inc., 719 W Mendenhall, Bozeman, MT 59715
Staff Planner Jacob Miller Engineer Cody Flammond
Noticing Public Comment Period Site Posted Adjacent Owners
Mailed
Newspaper Legal Ad
11/14/20 to 12/7/20 11/13/20 & 11/23/20 11/13/20 & 11/23/20 N/A
Advisory Boards Board Date
Recommendation
Development Review
Committee
6/24/20 Adequate
Recommendation Approval with conditions
Decision Authority Director of Community Development Date: 12/17/2020
Full application and file of record: Community Development Department, 20 E. Olive St., Bozeman, MT 59715
Staff Report
Southbridge Living
Site Plan Review Application 20173
December 17, 2020
Page 2 of 14
FINDINGS OF FACT AND APPEAL PROVISIONS CERTIFICATE
A) PURSUANT to Chapter 38, Article 2, Bozeman Municipal Code (BMC), and other applicable sections of Ch.38, BMC, public
notice was given, opportunity to submit comment was provided to affected parties, and a review of the Site Plan described in
this report was conducted. The applicant proposed to the City a Site Plan (SP) to permit the construction of a 4,357 square
foot commercial building with a dentist office in the Stadium Center PUD. The purposes of the Site Plan review were to consider
all relevant evidence relating to public health, safety, welfare, and the other purposes of Ch. 38, BMC; to evaluate the proposal
against the criteria of Sec. 38.230.100 BMC, and the standards of Ch. 38, BMC; and to determine whether the application
should be approved, conditionally approved, or denied.
B) It appeared to the Director that all parties and the public wishing to examine the proposed Site Plan and offer comment were
provided the opportunity to do so. After receiving the recommendation of the relevant advisory bodies established by Ch. 38,
Art. 210, BMC, and considering all matters of record presented with the application and during the public comment period
defined by Ch. 38, BMC, the Director has found that the proposed Site Plan would comply with the requirements of the BMC if
certain conditions were imposed. Therefore, being fully advised of all matters having come before them regarding this
application, the Director makes the following decision.
C) The Site Plan has been found to meet the criteria of Ch. 38, BMC, and is therefore approved, subject to the conditions listed
in this report and the correction of any elements not in conformance with the standards of the Title. The evidence contained in
the submittal materials, advisory body review, public testimony, and this report, justifies the conditions imposed on this
development to ensure that the Site Plan complies with all applicable regulations, and all applicable criteria of Ch. 38, BMC.
On this ______ day of ________________, 2020 Martin Matsen, Director of Community Development, approved with
conditions this Site Plan for and on behalf of the City of Bozeman as authorized by Sec. 38.200.010, BMC. The approval of
this Site Plan shall be effective for twelve (12) months from the date of Plan approval, which is the ______ day of
__________________, 2021. At the end of this period the Director may, at the request of the developer, extend the approval
in accordance with Ch. 38 Art.230, BMC.
D) This Director of Community Development’s project decision may be appealed by filing a documented appeal with and paying
an appeal fee to the Clerk of the Commission for the City of Bozeman within 10 working days after the date of the final decision
as evidenced by the Director’s signature, following the procedures of Sec. 38.250.030, BMC.
DIRECTOR OF COMMUNITY DEVELOPMENT
Staff Report
Southbridge Living
Site Plan Review Application 20173
December 17, 2020
Page 3 of 14
CONDITIONS OF APPROVAL
Please note that these conditions are in addition to any required code provisions identified in this report. Additional conditions
of approval and code corrections are required and will be included with the final report provided to the Director of Community
Development
Recommended Conditions of Approval:
1. The applicant is advised that unmet code provisions, or code provisions that are not specifically listed as
conditions of approval, does not, in any way, create a waiver or other relaxation of the lawful requirements of the
Bozeman Municipal Code or state law.
Staff Report
Southbridge Living
Site Plan Review Application 20173
December 17, 2020
Page 4 of 14
Figure 1: Current Land Use
Staff Report
Southbridge Living
Site Plan Review Application 20173
December 17, 2020
Page 5 of 14
Figure 2: Growth Policy Designation
Staff Report
Southbridge Living
Site Plan Review Application 20173
December 17, 2020
Page 6 of 14
Figure 3: Zoning
Staff Report
Southbridge Living
Site Plan Review Application 20173
December 17, 2020
Page 7 of 14
Figure 4: Site Plan
Staff Report
Southbridge Living
Site Plan Review Application 20173
December 17, 2020
Page 8 of 14
ANALYSIS AND FINDINGS
Analysis and resulting recommendations based on the entirety of the application materials, municipal codes, standards,
plans, public comment, and all other materials available during the review period. Collectively this information is the record
of the review. The analysis in this report is a summary of the completed review.
Plan Review, Section 38.230.100, BMC
In considering applications for plan approval under this title, the Director of Community Development shall consider the
following:
1. Conformance to and consistency with the City’s adopted growth policy
38.100.040 B
Meets Code?
Growth Policy Land Use Urban Neighborhood Yes
Zoning R-3 Yes
Comments: The uses are allowed within the zoning district. The property is within the City’s municipal
service area. Staff finds that the project does contribute to the goals of the growth policy including the
following goals and objectives:
Goal N-1.1: Promote housing diversity, including missing middle housing.
Goal N-1.10: Increase connectivity between parks and neighborhoods through continued trail and sidewalk
development. Prioritize closing gaps within the network.
The moderately sized apartment style units are likely to provide reasonably priced homes near a major
thoroughfare and directly adjacent to parks, with pedestrian connections to the park and adjacent sidewalks.
- Meets Code?
Current Violations None Yes
Comments: There are no current violations on the subject property
3. Conformance with all other applicable laws, ordinances, and regulations
38.100.080
Meets Code?
Conflicts NA NA
Condominium ownership Yes Yes
Comments: No specific conflicts identified.
4. Conformance with Plan Review for applicable permit types as specified in
article 2 Section 38.230
Meets Code?
Site Plan Yes
Comments: The site plan criteria are met with this project. The proposal is compatible and sensitive to the
immediate environment of the site and the adjacent neighborhoods. Architectural design, building mass,
building materials and character are compatible to the immediate environment of the site and
neighborhood.
5. Conformance with zoning provisions of article 3 38.320.100 Meets Code?
Permitted uses 38.310 Two-household, four-household dwelllings Yes
Staff Report
Southbridge Living
Site Plan Review Application 20173
December 17, 2020
Page 9 of 14
Form and intensity standards 38.320 Yes
Zoning
R-3 Setbacks
(feet)
Structures Parking /
Loading
Yes
Front 15’ NA
Rear 20’ NA
Side 5’ NA
Alley NA -
Comments: The proposed two and four-household dwellings are principle uses in R-3. The site conforms
to setback requirements.
Relationship to adjacent properties standards 38.520.030 (light and air access and
privacy) and angled setback plane 38.360.030
NA
Applicable zone specific or overlay standards 38.330-340 NA
Building Height Requirements 38.320.010-.060 Yes
Lot coverage 28% Allowed 40%.
Height 30’8” Allowed 40’ Yes
Comments: A 6:12 pitch roof is the primary roofline proposed. All form and intensity standards for the R-3
district are met.
General land use standards and requirements 38.350 NA
Comments: No Setback encroachments are proposed. No other general land use criteria are applicable.
Applicable supplemental use criteria 38.360 NA
Supplemental uses/type NA NA
Comments: No supplemental use criteria are applicable.
Wireless facilities 38.370 NA
Affordable Housing 38.380.010 NA NA
Affordable housing plan NA
Comments: NA, no wireless facilities or residential uses proposed.
6a(1). Conformance with the community design provisions of article 4:
Transportation facilities and access 38.400
Meets Code?
Street vision Yes Yes
Secondary access Yes
Traffic Impact Study /
LOS
NA Transportation grid
adequate to serve site
Yes Yes
Comments: A traffic study was not required by the Engineering Division.
Street dedication NA Yes
Drive access locations and widths Yes
Number of drive accesses 1, From Southbridge
Drive
Yes
Street easements NA
Special Improvement Districts No Yes
Comments: The vehicular access is from Southbridge Drive.
Parking requirements of 38.540
Required parking nonresidential NA Yes
Required parking residential 24
Staff Report
Southbridge Living
Site Plan Review Application 20173
December 17, 2020
Page 10 of 14
Reductions nonresidential NA
Reductions residential None
Provided parking off street 27
On street parking None
Comments: Parking requirements are met through garages with an additional stacked space per unit and
three parallel spaces in the drive aisle access to the site.
6a(2). Conformance with the community design provisions of article 4:
Pedestrian and vehicular ingress and egress 38.400
Meets Code?
Design of the pedestrian and vehicular circulation systems to assure that pedestrians
and vehicles can move safely and easily both within the site and between properties
and activities within the neighborhood area
Yes
Vehicle accesses to site 1 Yes
Pedestrian access location(s) Yes
Site vision triangles Yes
Fire lanes, curbs, signage and striping Yes
Non-automotive transportation and circulation systems, design features to enhance
convenience and safety across parking lots and streets, including, but not limited to
paving patterns, grade differences, landscaping and lighting
Yes
Crosswalks Yes
Curb ramps Yes
Pedestrian lighting No
Comments: This project site has pedestrian and vehicular access from Southbridge Drive with additional
pedestrian access from North 19th. A pedestrian pathway runs through the property and provides a crosswalk
over the drive aisle.
Adequate connection and integration of the pedestrian and vehicular transportation
systems to the systems in adjacent development and the general community
Yes
Access easements NA NA
Dedication of right-of-way or easements necessary for pedestrian, shared use
pathway and similar transportation facilities
NA`
Comments: The project will construct sidewalks, connecting the residential units to the sidewalk on
Southbridge Drive and on North 19th. The vehicular access provides adequate connection to the adjacent
street, Southbridge Drive.
6a(3) Loading and Unloading areas Meets Code?
Loading and unloading area requirements 38.540.080 NA
Loading and unloading NA NA
First Berth (min. 70 feet
length, 12 feet in width and
14 feet in height)
NA NA
Additional Berths (min. 45
feet length)
NA NA
Comments: NA. No off-street loading berths are required for this use.
6b Community design and element provisions 38.410 Meets Code?
Lot and block standards 38.410.040 Yes
Staff Report
Southbridge Living
Site Plan Review Application 20173
December 17, 2020
Page 11 of 14
Rights of way for pedestrians alternative block delineation NA
Comments: This project meets lot and block standards.
Provisions for utilities including efficient public services and utilities 38.410.050-060 Yes
Municipal infrastructure requirements Yes
Easements (City and public utility rights-of-way etc.) Yes
Water, sewer, and stormwater Yes
Other utilities (electric, natural gas, communications) Yes
CIL of water Yes
Comments: All utilities proposed are adequate to serve this project. CILWR has been paid for this lot.
Site Surface Drainage and stormwater control 38.410.080 Yes
Location, design and capacity Yes
Landscaping per 38.410.080.H Yes
Comments: An infrastructure design report was included with this project and was reviewed by engineering.
Grading 38.410.080 Yes
Maximum 1:4 slope requirements met NA
Comments: Reviewed and approved by Engineering Division.
6c. Park and recreation requirements 38.420 Meets Code?
Enhancement of natural environment NA
Wildlife habitat or feeding area preservation NA
Maintenance of public park or public open space access NA
Park/Recreational area design NA
Parkland Cash-in-lieu for maximum known density not to exceed
12 units/acre (ac.).
NA
__ ac. X __ units/ac. X 0.03 ac.= __
Cash donation in-lieu(CIL) NA NA
Improvements in-lieu NA NA
Comments: Parkland was provided at subdivision.
7a-c. Conformance with the project design provisions of Article 5,
Compatibility, Design and Arrangement
Meets Code?
Compatibility with, and sensitivity to, the immediate environment of the site and the
adjacent neighborhoods and other approved development relative to architectural
design, building mass, neighborhood identity, landscaping, historical character,
orientation of buildings on the site and visual integration
Yes
Block Frontage Standards 38.510 Yes
Building Design 38.530 Yes
Location and design of service areas and mechanical equipment 38.520.070 Yes
Comments: Individual totes will be used for trash service. The electrical and gas meters are not visible from
internal pathways or sidewalks.
Design and arrangement of the elements of the plan (e.g., buildings, circulation, open
space and landscaping, etc.) so that activities are integrated with the organizational
scheme of the community, neighborhood, and other approved development and produce
an efficient, functionally organized and cohesive development
Yes
Staff Report
Southbridge Living
Site Plan Review Application 20173
December 17, 2020
Page 12 of 14
Relationship to adjacent properties 38.520.030 Yes
Non-motorized circulation and design 38.520.040 Yes
Vehicular circulation and parking 38.520.050 Yes
Comments: This project provides internal pathways connecting to all street frontages, internal open spaces,
residential units and to the adjacent park south of the property.
Design and arrangement of elements of the plan (e.g., buildings circulation, open
space and landscaping, etc.) in harmony with the existing natural topography, natural
water bodies and water courses, existing vegetation, and to contribute to the overall
aesthetic quality of the site configuration
Yes
Site Planning and Design Elements 38.520 Yes
Comments: Project conforms to requirements.
7d. Conformance with the project design provisions of Article 5, Landscaping
including the enhancement of buildings, appearance of vehicular use, open
space and pedestrian area and the preservation of replacement of natural
vegetation
Meets Code?
Submittal requirements for landscape plans 38.220.100 Yes
Mandatory landscaping 38.550.050 Yes
Yard Yes
Additional screening Yes
Parking lot screening NA
Interior parking lot landscape NA
Off-street loading spaces screening NA
Street frontage Yes
Street median island NA
Acceptable landscape materials Yes
Protection of landscape areas Yes
Irrigation: plan, water source, system
type
Yes (underground)
Trees for residential adjacency NA
City rights-of-way and parks Yes
Tree plantings for boulevard ROW, drought-
resistant seed
NA
Public ROW boulevard strips NA
Irrigation and maintenance provisions for ROW NA
State ROW landscaping NA
Additional NA NA
Fencing and walls NA NA
Comments: Additional screening is provided between the open space areas and the ground floor
residential units. All boulevards and boulevard trees were constructed with the subdivision public
improvements.
Site planning and design required 38.520 Yes
Pedestrian area landscaping, including pathways and internal circulation 38.520.040 Yes
Internal roadway landscaping 38.520.050 NA
Open space landscaping 38.520.060 Yes
Service area and mechanical equipment landscaping and screening 38.520.070 NA
Staff Report
Southbridge Living
Site Plan Review Application 20173
December 17, 2020
Page 13 of 14
7g. Conformance with the project design provisions of Article 5, Signage
38.560
Meets Code?
Allowed (sq. ft)/building NA NA
Proposed (sq. ft) NA
Comments: No signage is currently proposed.
8a-c. Conformance with environmental and open space objectives in articles 4-
6 Meets Code?
Enhancement of natural environment: Integrated stormwater, LID, removal of
inappropriate fill
NA
Grading Yes
On-site retention/detention Yes
Comments: Project meets requirements.
Drainage design Yes
Stormwater maintenance plan 38.410.030.A Yes
Stormwater feature: landscaping amenity, native species, curvilinear, 75% live
vegetation
Yes
Comments: This project utilizes two stormwater retention ponds, constructed to standard.
Watercourse and wetland protections and associated wildlife habitats NA
If the development is adjacent to an existing or approved public park or public open
space area, have provisions been made in the plan to avoid interfering with public
access to and use of that area
NA
Comments: NA
9. Conformance with the natural resource protection provisions of articles 4-6 Meets Code?
Watercourse setback 38.410.100 NA
Watercourse setback planting plan NA
Floodplain regulations 38.600 NA
Wetland regulations 38.610 NA
Comments: Project meets requirements. The two open space areas are adequately landscaped.
7e. Conformance with the project design provisions of Article 5, Open Space Meets Code?
Open Space Section 38.520.060 Yes
Total required 1800 sf Yes
Total provided 2160 sf Yes
Comments: Open space is provided for residents through a combination of fenced yards for the ground
level units, and balconies and shared open space for the upper levels. Shared open space areas are
amenitized with benches and landscaping.
7f. Conformance with the project design provisions of Article 5, Lighting
38.570
Meets Code?
Building-mounted lighting (cutoff and temperature) Yes
Site lighting (supports, cutoff and temperature) NA
Minimum light trespass at property line Yes
Comments: The proposed building mounted lighting meets standards. Wall mounted lighting meet full
cutoff requirements.
Staff Report
Southbridge Living
Site Plan Review Application 20173
December 17, 2020
Page 14 of 14
Comments: NA
10. Other related matters, including relevant comment from affected parties
38.220
Meets Code?
Public Comment Yes Yes
Comments: Two public comments were received for this project. Both were related to concerns about on-
street parking generated through this project. They both mentioned that the site plans were not available
through the Community Development Viewer, so this project was re-noticed to allow for adequate review
time of application materials.
This project conforms to parking requirements and was provided with adequate time for public comment.
11. If the development includes multiple lots that are interdependent for
circulation or other means of addressing requirement of this title, whether the
lots are either: Configured so that the sale of individual lots will not alter the
approved configuration or use of the property or cause the development to
become nonconforming OR Are the subject of reciprocal and perpetual
easements or other agreements to which the City is a party so that the sale of
individual lots will not cause one or more elements of the development to
become nonconforming. 38.410.060
Meets Code?
Subdivision exemption NA NA
Required Easements Yes Yes
Reciprocal access and
shared parking easement
NA NA
Mutual access easement
and agreement
Yes Yes
Comments: The required drainage and access easements were provided.
12. Phasing of development 38.230.020.B including buildings and
infrastructure
Meets Code?
Phasing No # of phases 1 Yes
Comments: This project will be constructed in one phase.