INFRASTRUCTURE
INFRASTRUCTURE STRATEGIES & SUMMARIES
WATER RIGHTS
CASH-IN-LIEU TABLE
WATER WELL PROPOSED FOR IRRIGATION
CONCURRENT CONSTRUCTION PLAN
SECTION 5
5.00
5.01
5.02
COTTONWOOD + IDA
PUDF SUMITTAL || APRIL 2019
page 79
BELOW-GRADE PARKING GARAGE
Two of the residential buildings, the office building, and a portion of the public open space are
constructed over a parking garage.
96 Parking spaces
Entry & exit to the parking garage is from Aspen Street in order to direct traffic to Wallace Avenue,
and reduce traffic impacts on Cottonwood Street and Ida Avenue.
EAST ASPEN STREET
The entire right-of-way adjacent to the property is currently undeveloped. The proposal is to construct
a roadway, with sidewalk and other street improvements along the north and south side of the right-
of-way. In addition to the parking garage entry, the street will accommodate several parallel parking
spaces, and a loading zone.
EAST COTTONWOOD STREET
The Northern half of the right-of-way adjacent to the project site will be improved. The intention is
for the proposed improvements to match the character of recent improvements directly across the
street - with sidewalk, street trees, and diagonal parking.
NORTH IDA AVENUE
The right-of-way adjacent to the project site will be improved with sidewalk, street trees, curb,
and parallel parking. Improvements will continue East across the Ida right-of-way up to, but not
including, the opposite curb.
PEDESTRIAN ACCESS
The 20’ fire lane will serve as a through-block pedestrian connection between the active Cottonwood-
Wallace Intersection, and the open green space at Aspen Street.
PUBLIC OPEN SPACES
The main open space on the site takes advantage of the distinctive Misco Mill and the renovated
on-site building to create a plaza suitable for hosting food vendors, farmer’s markets, and similar
community events; as well as daily informal use by the office tenants, residents, and artisan
community. Public services, such as event storage and restrooms will be located in the renovated
building at the Southwest corner of the site.
SITE ACCESSIBILITY
INFRASTRUCTURE STRATEGIES & SUMMARIES
CONTINUED
COTTONWOOD + IDA
PUDF SUMITTAL || APRIL 2019
page 80
PARKING
The parking demand will be met primarily by the 96 space parking garage located partially
below-grade across most of the site. With nearby bus stops, and downtown within easy
walking and biking distance, we are able to provide residents and tenants with a community
that is less reliant on their cars for daily commuting and errands. With ample on-site bike
parking facilities, and a modest investment in carshare services, the reduced demand for
parking is crucial to creating a more attainable - and more diverse - set of housing options.
There will be accessible path of travel to commercial parking lot at Wallace & Aspen street.
RESIDENTIAL PARKING STUDIOS 1-BDRM 2-BDRM UNITS DEMAND
COUNTS 41 33 18 92
CURRENT CODE RATIO 1.25 1.5 2 137.5
PROPOSED REDUCTION RATIO 1 1.25 2 119.0
BIKE PARKING CODE 14
PROVIDED 134
NON-RESIDENTIAL PARKING NON-RESIDENTIAL AREA
AREA NET
SF
USE*RATIO DEMAND
BUILDING 4 3,573 PRIMARILY OFFICE 250 14.30
BUILDING 5 1,200 RESTAURANT (INDOOR)50 24.00
700 RESTAURANT (OUTDOOR)100 7.00
BUILDING 6 21,181 PRIMARILY OFFICE 250 84.72
16 COVERED BIKE AND LOCKERS -10%(8.47)
CURRENT CODE 121.55
PROPOSED PER PUD
REDUCTION
40%72.9
PARKING PROVIDED
ON SITE PARKING GARAGE 96 PRIMARILY RESIDENTIAL
OFF SITE LEASE 72 FOR NON-RESIDENTIAL USE WITHIN 800 FEET OF
ENTRANCE(S)
ON STREET 38 COUNTED TOWARD RESIDENTIAL ONLY
COVERED BIKE PARKING 80
ON SITE BIKE PARKING 54
TOTAL BIKE PARKING 134
TOTAL PROVIDED 208
TOTAL PER PUD REQUESTS 190
COTTONWOOD + IDA
PUDF SUMITTAL || APRIL 2019
page 81
FIRE PROTECTION
Buildings 1 and 6 will have floors and/or roof decks at least 30 feet above the adjacent road where fire
equipment will have access. We are proposing standpipe systems in the exit stairs at the North end of each
of these buildings.
All of the buildings and the below-grade parking garage will be fully-sprinklered per NFPA-13, with the
exception of the single-story open-air existing building (building 5).
The site is surrounded by public right of way on the North, South and East sides. The West side of the site
will be maintained as a 20 feet wide fire equipment access route. Each side of the project will have at least
one direct and readily accessible access point from the street or on-site fire access route onto the top of the
parking garage, which functions as the ground floor for each of the buildings.
INFRASTRUCTURE STRATEGIES & SUMMARIES
CONTINUED
SOLID WASTE COLLECTION
Unit owners are responsible for placing the trash recepticals in designated locations on pick-up day and
returning them to the enclosed locations at the end of the same day.
A Trash room A serves the 64 studio and one-bedroom apartments in buildings 1 and 2. The 34 units
on the upper floors have access to trash and recycling chutes that terminate in a trash room at
street level. The trash chute will have a compactor, while the recycling chute will feed directly into a
dumpster.
The trash room is 300 sf (18 feet x 17 feet), and can accommodate up to four 4-yard dumpsters,
roughly 6 feet x 4 feet each, including the two at the chutes.Building staff will use a pallet jack to
move the dumpsters from the trash room to Aspen Street for pick-up, and will place them back
in the trash room once they’ve been emptied. The 18 units on the ground floor will use a separate
small trash room with four standard curbside bins. Those bins will be set out and retrieved by
building staff.
B Trash room B serves the 28 one- and two-bedroom units in buildings 3 and 4, as well as the
commercial spaces in building 4. Residents and commercial tenants will place their trash and
recycling into standard curbside bins. The bins will be put out and retreived by building staff.
The trash room is 290 sf (21 feet x 14 feet) and is able to accommodate two 4-yard dumpsters for the
commercial tenants, and six curbside bins for the residential tenants. Building staff will place the
dumpsters and bins at Cottonwood Street for collection, and return them to the trash room when
they’ve been emptied.
C Trash room C serves the office building (building 6), with up to 90 employees. Janitorial staff will
collect trash and recycling from the offices, and place it in dumpsters and/or curbside bins. The
dumpsters and/or bins will be put out and retreived by building staff.
The trash room is 280 sf (15 feet x 19 feet), and able to accommodate up to four 4-yard dumpsters,
roughly 6 feet x 4 feet each.
D Trash room D serves building 5 and cafe staff will collect trash and recycling and place it in a
dumpster or curb side bins. The bins/dumpster will be out by staff and retrieved by staff. The trash
enclosure is 10 feet x 10 feet and able to accomodate a four yard dumpster and recycling bin.
COTTONWOOD + IDA
PUDF SUMITTAL || APRIL 2019
page 82
WATER RIGHTS
WATER WELL PROPOSED FOR IRRIGATION
An existing well, located approximately in the Northeast corner of the project area, is proposed to be used for
landscaping irrigation. We have had discussions with the department of natural resources and conservation
and we understand that, as the project progresses, this use of the existing well is contingent upon providing
proof of water rights. See Appendix G for letters and communications with DNRC in Well Water Right
Usuage Appendix.
USE USE AREA SF RESIDENTIAL
UNITS
UNIT WATER
DEMAND GAL/YR/1,000 SF
UNIT WATER
DEMAND AF/RESIDENTIAL
UNIT
ESTIMATED WATER
VOLUMN
GAL / YR AF / YR
APARTMENT UNITS --92 --0.124 3,717,308 11.41
RESTAURANT 2,138 --165,000 --352,770 1.08
ARTISAN MANUFACTURING
(ASSUMED RESTAURANT) 3,563 --165,000 --587,895 1.80
OFFICE 27,580 --10,000 --275.800 0.85
IRRIGATION N/A (EXEMPT WELL FOR
IRRIGATION WATER)
TOTAL 15.14
LESS CILWR CREDIT FROM 0.00
LESS HISTORICAL ANNUAL AVG METERED USE -0.07
NET VOLUME FOR CILWR 15.07
FINAL CILWR FEE - 18516 COTTONWOOD + IDA PUD @ $6,000 / AF $ 90,427
CASH-IN-LIEU TABLE
COTTONWOOD + IDA
PUDF SUMITTAL || APRIL 2019
page 83
CONCURRENT CONSTRUCTION PLAN
The Cottonwood & Ida project includes the construction of five new buildings and renovation of one existing
building with mixed use of commercial, multi-family residential and office/retail. Two of the proposed
buildings of which will be built on top of a podium above a parking garage. A courtyard/plaza, interior to
the site, will be a publicly-accessible space. These buildings will be constructed in a single phase. Off-site
infrastructure improvements will be necessary in conjunction with the aforementioned site improvements.
The Developer proposes concurrent construction of off-site infrastructure improvements in order to satisfy
the infrastructure needs of the project (water, sewer, storm drain and transportation) while progressing the
construction of the on-site parking structure, buildings and appurtenances. Full Concurrent Construction
Plan is provided in Appendix R.